BLOCK ISLAND is a 2012 freight ship. The Coast Guard has recorded 6 inspections since 2016, most recently in March 2023, along with 3 deficiencies.

Records from 2016 to 2023. Most recent: inspection, 24 March 2023.

Built
2012
Last inspected
24 March 2023
Documentation
Not in the documentation file of 10 September 2026
Controls
None recorded without a removal date

Identity

9614969 View on MarineTraffic leaves Maury; a third-party site, nothing from it is stored here
1269014
Flag
HONG KONG
—
Maury page id
psix-1269014

Inspections, by type

…with no type recorded1
Years with a record 5 calendar years (2016–2023)
The 6 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

This record may be incomplete: the most recent inspection recorded for this vessel was 3 years ago. Maury shows what the Coast Guard recorded, not whether the vessel has been inspected since, is still in service, or what condition it is in. Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Bulk Carrier class in Maury's sources begin in 1981.

Documentation record

Tonnage as PSIX records it34795 - Convention (Subpart B), Gross Ton
61442 - Dead Weight, Metric Ton
72322 - Displacement, Metric Ton
20209 - Convention (Subpart B), Net Ton
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.

Radio station licence

No FCC ship-station licence is recorded against this Official Number in the file of 6 September 2026. That is a fact about the licence file, not about the radio.

A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.

Inspection history · 6

24 March 2023 PSC B
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 7647059
9 January 2022 Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7377474
31 March 2021 Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7166688
30 March 2021 COE-Administrative
Administrative · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7165831
22 July 2020 PSC B · Administrative Inspection
Physical examination · Sector Lake Michigan · USCG Great Lakes District (CGD-GL) · Activity 7013284
27 July 2016 PII Safety Exam · Ballast Water Examination · ISPS II Exam
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5941864

Deficiency record · 3

02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 24 March 2023 Resolved
Termination and joints in all conductors shall be so made as to retain the original electrical, mechanical, flame-resistant and, where necessary fire-resistant properties of the cable. PSCO observed 05 overhead lights with wiring terminated outside or a junction box the location of these lights are: forecastle, purifier space, generator flat, and in the vicinity of the MDE and workshop in the Engine room. 74 SOLAS (20) II-1 45/5.6
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 April 2023
Resolved 11 September 2023
Resolution: Received Class Survey indicating cable terminations were secured inside junction box.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 24 March 2023 Resolved
Termination and joints in all conductors shall be so made as to retain the original electrical, mechanical, flame-resistant and, where necessary fire-resistant properties of the cable. PSCO observed an electrical splice outside of a junction box in the galley. The splice was found on the power cable for the refrigerator. 74 SOLAS (20) II-1 45/5.6
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 April 2023
Resolved 11 September 2023
Resolution: Received Class Survey indicating that the cable was removed and replaced with new cable.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 24 March 2023 Resolved
Termination and joints in all conductors shall be so made as to retain the original electrical, mechanical, flame-resistant and, where necessary fire-resistant properties of the cable. PSCO observed a broken electrical junction box in the emergency generator room.
Condition: Damaged By Earlier Event
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 April 2023
Resolved 24 March 2023
Resolution: Broken junction box was replaced prior to the PSCO's departure.

Ownership record