MAGNOLIA TLP is a 2004 industrial vessel. The Coast Guard has recorded 46 inspections since 2003, most recently in January 2026, along with 38 deficiencies.

Records from 2003 to 2026. Most recent: inspection, 6 January 2026.

Built
2004
Last inspected
6 January 2026
Documentation
Not in the documentation file of 10 September 2026
Controls
None recorded without a removal date

Identity

WDB4136
608232
Flag
UNITED STATES
—
Maury page id
psix-608232

Inspections, by type

Years with a record 22 calendar years (2003–2026)
The 46 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Offshore class in Maury's sources begin in 1978.

Documentation record

Tonnage as PSIX records itNot recorded
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.

Radio station licence

No FCC ship-station licence is recorded against this Official Number in the file of 6 September 2026. That is a fact about the licence file, not about the radio.

A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.

Inspection history · 46

6 January 2026 Annual Inspection · Administrative Inspection
Physical examination · USCG Heartland District (ocs) · USCG Heartland District (CGD-H) · Activity 8290817
1 July 2025 Administrative Inspection · Deficiency Check
Physical examination · Outer Continental Shelf National Center of Expertise · Activity 8171972
19 May 2025 Deficiency Check · Administrative Inspection
Physical examination · USCG Heartland District (ocs) · USCG Heartland District (CGD-H) · Activity 8170394
30 January 2025 Administrative Inspection · Deficiency Check
Physical examination · USCG Heartland District (ocs) · USCG Heartland District (CGD-H) · Activity 8077762
21 October 2024 Deficiency Check
Physical examination · USCG Heartland District (ocs) · USCG Heartland District (CGD-H) · Activity 8027146
20 August 2024 Administrative Inspection · Deficiency Check
Physical examination · Outer Continental Shelf National Center of Expertise · Activity 7985645
29 July 2024 Deficiency Check
Physical examination · Outer Continental Shelf National Center of Expertise · Activity 7969769
11 July 2024 Deficiency Check
Physical examination · Outer Continental Shelf National Center of Expertise · Activity 7956588
24 June 2024 Annual Inspection
Physical examination · Outer Continental Shelf National Center of Expertise · Activity 7946932
9 January 2023 Deficiency Check · COI Inspection
Physical examination · USCG Heartland District (ocs) · USCG Heartland District (CGD-H) · Activity 7619007
7 July 2022 Administrative Inspection
Administrative · USCG Heartland District (ocs) · USCG Heartland District (CGD-H) · Activity 7500179
26 October 2021 Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7341518
30 September 2020 Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7069312
16 October 2019 Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6835630
9 August 2019 COI Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6781988
29 October 2018 In-Service Inspection · Administrative Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6570544
10 September 2018 Administrative Inspection
Administrative · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6538698
31 August 2018 Damage Survey · Administrative Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6528309
15 August 2018 Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6514960
5 June 2018 In-Service Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6443127
21 August 2017 Deficiency Check
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6275382
15 August 2017 Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6243923
28 July 2016 Periodic Inspection · MTSA Verification
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5923372
17 September 2015 Administrative Inspection · In-Service Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5730924
2 June 2014 Internal Structural Exam · In-Service Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4877756
30 July 2012 Deficiency Check · Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4396764
6 June 2012 In-Service Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4336786
21 February 2012 Administrative Inspection · In-Service Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4250800
6 February 2012 Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4239430
7 December 2011 Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4209674
28 January 2011 Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3937127
18 November 2010 Deficiency Check · Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3892686
10 November 2010 Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3891906
25 October 2010 Administrative Inspection
Administrative · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3880570
18 October 2010 Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3863164
28 July 2009 Plan Review (Other than "T")
Administrative · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3549558
21 October 2008 Annual Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3348977
16 April 2008 Administrative Inspection
Administrative · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3185724
31 October 2007 Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3090533
12 September 2007 Annual Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3056143
21 February 2007 In-Service Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 2861910
1 February 2006 Annual Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 2545896
5 August 2004 Deficiency Check · Construction Oversight · COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 2103613
4 February 2004 Deadweight Survey · Construction Oversight · Inclining Experiment
Physical examination · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 2092048
29 January 2004 Administrative Inspection
Administrative · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1997002
10 February 2003 Construction Oversight
Physical examination · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 1968016

