← All vessels
BW CLEAR SKY
BW CLEAR SKY is a 2011 tank ship. The Coast Guard has recorded 20 inspections since 2016, most recently in October 2025, along with 5 deficiencies and 1 operational control.
Records from 2016 to 2025. Most recent: inspection, 20 October 2025.
- Built
- 2011
- Last inspected
- 20 October 2025
- Documentation
- Not in the documentation file of 10 September 2026
- Deficiencies
- 5 recorded · 0 without a recorded resolution
- Controls
- None recorded without a removal date
Identity
9413327 View on MarineTraffic leaves Maury; a third-party site, nothing from it is stored here
9V9665
1146601
Flag
SINGAPORE
—
Maury page id
psix-1146601
Inspections, by type
…with no type recorded3
Years with a record
10 calendar years (2016–2025)
The 20 inspections in the strip above, split by the kind of activity the US
Coast Guard recorded. Years with a record are calendar years in which a record exists, not
years in service. What Maury does not do.
Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Tank Ship class in Maury's sources begin in 1980.
Documentation record
Tonnage as PSIX records it36217 - Convention (Subpart B), Net Ton
100395 - Dead Weight, Metric Ton
131668 - Displacement, Metric Ton
109949 - Convention (Subpart B), Gross Ton
100395 - Dead Weight, Metric Ton
131668 - Displacement, Metric Ton
109949 - Convention (Subpart B), Gross Ton
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.
Radio station licence
No FCC ship-station licence is recorded against this Official Number in the file of
6 September 2026. That is a fact about the licence file, not about the radio.
Inspection history · 20
20 October 2025
Administrative Inspection · PSC B · COC-GAS Renew
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 8251485
10 October 2025
Administrative Inspection
Administrative · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 8250590
3 September 2024
Administrative Inspection
Administrative · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7995507
30 March 2024
COC-GAS Renew · PSC B
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 7882399
29 March 2024
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7882483
4 December 2023
Administrative Inspection
Administrative · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 7833407
19 August 2023
COC-GAS Annual · PSC B
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 7765650
1 February 2022
PSC B · COC-GAS Renew
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7386497
1 July 2021
Administrative Inspection
Administrative · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 7241235
11 December 2020
COC-GAS Annual · PSC B
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 7105653
10 December 2020
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7109842
11 September 2020
Type not recorded
No type recorded · Sector Virginia · USCG East District (CGD-E) · Activity 7054432
31 August 2020
COE-Administrative
Administrative · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7046942
8 November 2019
ISPS II Exam · Ballast Water Examination · COC-GAS Renew
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6845262
8 November 2019
Special
Type not classified · Liquefied Gas Carrier National Center of Expertise · Activity 7089580
29 January 2019
Administrative Inspection
Administrative · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 6616820
1 November 2018
COC-GAS Annual · ISPS II Exam · Ballast Water Examination
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6570714
29 October 2017
Ballast Water Examination · COC-GAS Renew · ISPS II Exam
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6295042
6 April 2016
ISPS II Exam · Ballast Water Examination · Deficiency Check · COC-GAS Renew
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5852023
5 April 2016
Special
Type not classified · Liquefied Gas Carrier National Center of Expertise · Activity 6093245
Deficiency record · 5
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 20 October 2025
Resolved
ELECTRICAL EQUIPMENT SHOULD BE SUCH AS TO MINIMIZE THE RISK OF FIRE & EXPLOSION FROM FLAMMABLE PRODUCTS.
PSCO OBSERVED 02 EXPLOSION PROOF ENCLOSURES IN CARGO SUBCOOLER ROOM THAT WERE NOT PROPERLY SEALED.
{93 IGC 10.1.2}
Deck/Cargo › Holds/Tanks › Valve, Pressure Vacuum Relief
Issued 6 April 2016
Resolved
Pressure relief valve should be set and sealed by a competent authority acceptable to the administration and a record of this action, including the valves of set pressure should be retained aboard the ship. The #2 cargo safety relief valve (#22619) is not sealed. Vessel could not provide port state control officers with a record of relief valve settings.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Emergency Shut-down
Issued 6 April 2016
Resolved
Emergency shutdown valves in liquid lines should fully close under all service conditions within 30 seconds of actuation. Port state control officers observed all 8 (4 port and 4 starboard) manifold liquid lines took 32 to 35 seconds to close after activating the emergency shutdown.
Deck/Cargo › Holds/Tanks › Fixed Gas Detection
Issued 6 April 2016
Resolved
The gas detection equipment should be capable of sampling and analysing for each sample head location sequentially at intervals not exceeding 30 minutes. Port state control officers obeserved an open valve in the cabinet of gas sample system which was diluting the samples. This prevented the system from showing an accurate reading from any of the sample points.
Deck/Cargo › Vapor Control Systems › Vapor Destruction Unit
Issued 6 April 2016
Resolved
Unless a cargo tank carrying LNG can withstand the pressure build up due to boil-off for 21 days, the pressure in the cargo tank must be maintained below the set pressure of the safety relief valve for at least 21 days by a waste heat or catalytic furnace. Following a test of the master gas valve for the gas combustion unit, the crew could not restart the gas combustion unit.
Ownership record
The Coast Guard's documentation record for this hull -- the Abstract of Title,
with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National