MAURY USCG vessel records Sign in
← All vessels

ZIM CONSTANZA

ZIM CONSTANZA is a 2010 freight ship. The Coast Guard has recorded 30 inspections since 2011, most recently in March 2022, along with 19 deficiencies and 8 operational controls, 1 with no removal date recorded.

Records from 2011 to 2022. Most recent: inspection, 15 March 2022.

Built
2010
Last inspected
15 March 2022
Documentation
Not in the documentation file of 10 September 2026
Controls
1 with no removal date recorded

Identity

9471202 View on MarineTraffic leaves Maury; a third-party site, nothing from it is stored here
1111804
Flag
ISRAEL
—
Maury page id
psix-1111804

Inspections, by type

…with no type recorded7
Years with a record 9 calendar years (2011–2022)
The 30 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

This record may be incomplete: the most recent inspection recorded for this vessel was 4 years ago. Maury shows what the Coast Guard recorded, not whether the vessel has been inspected since, is still in service, or what condition it is in. Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the General Dry Cargo Ship class in Maury's sources begin in 1980.

Documentation record

Tonnage as PSIX records it23747 - Convention (Subpart B), Net Ton
50086 - Dead Weight, Ton
67907 - Displacement, Ton
40542 - Convention (Subpart B), Gross Ton
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.

Radio station licence

No FCC ship-station licence is recorded against this Official Number in the file of 6 September 2026. That is a fact about the licence file, not about the radio.

Inspection history · 30

15 March 2022 PSC B
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7411992
25 May 2021 In-Service Inspection
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 7206054
23 May 2021 Administrative Inspection
Administrative · Sector Virginia · USCG East District (CGD-E) · Activity 7203708
17 May 2021 PSC B
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7198901
26 March 2021 Administrative Inspection
Administrative · Sector Virginia · USCG East District (CGD-E) · Activity 7163271
8 December 2020 Administrative Inspection
Administrative · Sector Virginia · USCG East District (CGD-E) · Activity 7108222
8 October 2020 Administrative Inspection
Administrative · Sector Virginia · USCG East District (CGD-E) · Activity 7073688
4 October 2020 Ballast Water Examination · MARPOL Annex VI Survey · PSC B
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7070959
15 August 2020 Administrative Inspection
Administrative · Sector Virginia · USCG East District (CGD-E) · Activity 7033608
8 August 2020 Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 7026982
9 June 2020 Type not recorded
No type recorded · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 6971908
6 June 2020 Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6969497
5 May 2020 Type not recorded
No type recorded · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 6948629
21 April 2020 Administrative Inspection
Administrative · Sector Virginia · USCG East District (CGD-E) · Activity 6941720
17 April 2020 Type not recorded
No type recorded · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 6940277
12 April 2020 Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6938403
22 February 2020 Administrative Inspection
Administrative · Sector Virginia · USCG East District (CGD-E) · Activity 6913516
21 February 2020 PSC B
Physical examination · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 6910506
13 May 2019 ISPS II Exam · PII Safety Exam · Ballast Water Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6682837
5 May 2018 Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6406524
4 May 2018 PII Safety Exam · Ballast Water Examination · ISPS II Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6405492
19 March 2018 Administrative Inspection · Deficiency Check
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 6374734
16 March 2018 Administrative Inspection
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 6372868
3 January 2018 Administrative Inspection
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 6331993
9 December 2016 ISPS II Exam · Ballast Water Examination · PII Safety Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6055443
6 September 2016 Administrative Inspection
Administrative · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 5993613
13 November 2015 ISPS II Exam · Ballast Water Examination · PII Safety Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5762939
17 October 2014 Administrative Inspection · Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5019413
5 October 2014 ISPS II Exam · Ballast Water Examination · PII Safety Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 4999211
11 September 2011 Ballast Water Examination · ISPS II Exam · PII Safety Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 4141387