Deficiency record · 38

07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 27 June 2024 Resolved
Fire boundaries are to be maintained at all times. The following practices were observed: a) Quarters stairwell doors were tied open at multiple levels upon arrival. While temporary and quickly corrected, it appears to be a common occurrence with non-magnetic tie-backs in place at multiple levels. b) Dumbwaiter fire door in the Laundry Room to be tied in the open position (non-magnetic hold-back). c) Numerous items were placed beneath the Galley/Messdeck and Scullery/Messdeck fire shutters during meal times that would prevent the shutters from fully closing during automatic activation, as designed. Maintain fire boundaries in accordance with unit’s design and fire control plan to afford proper protection against the spread of fire through vertical and horizontal zones. 46 CFR 108.143(g)(2) & § 108.137
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 27 June 2024
Resolved 27 June 2024
Resolution: Boundary maintenance practices restored for all observed fire boundary discrepancies.
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 27 June 2024 Resolved
Means must be provided to secure openings in spaces protected by a CO2 fire suppression system. a) A temporary portable air conditioning unit has been installed in the Emergency Diesel Generator (EDG) MCC Room to aid in cooling while the installed cooling unit is non-functional (currently on order). The added exhaust penetration contains no way of securing the opening and will reduce the effectiveness of the suppression system. Remove temporary exhaust and repair enclosure penetration to match original design. b) Intake and exhaust louvers for the EDG and Auxiliary Generator enclosures appear to be in disrepair. Recent 3rd Party service report contains no indication of testing the louvers to verify proper closure with the inspection of the CO2 fire suppression system. Prove proper operation of enclosure louvers. c) The Auxiliary Generator enclosure south doors are rotted and will not completely close, rendering the CO2 suppression system for the enclosure ineffective. Repair/replaced wasted enclosure panels/doors as necessary to restore boundary integrity to the enclosure. d) Wasted/holed areas of Main Gas Turbine (MGT) C enclosure to be repaired prior to placing MGT C back into service to ensure effectiveness of the CO2 fire suppression system. 46 CFR 108.455(b) & (c)
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 27 July 2024
Resolved 30 June 2025
Resolution: Doors replaced and enclosure work completed IAW with deficiency requirements. Photographic documentation provided and uploaded.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 27 June 2024 Resolved
Fire hose reels throughout the facility shall be maintained in good condition at all times. Observed several hose reel stations throughout the facility to have broken grease fittings for the hose reel swivel, or apparent lack of lubrication to reels with the grease fitting in place. Hose reel stations on the Main Deck (#5) and Heli-Deck west stairs have a seized swivel and unthread the swivel-to-pipe nipple connection when the reel is unspooled. 3rd party fire servicing report completed during May2024 doesn't list any concerns with the reels themselves
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 11 July 2024
Resolved 11 July 2024
Resolution: Received satisfactory documentation noting all reels serviced, with new grease fittings installed. Three replacement swivels ordered (OR# 347746). Work completed by crew 30Jun2024.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 27 June 2024 Resolved
Each fire detection system on a unit must show the zone where the fire has been detected. The Fireboy® detection system for the EDG enclosure was showing internal and ground trouble alarms. Prove proper operation of system.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 11 July 2024
Resolved 11 July 2024
Resolution: Received satisfactory documentation. Troble alarm cleared. Changed out one bad strobe light, one switch and EOL (End-of-Line) resistor. Work completed 30Jun2024.
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 27 June 2024 Resolved
Each fixed fire extinguishing system must have posted operating instructions. The South MCC Room FM-200 operating instructions placard is missing. Replace same. 46 CFR 108.631(b)
Condition: Damaged By Earlier Event
Action required: 50 - Rectify deficiencies w/in 30 days
Due 27 July 2024
Resolved 11 July 2024
Resolution: Received satisfactory documentation. Operating instructions posted with new sign/placard to be made.
11 - Life Saving Appliances › N/A - No Subsystem › Lifeboats
Issued 27 June 2024 Resolved
