Records from 2018 to 2024. Most recent: inspection, 6 June 2024.
11 - Life Saving Appliances › N/A - No Subsystem › Lifeboats
Issued 6 June 2024
Resolved
11101 - Lifeboats - Cargo ships shall carry one or more totally enclosed lifeboats complying with the requirements of section 4.6 of the code... The engine shall be capable of operating for not less then 5 min after starting from cold with the lifeboat out of the water. Vessel master notified PSCO that vessels freefall lifeboat was inoperable. 74SOLAS(20)III/31.1.1.1 LSA CH IV 4.4.6.3 - 10c
Action required: 10 - Deficiency Rectified
Resolved 6 June 2024
14 - Pollution Prevention › 148 - Ballast Water › Ballast Water Management System (BMWS)
Issued 6 June 2024
Resolved
CG006 - Ballast Water Managenebt System - After evaluation of an application the Coast Guard will advise the applicant in accordance with 46CFR159.005-13 whether the BWMS is approved. If the BWMS is approved a certification number will be issued and an approval certificate sent to the applicant in accordance with 46CFR2.75-5. The approval certificate will list conditions of approval applicable to BWMS. PSCO found that the vessel did not possess a US Coast Guard type approval letter for its ballast water treatment system after the compliance dates set forth in 33CFR151.2035(b) were exceeded. 46CFR162.060-10(g) - 50ac
Action required: 50 - Rectify deficiencies w/in 30 days
Due 6 July 2024
Resolved 6 June 2024
Resolution: VESSEL PROVIDED USCG TYPE APPROVAL CERTIFICATE.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 4 March 2021
Resolved
The purpose of this regulation is to prevent the ignition of combustible materials or flammable liquids for the purpose the following requirements must be met. Means shall be provided to control the leaks of flammable liquids. The emergency generator fuel tank low level sensor is leaking fuel oil. 74 SOLAS (14) II-2/4.1.1
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 18 March 2021
Resolved 15 March 2021
Resolution: Received class report stating one low level sensor of MGO tank for emergency generator engine was replaced and found in satisfactory.
02 - Structural Conditions › N/A - No Subsystem › Bulkheads - operational damage
Issued 4 March 2021
Resolved
Ships shall be designed constructed and maintained in compliance with the structural, mechanical, and electrical requirments of a classification society which is recognized by the administration. Insets were found near the port side #5 cargo hold and starboard aft quarter. 74 SOLAS (14) II-1/3-1
Condition: Damaged By Earlier Event
Action required: 16 - Rectify deficiencies w/in 14 days
Due 18 March 2021
Resolved 15 March 2021
Resolution: Received class report stating the damaged areas shall be permanently repaired at next dry dock but no later than 10FEB2022.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 4 March 2021
Resolved
Every steam pipe and every fitting connected thereto through which steam may pass. shall be so designed constructed and installed as to withstand the maxximum working stresses to may be subjected. Steam pipe oil heater for purifier is leaking. 74 SOLAS (14) II-1/33.1
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 4 March 2021
Resolved 4 March 2021
Resolution: Crew repaired steam pipe and no leak was detected after repair.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 27 September 2018
Resolved
9900: IF exceptional circumstances required deviation from the Ballast Water Management Plan, the details surrounding the need for deviation and asociated actions must be explained. The signature requirement may be satisfied by affirming the ciertification portion of the electronic ballast water report. Vessels plan only authorizes flow through method, however the vessel used sequential method. 33CFR151.2070(a)(2) [Code 10a]
Action required: 10 - Deficiency Rectified
Resolved 27 September 2018
Resolution: Corrected immediately