Deficiency record · 19

13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 25 May 2021 Resolved
The machinery shall be of a design and construction adequate for the service for which they are intended. PSCO received report the vessels fuel pump is not fully operational. 17ac
Action required: 17 - Rectify deficiencies prior to departure
Due 25 May 2021
Resolved 26 May 2021
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Company responsibility and authority
Issued 13 May 2019 Resolved
The company should establish procedures for the implementation of corrective action, including measures intended to prevent recurrence. Since the previous US Coast Guard detention of the vessel in May 2018 for excessive amounts of oily mixtures in the engine room, the company failed to take any measures to prevent recurrence. Excessive oil was observed around the main engine, in the fuel oil purifier room, underneath the main engine lube oil purifier, in the engine room bilges, and under the shaft. 74SOLAS (2014 CONS) IX/3.1 ISM Code 9.2
Action required: 30 - Ship detained
Resolved 16 May 2019
Resolution: Class provided class report attesting to deficiency identified. CG inspectors conducted general walkthrough of engine room and attested to the rectification of deficiency. DPA also provided internal audit outlining company's non-conformance procedures.
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Masters responsibility and authority
Issued 13 May 2019 Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Action required: 30 - Ship detained
Resolved 16 May 2019
Resolution: DPA internal audit outlines procedures on the reporting of non-conformities and issued company wide procedures to report non-conformities to appropriate authority's.
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 13 May 2019 Resolved
Means shall be provided to control leaks of flammable liquids. The vessel had excessive amounts of oily mixtures in bilges from leaking; main engine, generators, fuel oil purifiers, lube oil purifiers, and shaft seal. Oil soaked lagging was observed around fuel pumps on Main engine and in the Purifier room. Additionally, the main engine had pooled oil around the fuel pumps, cylinder heads, and lube oil exhaust lines. 74 SOLAS (2004 CONS) II-2/ 4.1.1
Action required: 30 - Ship detained
Resolved 17 May 2019
Resolution: Recieved satisfactory Flag/Class report. CG inspectors conducted general walkthrough of engine room and attested to the rectification of deficiency.
04 - Emergency Systems › N/A - No Subsystem › Emergency source of power - Emergency generator
Issued 13 May 2019 Resolved
Each emergency generating set arranged to be automatically started shall be equipped with starting devices approved by the Administration. A second source of energy shall be provided. Secondary means of starting emergency generator was inoperable. 74 SOLAS (2004 CONS) II-1/44.2
Action required: 17 - Rectify deficiencies prior to departure
Resolved 17 May 2019
Resolution: Received satisfactory class report.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 13 May 2019 Resolved
After any survey of the ship under regulations 7, 8, 9 or 10 has been completed, no change shall be made in the structural arrangements, machinery, equipment, and other items covered by the survey without the sanction of the Administration. Flex hose is installed connecting AC condensate drain line to sewage holding tank. A flex hose is also installed from grey water drain line aft of the main engine running the length of the shaft and emptying in the aft bilge well. 74 SOLAS (2014 CONS) I/ 11(b)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 17 May 2019
Resolution: Recevied satisfactory Class report.
07 - Fire Safety › N/A - No Subsystem › Jacketed high pressure lines and oil leakage alarm
Issued 13 May 2019 Resolved
Connections withing the fuel supply and spill lines shall be constructed having regard to their ability to prevent pressurized fuel leaks while in service and after maintenance. 09 high pressure jacketed fuel lines on M/E have evidence of fuel leakage. Fuel lines identified are listed below: Cylinder 1 - Center Fuel Line Cylinder 3 - Fwd Fuel Line Cylinder 5 - Center Fuel Line Cylinder 6 - Fwd & Center Fuel Line Cylinder 7 - Fwd & Center Fuel Line Cylinder 8 - Fwd & Center Fuel Line Vessel is required to replace/fix the fuel lines identified above.
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Due 16 May 2019
Resolved 17 May 2019
Resolution: Received satisfactory class report.
Operations/Management › Vessel Safety Management › Master's Responsiblity/Authority
Issued 4 May 2018 Resolved
The company should clearly define and document the Masters responsibility to implement the safety policy of the company. The Master has overriding authority on affecting safety according to the SMS QP 8.1. The Master failed to implement the safety policy on the ship.
Condition: Improper/Lack of Maintenance
Action required: 30 - Ship detained
Resolved 7 May 2018
Resolution: The company completed an internal audit of the ships Safety Management System.
Operations/Management › Bilge/Bilge System Management › Control of Oil Mixtures
Issued 4 May 2018 Resolved
The purpose of this regulation is to limit fire growth potential in every space of the ship. The ship had excessive amounts of oily mixtures in bilges from leaking; Main Engine, all four generators, purifier #1 feet pump, and shaft seal.
Condition: Improper/Lack of Maintenance
Action required: 30 - Ship detained
Resolved 7 May 2018
Resolution: The oily mixtures were removed from the bilges.
Fire Fighting › Fixed Gas Fire Extinguishing System › Operating Controls