Lifeboats and their equipment are to be maintained in good condition at all times. Lifeboats (LBs) were serviced by the Original Equipment Manufacturer (OEM) on 15Jun2024; however, the following discrepancies were noted: a) The storage compartment in LB 1 containing lifeboat outfit/loose equipment contained several inches of water that had damaged some of the equipment. Dry stowage compartment and replace damaged/deteriorated equipment. b) LBs 3 and 4 were both found to have water in the bilge area where the self-contained air system cylinders are stowed. LB air cylinders were also found to be stowed in a manner where there was cylinder-to-cylinder or direct steel-to-steel contact with the stowage brackets that could accelerate corrosion of the compressed air cylinders. Dry compressed air cylinder stowage area for LBs 3 & 4. c) LB 3 has a defective compressed air regulator (noted on the May2024 servicing report). Replace same.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 July 2024
Resolved 11 July 2024
Resolution: Received satisfactory documentation. LB1 storage compartment dried and replacement equipment ordered (OR# 347958). LB3 & 4 bilges/air cylinder stowage dried. ARMS (OEM) contacted about air cylinder bracket isolators. LB3 air regulator replaced 03Jul2024.
09 - Working and Living Conditions › 092 - Working Conditions › Ventilation (Working spaces)
Issued 27 June 2024 Resolved
Each enclosed space must be ventilated. The majority of the supply vent screens throughout the SW and SE hull columns were observed to be partially or mostly blocked, reducing ventilation flow in the active columns. The intake guard for the SE upper column exhaust fan is corroded and no longer providing protection for/against rotating machinery. Clean all screens and verify intake guards/screens are in place as appropriate to reduce intake of debris and birds contributing to downstream blockages. 46 CFR 108.181 & § 108.223
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 27 July 2024
Resolved 11 July 2024
Resolution: Received satisfactory documentation. Unit is fabricating new screens on location. Vent screen cleaning completed 03Jul2024.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 27 June 2024 Resolved
Brazed piping joints shall be sufficient for the intended service. Brazed joints for the potable water UV filter system in the Water Filter Room have temporary repairs due to joint issues. Affect repairs to ensure proper and leak free joints.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 27 July 2024
Resolved 29 July 2024
Resolution: Piping in way leaks replaced. Picture and statement on correction provided by the PIC.
11 - Life Saving Appliances › N/A - No Subsystem › Operational readiness of lifesaving appliances
Issued 9 January 2023 Resolved
A lifeboat engine shall be provided with either a manual starting system, or a power starting system with two independent rechargeable energy sources. Lifeboat 4's secondary battery bank was tagged out and inoperable. Make repairs to the secondary starting system ensuring two independent means of starting. 46CFR 160.135 LSA Code 4.4.6.2
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 February 2023
Resolved 13 February 2023
Resolution: The battery bank has been repaired.
04 - Emergency Systems › N/A - No Subsystem › Functionality of Safety Systems
Issued 9 January 2023 Resolved
The operator shall ensure that all equipment specified in the EEP, whether the equipment is located on or off of the facility, is made available and located as indicated in the EEP and is designed and maintained so as to be capable of performing its intended function during an emergency evacuation. While conducting emergency drills no means of communication was operable to allow the Incident Command Center to contact shore to report casualties. Personnel were using personal cell phones that relied on electrical power and a wifi signal to communicate. Make repairs to the phone system to ensure personnel are able to contact shore from their designated position on the station bill. 46CFR 146.140(e)(1)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 February 2023
Resolved 13 February 2023
Resolution: The phone system has been repaired.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 30 September 2020 Resolved
Each crane must meet the following rated load test each 60 months. Facility did not have any documentation for 5 year load test. Provide documentation or conduct test.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 11 November 2020
Resolved 30 September 2020
Resolution: Def issued in error.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 30 September 2020 Resolved
All cable for electric power must be checked for proper insulation resistance. Found multiple cables with outer jacket cut. Make proper repairs to satisfaction of USCG.
Condition: Damaged By Earlier Event
Action required: 16 - Rectify deficiencies w/in 14 days
Due 11 November 2020
Resolved 20 December 2020
Fire Fighting › Structural - A Class Divisions › Doors
Issued 15 August 2017 Resolved
