Inspection history · 25
6 February 2026
Appeal
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 8317305
9 January 2026
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 8294038
3 June 2025
COI Inspection · Deficiency Check · Administrative Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 8097757
6 July 2024
Administrative Inspection · Deficiency Check
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7950956
10 June 2024
Administrative Inspection · Deficiency Check · Damage Survey
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7937400
31 October 2023
Deficiency Check
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7821187
27 July 2023
Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7752261
14 July 2022
Annual Inspection · Administrative Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7478234
19 May 2021
Internal Structural Exam · Drydock Exam · Administrative Inspection · COI Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7200164
19 April 2020
Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6955533
2 October 2019
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6826626
24 May 2019
Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6690962
22 May 2018
Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6414577
24 May 2017
Administrative Inspection · Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6226790
24 October 2016
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6028888
18 October 2016
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6024800
25 April 2016
COI Inspection · Drydock Exam · Internal Structural Exam
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 5862082
30 July 2015
Deficiency Check
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 5200960
23 July 2015
Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 5125066
5 December 2014
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 5035110
14 April 2014
Annual Inspection · Administrative Inspection · MTSA Verification
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 4871590
7 November 2013
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 4749243
25 June 2013
Deficiency Check · MTSA Verification · Administrative Inspection · Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 4613795
12 July 2012
Annual Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 4398382
24 May 2012
Examination of Repairs
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 4321834
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 9 January 2026
No resolution recorded
In hazardous areas machinery and electrical equipment must be approved for the installation by MSC. The
portable diesel engine driven cargo pump must be
approved for operation within the hazardous zone or modified to place the engine and electrical components outside the hazardous zone (10 ft). *Complete prior to operating in 2026.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 9 January 2026 — due date passed with no resolution recorded
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 9 January 2026
No resolution recorded
On all tank vessels, the construction or conversion of which is started on or after July 1, 1951, the cargo piping shall be: A fixed cargo piping system shall be installed on a tank vessel carrying Grade A, B, or C cargo. A portable diesel engine-driven cargo pump is being utilized within a hazardous location, and portable cargo hoses are being used for cargo transfer operations. This arrangement does not comply with the regulatory requirements for hazardous area installations and fixed cargo piping systems on tank barges carrying Grade A, B, or C cargo. *Complete prior to operating in 2026.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 9 January 2026 — due date passed with no resolution recorded
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 3 June 2025
Resolved
To maintain a valid Certificate of Inspection, you must complete your annual and periodic inspections within the periods specified in § 31.10-17 (a) and (b) and your Certificate of Inspection must be endorsed. The Periodic Inspection was required to be completed by August 19, 2024 in order to maintain maintain the validity of the COI but the periodic inspection was not completed within the required time frame.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 3 June 2025
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 3 June 2025
Resolved
The transfer procedures required by § 155.720 must be permanently posted or available at a place where the procedures can be easily seen and used by members of the crew when engaged in transfer operations. The oil transfer procedures were not on board and available for the crew.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 9 June 2025
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 3 June 2025
Resolved
Electrical equipment should not be installed in hazardous locations unless essential for operational purposes. When installed in these locations, special precautions should be taken to ensure that the electrical equipment is not a source of ignition. Electrical equipment not rated for hazardous locations (not intrinsically safe or explosion-proof) was improperly used inside a conex box located within a hazardous area on deck. Power was supplied to this equipment via an extension cord.
46 CFR 32.45-1
46 CFR 111.105-3(a)
Action required: 10 - Deficiency Rectified
Resolved 3 June 2025
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 3 June 2025
Resolved
Manholes and flush scuttles in position 1 or 2 or within superstructures other than enclosed superstructures shall be closed by substantial covers capable of being made watertight. The gaskets for the manholes hatches on the cargo domes were found wasted and not maintaining watertight integrity.