Issued 4 May 2018 Resolved
Carbon Dioxide systems for the protection of spaces shall have a control to ensure the activation of an alarm for the release of carbon dioxide into the space. The alarm limit switches on the CO2 system are disconnected.
Condition: Damaged By Earlier Event
Action required: 30 - Ship detained
Resolved 7 May 2018
Resolution: The CO2 alarms were installed, tested and verified through class report.
Fire Fighting › Structural - A Class Divisions › Control Stations
Issued 4 May 2018 Resolved
"A" Class divisions shall be insulated with approved non-combustible materials. The "A-60" boundary insulation has been removed from the CO2 room.
Condition: Damaged By Earlier Event
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 18 June 2018
Lifesaving › Lifebuoys › Stowage
Issued 4 May 2018 Resolved
Lifebuoys shall be capable of being rapidly cast loose and not permanently secured in any way. All lifebuoys were permananetly tied down to bracket with rope in the steering gear room.
Condition: Improper Installation
Action required: 17 - Rectify deficiencies prior to departure
Resolved 7 May 2018
Resolution: Lifebuoys are not permanently secured and are able to be cast free.
Fire Fighting › Portable CO2 Fire Extinguisher › Mounting Bracket
Issued 4 May 2018 Resolved
Fire fighting appliances shall be maintained ready for use. The fire extinguisher was permanently secured to the bracket with rope in the steering gear room.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 7 May 2018
Resolution: The fire extinguisher mounting bracket was replaced and is now operational.
Lifesaving › Inflatable Liferafts › Container Construction
Issued 19 March 2018 Resolved
THE CONDITION OF THE SHIP AND EQUIPMENT SHALL BE MAINTAINED TO ENSURE THE SHIP WILL REMAIN FIT TO PROCEED TO SEA. DURING VOYAGE ACROSS THE ATLANTIC, THE VESSEL SUSTAINED DAMAGE DUE TO SEVERE WEATHER TO THE FOLLOWING: FRACTURES TO STARBOARD SIDE BREAK WATER, NAVIGATION LIGHT STARBOARD SIDE, FLOOD LIGHTS ON FORWARD MAST, FORWARD STARBOARD LIFEBUOY LIGHT, AFT MOORING STATION LIFEBUOY WITH LINE, FORWARD STARBOARD FIRE HYDRANT WHEEL, AND FORWARD LIFERAFT CASING. 74SOLAS(2014) I/11 (17AC)
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 20 March 2018
Resolution: RECEIVED CLASSIFICATION SOCIETY (DNV GL) REPORT ADDRESSING ALL DAMAGED EQUIPMENT HAS BEEN SATISFACTORILY REPLACED (SEE DOCUMENTS).
Fire Fighting › Structural - A Class Divisions › Machinery Spaces
Issued 5 October 2014 Resolved
0999-Other (Safety in general) - Fire integrity of bulkhead between Engine Control Room (ECR) and Machinery Space is required to be on an A-60 bulkhead. Cracks were found on both ECR windows and aft ECR door. This condition compromises the A-60 boundary and shows indication of stress on the bulkhead. SOLAS 74' (2004 cons) II-2/4.2.3.3
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 6 November 2014
Resolved 12 November 2014
Resolution: Received, reviewed and accepted photographs and Flag report from [name withheld] of Transport rectifying the deficiency. Cracks were permanently repaired to the satisfaction of the vessel''s Administration.
Electrical › Lighting (emergency) › Lighting Fixture
Issued 5 October 2014 Resolved
0945-Emergency Lighting - Posters or signs shall be provided on or in vicinity of survival craft and their launching controls and shall be seen easily seen under emergency lighting conditions. The Emergency Lights in the vicinity of the Forward Life Raft are inoperable. SOLAS 74 (2009 cons) III/9.2.2
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 6 November 2014
Resolved 12 November 2014
Resolution: Received, reviewed and accepted photographs and a Flag report from [name withheld] of Transport clearing the deficiency. Light fixtures were repaired to the satisfaction of Flag.
Documentation › Certificates/Documents › Cargo Ship Safety Equipment Certificate
Issued 5 October 2014 Resolved
0110-Cargo Ship Safety Equipment - Cargo Ship Safety Equipment Certificate was issued indicating 12 Rescue Boats. Revise certificate as needed. SOLAS 74 (2009 cons) I/12.a.iii
Action required: 705 - Other - as specified
Due 6 November 2014
Resolved 6 November 2014
Resolution: Received, reviewed and accepted flag letter clearing the deficiency. A new CSSE Certificate was issued to the ship which states that there is 01 Rescue Boat.
Engineering › Diesel Engine (auxiliary) › Gear/Clutch Starter (hydraulic)
Issued 11 September 2011 Resolved
1430-Auxiliary engines-Manually charged hydraulic accumulators shall be demonstrated as effective when starting the emergency generator sets. Emergency Generator is unable to start reliably, only starting 2 out of 10 times. Pump air bound, tested satisfactorily after repair. SOLAS '09 Ch II/1 Reg 44 SOLAS 2009, Ch II-1, Reg 44
Action required: 705 - Other - as specified
Resolved 11 September 2011
Resolution: Hydraulic started was found to be air bound preventing consistent starting. Starter was bled while inspection team was aboard and deficiency was cleared.
Fire Fighting › Emergency Fire Pumps › Power Source
Issued 11 September 2011 Resolved
0740-Pumps-Fire fighting systems shall be readily available for immediate use. Emergency fire pump failed to start. Trouble-shooting revealed a blown fuse in pump's electrical control box. Blown fuse was incorrect according to electrical schematic. Correct fuse installed and tested satisfactorily. SOLAS '09 Ch. II/2 Reg 14 SOLAS 2009, Ch II-2, Reg 14
Action required: 705 - Other - as specified
Resolved 11 September 2011
Resolution: Deficiency was resolved while inspection team was onboard.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.