Accommodation exterior doors and blast wall door need to be adjusted IAW Fire Control Plan.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 15 September 2017
Resolved 21 August 2017
Electrical › Electric Supply System (service) › Cable
Issued 15 August 2017 Resolved
Electrical water heater #1 440 volt wiring not electrically sound.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 15 September 2017
Resolved 21 August 2017
Deck/Cargo › Cargo Transfer (solid) › General
Issued 15 August 2017 Resolved
Both cranes past due on 5 yr rated load test.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 15 September 2017
Resolved 21 August 2017
Lifesaving › Launching Appliances › Davit
Issued 28 July 2016 Resolved
Limits switches on #1 lifeboat, which is the designated rescue boat, were siezed and would not allow rasiing of the boat from a lowered position. Limit switches on all lifeboat davits were seized.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 14 August 2016
Resolved 1 August 2016
Resolution: The OIM provided a statement that the platform's crew exercised and lubricated all limit switches. It is also stated that any limit switches that do not function properly during the next monthly test will be replaced.
Fire Fighting › Structural - A Class Divisions › Doors
Issued 18 October 2010 Resolved
Ensure proper operation of self closing devices on all class "A" doors on all floors for dumbwaiter doors and electrical room doors.
Action required: 705 - Other - as specified
Due 18 November 2010
Resolved 10 November 2010
Resolution: Verified that all doors for dumb waiter closets were properly adjusted to self close and that the door knob and latch for the electrical closet door on the 4th deck of the accommodations space was installed.
Fire Fighting › Fixed CO2 Fire Extinguishing System › Piping
Issued 18 October 2010 Resolved
Identified improperly installed flexible loops at fire stations (CO2) #19 and (FM200) #1, #5, and #6. Ensure flexible loops are properly installed on all fixed fire fighting stations.
Action required: 705 - Other - as specified
Due 18 November 2010
Resolved 10 November 2010
Resolution: Verified that repairs on the listed fixed fire fighting systems were completed. All flexible loops were installed or adjusted to our satisfaction.
Fire Fighting › Fire Main › Condition
Issued 18 October 2010 Resolved
Identified temporary repairs on FRP fire main pipe in the OVHD on top of #2 column. Make permanent repairs.
Action required: 705 - Other - as specified
Due 18 November 2010
Resolved 18 November 2010
Lifesaving › Lifeboat › Propeller
Issued 18 October 2010 Resolved
Identified two missing bolts on the #2 lifeboat propeller guard. Ensure bolt are properly installed.
Action required: 705 - Other - as specified
Due 18 November 2010
Resolved 10 November 2010
Resolution: Verified that the identified missing bolts for the lifeboat propeller guard were replaced.
Lifesaving › Lifejacket/PFD (Type I) › Lights
Issued 18 October 2010 Resolved
Install lights on all lifejackets in control room.
Action required: 705 - Other - as specified
Due 18 November 2010
Resolved 10 November 2010
Resolution: Verified that all lifejackets stored in rigs control room had all proper attachements.
Documentation › Certificates/Documents › Certificate of Financial Responsibility
Issued 12 September 2007 Resolved
COFR expired 01 Jul 2007.
Condition: Unknown
Action required: 705 - Other - as specified
Due 11 November 2007
Resolved 31 October 2007
Resolution: Owner obtained new COFR.
Documentation › Safety/Response Plans/Programs › Fire Control Plans
Issued 5 August 2004 Resolved
Provide updated Fire Control Plan for approval to MSO Port Arthur.
Due 14 November 2004
Resolved 10 March 2005
Resolution: After further revision, plan was reviewed and approved.
Fire Fighting › Fire Main › Diameter
Issued 5 August 2004 Resolved
Install MSC approved fire main system for the Nabors MODS 201 drilling package. Current system to be used only on MAGNOLIA project and only within MSO Port Arthur's zone. For further clarification, reference [name withheld] narrative comments in activity number 2103613.
Due 21 October 2005
Resolved 31 October 2007
Resolution: Moved Details to note in Vessel Summary.
Documentation › Certificates/Documents › Stability Letter
Issued 5 August 2004 Resolved
Complete all outstanding conditions of class by the set deadlines of ABS.
Action required: 705 - Other - as specified
Resolved 3 March 2005
Resolution: Received confirmation that platform met all conditions of class.
Fire Fighting › Fixed Gas Fire Extinguishing System › Quantity of Gas
Issued 4 February 2004 Resolved
Provide approved fixed gaseous type fire extinguishing system for enclosed diesel pump room in SW column prior to issuance of COI. Until installation of this system is completed, diesel pumps may only be operated manually, and only long enough to fill day tanks-then shut down. While running, pumps must be maintained under continuous fire watch.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 22 October 2004
