Records from 2012 to 2026. Most recent: inspection, 12 January 2026.
Documentation record
Registered dimensions (L × B × D)297.5 ft × 54.0 ft × 13.0 ft
Registered tonnagegross 1,754 / net 1,754
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderCONRAD SHIPYARD LLC · MORGAN CITY, LA, UNITED STATES · built 2012
Hull materialSteel
PropulsionNot recorded
Hull shapeBox
Hull configurationMonohull
Hailing portBALTIMORE, MD
Trade endorsementsCoastwise, unrestricted, Registry, non-fishing vessel
DocumentationValid · issued 30 January 2026 · expires 31 January 2027
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it1754 - Simplified, Gross Ton
1754 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 26
12 January 2026
Annual Inspection
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 8294637
25 November 2024
Periodic Inspection · Internal Structural Exam
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 8039461
29 February 2024
Deficiency Check
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7872166
3 January 2024
Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7845207
2 February 2023
Annual Inspection · MTSA Verification · Deficiency Check · Administrative Inspection
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 7631208
19 November 2021
Internal Structural Exam · Cargo Tank Internal · Hull Examination · COI Inspection
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 7353065
15 February 2021
MTSA Verification · Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7141188
13 February 2020
Annual Inspection · MTSA Verification
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6920771
29 October 2019
Internal Structural Exam
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 6840633
6 February 2019
MTSA Verification · Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6621819
2 October 2018
Damage Survey · Deficiency Check
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 6554569
17 April 2018
Damage Survey · Examination of Repairs
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 6397265
2 February 2018
Annual Inspection · MTSA Verification
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6349583
20 October 2016
MTSA Verification · Internal Structural Exam · Drydock Exam · COI Inspection · Cargo Tank Internal
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 6026477
19 July 2016
Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 5949388
15 September 2015
Type not recorded
No type recorded · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 5719737
22 April 2015
MTSA Verification · SIP Inspection/Audit
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 5103569
22 April 2015
Internal Structural Exam
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 5108646
14 July 2014
Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 4922441
28 March 2014
Damage Survey · Examination of Repairs
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 4824811
20 March 2014
Type not recorded
No type recorded · Sector Virginia · USCG East District (CGD-E) · Activity 4819524
18 March 2014
Deficiency Check · Examination of Repairs · Damage Survey
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 4818230
26 November 2013
Damage Survey
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 4759436
25 November 2013
Type not recorded
No type recorded · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 4760264
16 July 2013
SIP Initial Entry · MTSA Verification
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 4639599
14 February 2012
Hull Examination · Initial Certification · Drydock Exam · Administrative Inspection · Internal Structural Exam
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 4294973
02 - Structural Conditions › N/A - No Subsystem › Beams, frames, floors-op. damage
Issued 25 November 2024
No resolution recorded
Scantlings, material, and workmanship, subdivision of
cargo spaces, fitting of cofferdams, and testing of
tanks shall be at least equivalent to the requirements
of the American Bureau of Shipping or other recognized
classification society. (02) broken welds were found on
diagonal shock absorber located in the bow rake void.
Repair at next credit drydock. 46 CFR 32.60-1(a)
Action required: 705 - Other - as specified
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 25 November 2024
No resolution recorded
Non-welded valves complying with the standards listed in
§ 56.60-1 may be used within the specified pressure and
temperature ratings of those standards, provided the
limitations of § 56.07-10(c) are applied. Materials must
comply with subpart 56.60. Welded valves complying with
the standards and specifications listed in § 56.60-1 may
be used in Class II systems only unless they meet
paragraph (c) of this section. (02) wasted gasoline vent
handles located amidships on main deck were identified.
Repair at next credit drydock. 46 CFR 56.20-1(b)
Action required: 705 - Other - as specified
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 3 January 2024
Resolved
All valves, flanges, fittings, and accessory equipment shall be of a type suitable for use with liquefied flammable gases, and shall be made of steel or grade A malleable iron, acceptable for the service temperature and pressure according to the requirements of part 56 of subchapter F (Marine Engineering) of this chapter. Other materials may be specially considered and approved by the Commandant.
Residual tank needing two new ball valve handles.
46CFR38.10-1(a)
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 3 February 2024
Resolved 29 February 2024
Resolution: New valves added.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 3 January 2024
Resolved
Approved fire extinguishing systems must be installed on all tankships in the following locations. Previously approved installations may be retained as long as they are maintained in good condition to the satisfaction of the Officer in Charge, Marine Inspection. All (03) extinguishers not properly marked with the inspected date.
46CFR34.05-5(a)
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 29 February 2024
Resolution: All extinguishers properly marked.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 3 January 2024
Resolved
Piping, including valves, pipe fittings and flanges, conveying vapors, gases or liquids whose temperature exceeds 150 °F., shall be suitably insulated where necessary to preclude injury to personnel. Lagging on generator not properly covering turbo.
46CFR56.50-1(k)
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 3 February 2024
Resolved 29 February 2024
Resolution: Lagging added.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo operation
Issued 2 February 2023
Resolved
Each vessel vapor connection flange face must have a permanent stud projecting outward that has a 12.7 millimeter (0.5 inch) diameter and is at least 25.4 millimeters (1 inch) long. Port side VCS manifold flange's stud is sheared off. Barge is transfer restricted for any cargo that requires a VCS connection on the port side. Company is to submit a repair proposal to the OCMI.
46CFR39.2001(j)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 2 March 2023
Resolved 30 June 2023
Resolution: Received objective evidence stud was welded to the VCS manifold flange.
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 28 March 2014
Resolved
Port cargo tank #4 had a cracked weld where the tank top meets the re-inforcement plate on the port aft corner.
Action required: 701 - Prior to carriage of passengers/cargo
Due 31 March 2014
Resolved 31 March 2014
Resolution: All repairs complete, final weld test performed on main cargo tank and both voids.
Construction/Loadline › Structures › Trunk
Issued 14 March 2014
Resolved
Prior to cargo operations, vessel shall be made available for inspection due to suspected crack in the #4 starboard cargo tank at intersection of deck and tank trunk. Any repairs shall be made to the satisfaction of the attending CG Marine Inspector.
Action required: 705 - Other - as specified
Due 14 March 2014
Resolved 24 March 2014
Resolution: Repairs completed. All sat. See MSLE activity.
Construction/Loadline › Hull › Hull Plating
Issued 26 November 2013
Resolved
During prep for bunkering, tanker man discovered a sheen in water and a small crack In tank top In Way Of#4 Tank and Trunk Intersection. Depart CATO Oil in Salisbury, MD. and Proceed directly to Fairfield MD for gas freeing and continued damage assessment and subsequent repairs at General Ship, Baltimore MD.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 28 November 2013
Resolved 28 November 2013
Resolution: Repairs corrected. see inspection narrative and documents section of activity.