46 CFR 31.25-1
46 CFR 42.15-40
Action required: 17 - Rectify deficiencies prior to departure
Resolved 12 June 2025
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 3 June 2025
Resolved
A vessel being pushed ahead, not being part of a composite unit, shall exhibit at the forward end; sidelights. The portable sidelights were not operational.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 9 June 2025
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo transfer - Tankers
Issued 6 July 2024
Resolved
When minor repairs of tank vessels become necessary such work shall be under the direction of the Officer in Charge, Marine Inspection, and shall be in accordance with the regulations in effect at the time the vessel was contracted for or built, or in accordance with the regulations in effect for new construction insofar as possible. Vessel cargo pump soft start failed. Vessel is authorized temporary use of portable cargo pump outside of hazardous zone while awaiting permanent repair of existing cargo pump. 46CFR30.01-10
Action required: 50 - Rectify deficiencies w/in 30 days
Due 6 August 2024
Resolved 7 August 2024
Resolution: Sturgeon Electrical attended vessel, made repairs, and provided a report. Uploaded to documents.
02 - Structural Conditions › N/A - No Subsystem › Hull damage impairing seaworthiness
Issued 31 October 2023
Resolved
Vessel was reported beset in ice for three days in Kuskokwim River, until favorable tide change freed the barge. No damage was reported by operator, and the barge is schedule for two more deliveries (Village of Kasigluk and Nunapitchuk) before being laid up for the season. After making deliveries to the two listed villages, vessel is required to complete Internal Structural Exam prior to operating with Cargo. 31.10-21
Condition: Invalid
Action required: 701 - Prior to carriage of passengers/cargo
Due 30 April 2024
Resolved 14 June 2024
Resolution: ISE completed
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 27 July 2023
Resolved
09209 - The locations in the weather are Class I, Division 1 (Zone 1) locations (except the open deck area on an inorganic acid carrier which is considered a non-hazardous location) and may have only approved intrinsically safe, explosion proof, or purged and pressurized electrical equipment. Cargo pump motor is marked for use within Class I, Division 2. 46 CFR 111.105-31(l)
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 10 June 2024
Resolution: New Class 1 Div 1 motor installed
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo transfer - Tankers
Issued 27 July 2023
Resolved
06106 - The transfer procedures required by 33 CFR 155.720 must contain all the required items listed in 33 CFR 155.750. Vessel currently has a generic tankerman's manual that meets many of the requirements, but lacks barge specific items (e.g. description of the transfer, line diagrams, and cargo information). 33 CFR 155.750
Condition: Design Flaw
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 10 June 2024
Resolution: Transfer procedures met requirement
01 - Certificates & Documentation › 013 - Documents › Log-books/compulsory entries
Issued 27 July 2023
Resolved
01305 - The vessel operator shall keep a written record available for inspection by the COTP or OCMI of the date and result of the most recent test and inspection of each item tested or inspected as required by § 156.170 of this chapter. Pressure gauges on the discharge side of the cargo pumps did not have records of test indicating accuracy within 10 percent of the actual pressure. 33 CFR 155.820 / 33 CFR 156.170
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 10 June 2024
Resolution: New calibrated gauges purchased installed.
09 - Working and Living Conditions › 092 - Working Conditions › Warning notices
Issued 27 July 2023
Resolved
09217 - A sign shall be displayed to warn persons approaching the gangway, while a vessel is moored or anchored unless it is empty and gas-freed. The sign shall state in letters not less than 2 inches high substantially as follows: Warning, No open lights, No smoking, No visitors. Vessel does not have the required sign as described in 46 CFR 35.30-1(b). 46 CFR 35.30-1(b)
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 10 August 2023
Resolved 17 August 2023
Resolution: Sector Anchorage received photographic evidence of purchased warning sign required by Subchapter D
01 - Certificates & Documentation › 013 - Documents › Log-books/compulsory entries
Issued 27 July 2023
Resolved
01305 - If your vessel is greater than or equal to 300 gross tons, you must submit a signed and certified, complete and accurate NOI in accordance with the requirements of Appendix E to receive coverage under the vessel general permit. Vessel has not filed an NOI for this vessel. 2013 VGP 1.5.1.1
Condition: Placed in Improper Service
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 9 August 2023
Resolution: VGP eNOI submitted to EPA
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo operation
Issued 19 May 2021
Resolved
Complete satisfactory hydro test of cargo piping system.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 20 June 2021
Resolution: O/O sent video of pipe testing
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Piping
Issued 25 April 2016
Resolved
Provide proof of hydro-testing of cargo piping prior to conducting operations.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 24 October 2016
Resolution: Administratively closed.