Resolution: Reviewed approval & tested system.
Fire Fighting › Structural - A Class Divisions › Control Stations
Issued 4 February 2004 Resolved
Install suitable ventilation system for EMCC that meets A-Class structural fire protection boundary and fulfills shutdown & closure required functions for fixed fire extinguishing system. Manning of this space will require OIM permission, with door open to provide adequate ventilation, and door closure when space is not manned.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 31 March 2005
Resolved 26 May 2005
Resolution: Reviewed approval & visually inspected.
Fire Fighting › Fixed Gas Fire Extinguishing System › Piping
Issued 4 February 2004 Resolved
Obtain approval for fixed fire extinguishing system for upper level MCC (South). Until such time that this system is approved, system must remain disabled to prevent possible inadvertent discharge.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 12 October 2004
Resolution: Approval received from MSC.
Accommodation/Occupational Safety › Potable Water System › General
Issued 4 February 2004 Resolved
Obtain NSF approval/mark for nonmetallic potable water piping IAW 46 CFR 56.60-25. Until such time that this approval is received, complete weekly water sampling as necessary to ensure potable water quality. Make bottled water available for consumption.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 31 March 2005
Resolved 21 February 2005
Resolution: Received NSF approval.
Fire Fighting › Structural Fire Protection - General › Fiber Reinforced Plastic
Issued 4 February 2004 Resolved
Complete installation as proposed for metallic support for exterior deck lights currently suspended by "Tuff-Span" FRP beams so that failure of these beams will not cause cables/lights they are supporting to fall & hinder excape or access by firefighters.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 12 October 2004
Resolution: Installation complete.
Fire Fighting › Fixed CO2 Fire Extinguishing System › Operating Controls
Issued 4 February 2004 Resolved
Obtain/provide approval documentation for fixed CO2 systems installed to protect turbine generator enclosures. These 350# (pound) systems do not have the alarm (w/ 20 second time delay) and means of escape required by 46 CFR 108.445. Systems must be approved prior to operation of these turbines.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 22 October 2004
Resolution: Reviewed approval & tested system.
Fire Fighting › Structural - A Class Divisions › Fire Doors
Issued 4 February 2004 Resolved
Demonstrate proper function for hull MCC fire doors while space is at normal operating pressure.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 12 October 2004
Resolution: Function tested doors.
Fire Fighting › Fire Hydrants › Location/Position
Issued 4 February 2004 Resolved
Temporary arrangement is authorized for fire protection of inactive columns pending outcome of request for equivalency in lieu of installation of firemain system required by 46 CFR 108.423. See COI for operating condition.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 12 October 2004
Resolution: Received equivalency.
Lifesaving › Lifebuoys › Stowage
Issued 4 February 2004 Resolved
Provide quick release arrangement for at least two lifebuoys with self-activating smoke signals as required by 46 CFR 108.580.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 22 October 2004
Resolution: Inspected quick release mechanism.
Fire Fighting › Fire Main › Condition
Issued 4 February 2004 Resolved
Provide protection for fire monitor installed in way of the platform east side crane laydown area.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 12 October 2004
Resolution: Inspected protective barrier.
Fire Fighting › Fixed CO2 Fire Extinguishing System › Operating Controls
Issued 4 February 2004 Resolved
Demonstrate proper function (and provide approval documentation) for fixed fire extinguishing systems on compressor turbine enclosures.
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 22 October 2004
Resolution: Reviewed approval & tested system.
Communications › Alarms/Indicators › General Alarm
Issued 4 February 2004 Resolved
Once offshore and operating, demonstrate that GA/PA system provides sound pressure levels above background noise as required by 46 CFR 113.
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 26 May 2005
Resolution: Reviewed noise survey & spot checked comms system during operating mode.
Electrical › Electrical Distribution System (service) › Wiring
Issued 4 February 2004 Resolved
Verify proper installation of all electrical equipment in hazardous locations and verify area classification plan (once it is approved.)
Action required: 705 - Other - as specified
Due 1 August 2004
Resolved 22 October 2004
Resolution: Inspected electrical installation

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.