MAURY USCG vessel records Sign in
← All vessels

LIA

LIA is a 2011 freight ship. The Coast Guard has recorded 5 inspections since 2020, most recently in April 2024, along with 3 deficiencies and 2 operational controls.

Records from 2020 to 2024. Most recent: inspection, 16 April 2024.

Built
2011
Last inspected
16 April 2024
Documentation
Not in the documentation file of 10 September 2026
Controls
None recorded without a removal date

Identity

9584152 View on MarineTraffic leaves Maury; a third-party site, nothing from it is stored here
9HA2673
1110430
Flag
MALTA
—
Maury page id
psix-1110430

Inspections, by type

…with no type recorded2
Years with a record 3 calendar years (2020–2024)
The 5 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Bulk Carrier class in Maury's sources begin in 1981.

Documentation record

Tonnage as PSIX records it56771 - Dead Weight, Metric Ton
19231 - Convention (Subpart B), Net Ton
67681 - Displacement, Ton
34044 - Convention (Subpart B), Gross Ton
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.

Radio station licence

No FCC ship-station licence is recorded against this Official Number in the file of 6 September 2026. That is a fact about the licence file, not about the radio.

A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.

Inspection history · 5

16 April 2024 PSC B
Physical examination · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 7891777
13 March 2021 Type not recorded
No type recorded · Marine Safety Unit Portland OR · USCG Northwest District (CGD-NW) · Activity 7155528
8 June 2020 Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6970748
12 February 2020 PSC B
Physical examination · Marine Safety Unit Portland OR · USCG Northwest District (CGD-NW) · Activity 6902643
10 February 2020 Type not recorded
No type recorded · Sector Columbia River · USCG Northwest District (CGD-NW) · Activity 6903385

Deficiency record · 3

09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 12 February 2020 Resolved
Electrical installations shall be such that the safety of crew and ship from electrical hazards will be ensured. PSCO found dead end wiring and spliced wiring on all three generators. In addition, two wires outside of the cable run were found hanging within an inch of the prime mover on number one generator. 74 SOLAS (14) II-1/48.1.3 17ac
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 12 February 2020
Resolved 13 February 2020
Resolution: Received Class Report from BV stating that all dead end and spliced wiring has been removed and hanging wires were properly secured.
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 12 February 2020 Resolved
In a ship in which oil fuel is used, the arrangements fo rthe storage, distribution and utilization of the oil fuel shall be such as to ensure the safety of the ship and persons on board. PSCO found active fuel oil leaks on number one generator fuel supply line and number three generator fuel rack. 74SOLAS (09) II-2/4.4.4 17 ac
Action required: 17 - Rectify deficiencies prior to departure
Due 12 February 2020
Resolved 13 February 2020
Resolution: Received Class Report from BV stating that fuel oil leaks from generators were rectified with replaced 'O' Rings and seal rings.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 12 February 2020 Resolved
The machinery, boilers, and other pressure vessels, associated piping systems and fittings shall be of a design and construction for the service which they are intended. PSCO found active water leak from fresh water heat exchanger for essential machinery. 74SOLAS (14) II-1/26.1 17ac
Action required: 17 - Rectify deficiencies prior to departure
Due 12 February 2020
Resolved 13 February 2020
Resolution: Received Class Report from BV stating that fresh water heat exchanger end plate bolts were tightened and leak was rectified.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.