Electrical › Electrical Distribution System (service) › Switch
Issued 23 July 2015
Resolved
Provide new or properly repair Class 1 Div 1 cargo pump emergency shut down switch.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 July 2015
Resolution: switch repaired.
Fire Fighting › Portable Dry Chemical Fire Extinguisher › Service
Issued 23 July 2015
Resolved
Provide servicing report for all portable fire extinguishers.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 18 October 2016
Resolution: Closed due to satsifactory COI exam being completed on 4/25/16 by GS12 Miner
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Transfer Hose
Issued 23 July 2015
Resolved
Provide hydrostatic test reports for all cargo hoses to be used in service, 1.5 times the MAWP.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 18 October 2016
Resolution: Closed due to satisfactory COI exam being conducted on 4/25/16 by GS12 Miner
Documentation › Manuals/Policy Documentation › Transfer Procedures
Issued 23 July 2015
Resolved
Update transfer procedures piping drawing to reflect currentl configuration.
Action required: 705 - Other - as specified
Due 23 August 2015
Resolved 18 October 2016
Resolution: Closed due to satisfactory inspection completed on 4/25/16 by GS12 Miner.
Pollution Prevention/Response › Prevention Equipment › Fixed Containment
Issued 23 July 2015
Resolved
Provide containment under each oil loading manifold and transfer connections as required by 33 CGR 155.310
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 18 October 2016
Resolution: Closed due to satisfactory COI exam being conducted by GS12 Miner on 4/25/16.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Flame Screens
Issued 25 June 2013
Resolved
Provide three ullage opening flame screens for 4P, 5P, & 4S (46 CFR 35.30-10).
Due 9 August 2013
Resolved 15 August 2013
Resolution: Rcvd email fm [name withheld] w/ certification that flame screens were aboard barge.
Lifesaving › Lifebuoys › Not on Board
Issued 25 June 2013
Resolved
Provide two ring life buoys mounted at each end of the barge marked with name & hailing port (46 CFR 199.640(i)(2)).
Due 9 August 2013
Resolved 25 September 2013
Resolution: Administratively cleared - COI to be amended that ring life buoys are required when personnel are on board.
Electrical › Electrical Distribution System (service) › Non-conducting Deck Covering
Issued 25 June 2013
Resolved
Install electrical non-conductive deck covering at front of switchboard (46 CFR 111.30-11).
Due 9 August 2013
Resolved 15 August 2013
Resolution: Rcvd email fm [name withheld] w/ pictures indicating installation of non-conductive deck covering.
Documentation › Logs/Records › Oil Record Book
Issued 25 June 2013
Resolved
Obtain & maintain oil record book part 1 & part 2 (33 CFR 151.25).
Due 9 August 2013
Resolved 25 September 2013
Resolution: Rescinded (Per communication w/ HQ/CVC, ORBs shall only be required on barges which are actually fitted w/ some type of overboard discharge method - either OWS or ODME for cargo tanks - neither of which are fitted on the CAUNEQ).
Personnel › Manning/Qualifications › Person in Charge (PIC) of Transfer
Issued 12 July 2012
Resolved
Provide current list of approved PIC's
Action required: 705 - Other - as specified
Due 19 July 2012
Resolved 2 August 2012
Resolution: Updated/current PIC list provided.
Communications › Visual Communication › Red Warning Signal
Issued 12 July 2012
Resolved
Provide benzene regulated area stripe for barge.
Action required: 705 - Other - as specified
Due 12 August 2012
Resolved 19 July 2012
Resolution: provided.