LVM AARON is a 2014 tank ship. The Coast Guard has recorded 10 inspections since 2016, most recently in July 2026, along with 4 deficiencies and 1 operational control.
Records from 2016 to 2026. Most recent: inspection, 10 July 2026.
Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Tank Ship class in Maury's sources begin in 2016.
Every line above is a count of records the US Coast Guard wrote, or a date it recorded.
A blank resolution means none was recorded in this data; it does not establish that a
deficiency is outstanding. Years with a record are calendar years in which a record
exists, not years in service. What Maury does
not do.
Tonnage as PSIX records it13885 - Convention (Subpart B), Net Ton 50926 - Dead Weight, Metric Ton 61929 - Displacement, Metric Ton 30264 - Convention (Subpart B), Gross Ton
This hull's Official Number is not in the NVDC file dated 10 August 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.
Vessel history report
Every record for this hull, in one document — $299
Every recorded inspection, 2016 to
2026 for this class, in one chronology · every deficiency, with system, dates
and resolution · operational controls imposed and removed · every name this
hull has been recorded under · the vessels it was inspected alongside, and when
· how its record compares with hulls of similar age and size, as a fact about the
population and never a judgement about this vessel.
This report is in development and is not for sale yet. There is
no date, and nothing is charged. Leave an email and we will tell you when it exists, once.
Used only to tell you when the report exists.
Not shared, not sold, and not added to a mailing list.
Inspection history · 10
10 July 2026COC-CHEM & TVE Renew · PSC B
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 8429830
20 September 2025Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 8237782
21 March 2025COC-CHEM & TVE Renew · PSC B
Physical examination · Sector Boston · USCG Northeast District (CGD-NE) · Activity 8091166
07 - Fire Safety › N/A - No Subsystem › Jacketed high pressure lines and oil leakage alarm
Issued 12 September 2019Resolved
The purrpose of this regulation is to prevent the ignition of a combustible materials or flammable liquids. For this purpose the following functional requirements shall be met: Means shall be provided to control leaks of flammable liquids. PSCO observed significant fuel leaks on MDE 3,4,5 and 6. 74SOLAS (14) Cons II-2/4.1.1
Action required: 60 - Rectify deficiencies prior to movement
Resolved 15 September 2019
Resolution: Received LR class report. All satisfactoy.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 12 September 2019Resolved
The machinery, boilers and other pressure vessels associated piping systems and fittings shall be of a design and construction adequate for the service for which they are intended and shall be so installed and protected as to reduce the minimum danger to any person onboard, due regard being paid to moving parts, hot surfaces and other hazards. PSCO observed leaking cylinder jacket cooling water on cylinder heads 3 & 5. 74 SOLAS (14) Cons II-1/26.1
Action required: 60 - Rectify deficiencies prior to movement
Resolved 15 September 2019
Resolution: Received LR class report. All satisfactoy.
Internal combustion engines of 2,250KW and above or having cylinders of more than 300mm bore shall be provided with crankcase oil mist detectors or engine bearing temperature monitors. PSCO observed two inoperable oil mist detectors that require replaceing. 74 SOLAS (14) cons II-1/47.2
Action required: 60 - Rectify deficiencies prior to movement
Resolved 15 September 2019
Resolution: Received LR class report. All satisfactoy.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Atmosphere testing instruments
Issued 12 September 2019Resolved
The company should establish procedures, plans and instructions including checklist as appropriate for key shipboard operations concerning the safety of the personnel and ship. In accoradance with the vessel's SMS procedures the vessels ballast tanks gas detection system shall be in continuous use. The PSCO found the vessels's ballast tank gas sampling system was turned off even though the vessel's cargo tanks are fully loaded. Provide a corrective action plan with concurrence of the shipboard SMS and to satisfaction of the vessel's clasification society. 74SOLAS (14) cons. IX/3 ISM Code A/7
Action required: 50 - Rectify deficiencies w/in 30 days
Due 12 October 2019
Resolved 15 September 2019
Resolution: Received LR class report. All satisfactoy.
Ownership record
The Coast Guard's documentation record for this hull -- the Abstract of Title,
with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National
Vessel Documentation Center, files it here with its date, and every reader of this page gets it.