MAURY USCG vessel records
← All vessels

SAUVAN

SAUVAN is a 2010 freight ship. The Coast Guard has recorded 7 inspections since 2018, most recently in April 2026, along with 3 deficiencies.

Records from 2018 to 2026. Most recent: inspection, 26 April 2026.

Built
2010
Last inspected
26 April 2026
Documentation
Not in the documentation file of 10 August 2026
Controls
None recorded without a removal date

Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Bulk Carrier class in Maury's sources begin in 2016.

Inspection record

Last inspected 26 April 2026
Operational controls None recorded without a removal date
Years with a record 4 calendar years (2018–2026)
Every line above is a count of records the US Coast Guard wrote, or a date it recorded. A blank resolution means none was recorded in this data; it does not establish that a deficiency is outstanding. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Identity

9537628
1097077
Flag
LIBERIA
Maury page id
psix-1097077

Documentation record

Tonnage as PSIX records it43506 - Convention (Subpart B), Gross Ton
27692 - Convention (Subpart B), Net Ton
93377 - Displacement, Metric Ton
79699 - Dead Weight, Metric Ton
This hull's Official Number is not in the NVDC file dated 10 August 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.
Vessel history report

A report is not offered for this hull. Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. What a sparse-record report looks like.

Inspection history · 7

26 April 2026 PSC B
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 8333340
27 March 2026 Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 8332892
1 July 2023 Deficiency Check
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 7727946
28 June 2023 PSC B
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 7717376
1 August 2019 Administrative Inspection
Administrative · Sector Virginia · USCG East District (CGD-E) · Activity 6769780
11 February 2019 Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6623847
28 July 2018 ISPS II Exam · Ballast Water Examination · PII Safety Exam
Physical examination · Marine Safety Unit Portland OR · USCG Northwest District (CGD-NW) · Activity 6484897

Deficiency record · 3

14 - Pollution Prevention › 144 - MARPOL Annex IV (Not Applicable to PSC Exams conducted in the U.S.) › Sewage treatment plant
Issued 28 June 2023 Resolved
After any survey of the ship has been completed, no change shall be made in the structural arrangements, machinery equipment and other items covered by the survey. PSCO observed portable fan cooling sewage treatment plant motor. High level of H2S was recorded in hospital space.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 30 June 2023
Resolution: Repaired/Rectified: Sewage treatment system blower was renewed with one of the same specification as of the original one. This finding is considered by DNV to have been sufficiently addressed.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 28 June 2023 Resolved
The associated piping system and fittings shall be of a design and construction adequate for the service in which they are intended. PSCO observed several pin hole leaks along the freshwater line between the potable water holding tank and hydrophore tank and the raw water line from the boiler to the condensation collection tank.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 12 July 2023
Resolved 1 July 2023
Resolution: Crew replaced piping. No leaks detected.
01 - Certificates & Documentation › 013 - Documents › Oil record book
Issued 28 June 2023 Resolved
Each operation described in paragraph 2 of this regulation shall be fully recorded withour delay in the Oil Record Book Pt 1, so that all entries in the book appropriate to that operation are completed. PSCO observed several entries that were improperly recorded by the 2/E and C/E from 30 April 2023 to 25 June 2023. MARPOL I/17.4 16AC
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 1 July 2023
Resolution: Through the technical office, training was discussed and carried out with Superintendent Engineer and crew. Attending DNV Surveyor discussed with Engine Officers and satisfied they understand procedure and re-occurrence will not happen again.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.