MAURY USCG vessel records
← All vessels

EVER LYRIC

EVER LYRIC is a 2015 freight ship. The Coast Guard has recorded 6 inspections since 2016, most recently in June 2022, along with 3 deficiencies.

Records from 2016 to 2022. Most recent: inspection, 28 June 2022.

Built
2015
Last inspected
28 June 2022
Documentation
Not in the documentation file of 10 August 2026
Controls
None recorded without a removal date

This record may be incomplete: the most recent inspection recorded for this vessel was 4 years ago. Maury shows what the Coast Guard recorded, not whether the vessel has been inspected since, is still in service, or what condition it is in. Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the General Dry Cargo Ship class in Maury's sources begin in 2016.

Inspection record

Last inspected 28 June 2022
Operational controls None recorded without a removal date
Years with a record 5 calendar years (2016–2022)
Every line above is a count of records the US Coast Guard wrote, or a date it recorded. A blank resolution means none was recorded in this data; it does not establish that a deficiency is outstanding. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Identity

9629108
1377318
Flag
TAIWAN
Maury page id
psix-1377318

Documentation record

Tonnage as PSIX records it49583 - Convention (Subpart B), Net Ton
138795 - Displacement, Metric Ton
103891 - Dead Weight, Metric Ton
101063 - Convention (Subpart B), Gross Ton
This hull's Official Number is not in the NVDC file dated 10 August 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.
Vessel history report

A report is not offered for this hull. Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. What a sparse-record report looks like.

Inspection history · 6

28 June 2022 PSC B
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7489467
30 December 2020 Administrative Inspection
Administrative · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7117807
17 August 2020 Administrative Inspection
Administrative · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7035611
6 June 2019 PII Safety Exam · Ballast Water Examination · ISPS II Exam
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6705409
7 June 2018 ISPS II Exam · PII Safety Exam · Ballast Water Examination
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6436709
12 January 2016 PII Safety Exam · ISPS II Exam · Ballast Water Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5795689

Deficiency record · 3

07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 28 June 2022 Resolved
The purpose of this regulation is to precvent the ignition of combustible material or flammable liquids. For this purpose, the folllowing requirements shall be met: means shall be provided to control leaks of flammable liquids. PSCO observed lube and hydraulic oil leakage in multiple locations around the main diesel engine. SOLAS (20) II-2/4.1.1
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 1 July 2022
Resolved 1 July 2022
Resolution: Received report from Class NK attesting to the cleaning of oil around the main diesel engine.
09 - Working and Living Conditions › 092 - Working Conditions › Steam pipes and pressure pipes
Issued 28 June 2022 Resolved
Every steam pipe and every fitting connected thereto through which steam may pass shall be so designed, constructed, and installed as to withstand the maximum working stresses to which it may be subjected. PSCO observed purifier and boiler steam lines leaking hot air from the flanges. Additionally, the steam drain water from the boiler was damaged and leaking water.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 12 July 2022
Resolved 1 July 2022
Resolution: Received report from Class NK attesting to the tightening of steam line flanges and installation of new lagging around the boiler drain line.
09 - Working and Living Conditions › 092 - Working Conditions › Pipes, wires (insulation)
Issued 28 June 2022 Resolved
Machinery, boilers, and other pressure vessels, associated piping systems, and fittings shall be of a design and contruction adequate for the service for which they are intended and shall be so installed and protected as to reduce to a minimum any danger to persons on board. PSCO observed lagging in multiple areas throughout the engine room. Lagging associated with main diesel engine was soaked through with oil.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 12 July 2022
Resolved 1 July 2022
Resolution: Received report from Class NK attesting to the replacement of lagging around the main diesel engine previously found to be soaked with oil.

Ownership record