Records from 2018 to 2024. Most recent: inspection, 25 November 2024.
Inspection history · 9
25 November 2024
Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8039837
27 October 2024
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8025192
10 June 2024
Ballast Water Examination · In-Service Inspection
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 7931694
5 June 2024
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 7928852
1 May 2023
PSC B
Physical examination · Marine Safety Unit Brownsville · USCG Heartland District (CGD-H) · Activity 7670455
1 May 2023
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 7678771
5 April 2021
PSC B · Deficiency Check
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7169120
13 December 2018
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6597313
12 December 2018
ISPS II Exam · Ballast Water Examination · PII Safety Exam
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6596390
14 - Pollution Prevention › 148 - Ballast Water › Extraordinary Condition Claims
Issued 27 October 2024
Resolved
The master, owner, operator, agent, or person in charge of a vessel equipped with ballast tanks that operates in the waters of the United States must employ one of the authorized ballast water management methods listed in 33 CFR 151.2025(a). Vessel’s ballast water management system is inoperable. Vessel has been granted an extraordinary circumstance to employ the ballast water management method listed in 33 CFR 151.2025(a)(3) to conduct cargo operations while in the Sector New Orleans COTP Zone. In accordance with 33 CFR 151.2040(b)(3), the vessel must discharge only that amount of ballast water operationally necessary to ensure the safety and stability of the vessel for cargo operations. 33 CFR 151.2025(a)
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 25 November 2024
Resolution: PSC NOLA received a class report from issuing entity satisfying the requirement.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 1 May 2023
Resolved
74 SOLAS (20) II-2/4.1
THE PURPOSE OF THIS REGULATION IS TO PREVENT THE IGNITION OF COMBUSTIBLE MATERIALS OR FLAMMABLE LIQUIDS. FOR THIS PURPOSE, MEANS SHALL BE PROVIDED TO CONTROL LEAKS OF FLAMMABLE LIQUIDS.
PSCO OBSERVED LEAKS COMING FROM THE FUEL INJECTOR ON THE #5 CYLINDER OF BOTH THE #1 AND #2 SHIP SERVICE DIESEL GENERATORS.
Action required: 15 - Rectify deficiencies by next port
Resolved 5 May 2023
Resolution: Vessel provided class report attesting to the repair of both #5 fuel injectors on the #1 and #2 SSDG.
07 - Fire Safety › N/A - No Subsystem › International shore-connection
Issued 1 May 2023
Resolved
74 SOLAS (20) II-2/10.2.1.7 ... FSS CODE CHAP. 2, 2.2
SHIPS OF 500 GROSS TONNAGE AND UPWARDS SHALL BE PROVDED WITH AT LEAST ONE INTERNATIONAL SHORE CONNECTION COMPLYING WITH THE FIRE SAFETY SYSTEM CODE. PSCO OBSERVED THE PORT SIDE INTERNATIONAL SHORE CONNECTION ASSEMBLY TO BE MISSING THE ERQUIRED GASKET.
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 1 May 2023
Resolved 1 May 2023
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 6 April 2021
Resolved
The following fire protection systems shall be kept in good order so as to ensure required performance if a fire occurs:structural fire protection. The insulation on the A60 fire boundary from the galley to the ships stores was damaged in multiple areas.
74 SOLAS (14) II-2/14.2.1.1.1
Action required: 17 - Rectify deficiencies prior to departure
Resolved 9 April 2021
Resolution: Received class report attesting to repairs.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 6 April 2021
Resolved
All life saving appliances shall be fit with retro-reflective material where it will assist in detection. PSCO observed deteriorated retro-reflective tape on the lifeboat, rescue boat, and multiple life buoys rendering it ineffective.
74 SOLAS (14) III/34, LSA 1.2.2.7
Action required: 17 - Rectify deficiencies prior to departure
Resolved 9 April 2021
Resolution: Received class report attesting to repairs.
11 - Life Saving Appliances › N/A - No Subsystem › Immersion suits
Issued 6 April 2021
Resolved
Stowage locations for life-saving equipment shall be marked with symbols. Numerous symbols marking the location of life saving equipment were faded.
74 SOLAS (14) III/20.10
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 9 April 2021
Resolution: Received class report attesting to repairs.