Records from 2012 to 2026. Most recent: inspection, 23 April 2026.
Documentation record
Registered dimensions (L × B × D)297.5 ft × 54.0 ft × 12.0 ft
Registered tonnagegross 1,619 / net 1,619
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderTRINITY MARINE PRODUCTS INC PLANT 296 · ASHLAND CITY, TN, UNITED STATES · built 2012
Hull materialSteel
PropulsionNot recorded
Hull shapeBox
Hull configurationMonohull
Hailing portBOWLING GREEN, KY
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 13 January 2026 · expires 28 February 2027
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it1619 - Simplified, Gross Ton
1619 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 21
23 April 2026
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 8354944
2 March 2026
Examination of Repairs · MTSA Verification · Cargo Tank Internal · Internal Structural Exam · COI Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 8316450
26 June 2025
Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 8168589
25 June 2024
Periodic Inspection · Administrative Inspection
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 7942511
22 May 2023
Annual Inspection · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7693976
8 June 2022
Administrative Inspection · MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7471786
17 May 2021
Administrative Inspection
Administrative · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 7198986
29 January 2021
Internal Structural Exam · Drydock Exam · MTSA Verification · Examination of Repairs · COI Inspection · Cargo Tank Internal
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7133007
4 May 2020
MTSA Verification · Administrative Inspection · Periodic Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 6948061
13 June 2019
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Huntington · USCG Heartland District (CGD-H) · Activity 6752395
10 May 2018
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Huntington · USCG Heartland District (CGD-H) · Activity 6411264
1 July 2017
Examination of Repairs · Damage Survey
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6196278
25 April 2017
Deficiency Check · Examination of Repairs · Internal Structural Exam · COI Inspection · MTSA Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6129919
1 March 2017
Special · Administrative Inspection
Administrative · Marine Safety Unit Huntington · USCG Heartland District (CGD-H) · Activity 6109138
29 February 2016
Annual Inspection · Administrative Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5822002
29 May 2015
Administrative Inspection
Administrative · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 5138831
28 May 2015
Periodic Inspection · MTSA Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5132021
20 February 2015
Type not recorded
No type recorded · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 5072243
20 February 2015
Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 5072253
1 May 2014
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4845969
23 January 2012
Hull Examination · Cargo Tank Internal · Initial Construction-Excluding Oversight · Initial Certification · MTSA Verification · Administrative Inspection · Internal Structural Exam
Physical examination · Marine Safety Detachment Nashville · USCG Heartland District (CGD-H) · Activity 4230188
Documentation › Safety/Response Plans/Programs › Vessel Response Plan
Issued 10 May 2018
Resolved
The operator of the unmanned tank barge did not have the required Vessel Response Plan documents on board as required in 33 CFR 155.1030 (i)(2).
Obtain and store required documents prior to transiting a loaded barge.
Action required: 701 - Prior to carriage of passengers/cargo
Due 10 June 2018
Resolved 11 May 2018
Resolution: VRP documents were placed on board vessel.
Construction/Loadline › Hull › Side Shell
Issued 3 July 2017
Resolved
Vessel was involved in marine casualty. STBD #5 W/T sideshell damaged. Repair to the satisfaction of attending marine inspector. see 835 for details.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 2 August 2017
Resolved 14 July 2017
Resolution: air tested #5 STBD W/T. Repairs conducted satisfactory, all items welded and repairs in accordance with existing structures.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 21 March 2017
Resolved
Certifacate May exspire while in trasit to New Orleans Area. Viod,bow and stern clean and dry. Cargo tanks empty NOT clean or Gas free.GS
Action required: 705 - Other - as specified
Due 18 April 2017
Resolved 26 July 2017
Operations/Management › Pollution › Compliance with Transfer Procedures
Issued 29 February 2016
Resolved
Vessel did not have all required sections of transfer procedures as per 33CFR155.750.
Due 14 March 2016
Resolved 2 March 2016
Resolution: Received email with full transfer procedures attached