Records from 2017 to 2026. Most recent: inspection, 23 March 2026.
Inspection history · 20
23 March 2026
Vessel Attendance · Annual Inspection · Administrative Inspection
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 8351267
3 March 2025
Annual Inspection · Administrative Inspection
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 8087598
5 February 2025
Simplified Stability Test
Physical examination · Marine Safety Center (MSC) · Activity 8080587
13 November 2024
Administrative Inspection · Special Consideration · Drydock Exam · Internal Structural Exam
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 8031951
13 November 2024
Simplified Stability Test · Special · Administrative Inspection
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 8036629
2 April 2024
Annual Inspection
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 7888890
18 January 2024
Administrative Inspection
Administrative · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 7850861
20 June 2023
Administrative Inspection
Administrative · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 7719197
24 April 2023
Deficiency Check
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 7674349
17 April 2023
Annual Inspection
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 7670973
8 March 2023
Drydock Exam · Internal Structural Exam
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 7648093
30 March 2022
COI Inspection · Administrative Inspection · DAPI Audit · Deficiency Check
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 7415553
9 March 2021
Annual Inspection · Internal Structural Exam · Drydock Exam
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 7152642
18 June 2020
Administrative Inspection · DAPI Audit · Annual Inspection
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 7001559
18 April 2019
Annual Inspection · Administrative Inspection · DAPI Audit
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 6668652
7 February 2019
Hull Examination · Administrative Inspection
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 6621894
13 September 2018
Administrative Inspection · Annual Inspection · DAPI Audit
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 6542538
23 March 2017
DAPI Audit · Deficiency Check · COI Inspection · Administrative Inspection
Physical examination · Marine Safety Detachment Panama City · USCG Heartland District (CGD-H) · Activity 6105482
6 March 2017
Simplified Stability Test
Physical examination · Marine Safety Center (MSC) · Activity 6109701
2 January 2017
Construction Oversight · Initial Certification
Physical examination · Marine Safety Unit Portland OR · USCG Northwest District (CGD-NW) · Activity 6064697
01 - Certificates & Documentation › 013 - Documents › Stability Information Booklet
Issued 13 November 2024
Resolved
Any alterations or modifications including, but not limited to the removal, replacement, or addition of weight will invalidate the stability letter.
The vessel has completed some major alterations that was not reported. Most notably,
1. Removed the paddlewheel & associated cross members brackets.
2. Removed all (10) pedal cycles & associated drive chain gearing.
3. Installed a railing on the stern where the paddlewheel was removed.
4. Installed tiki thatched roofing material.
5. Installed a ladder on the stern.
6. Installed approximately 200 pounds of lead ballast weight aft/forward of the outboard engine.
7. Repowered the outboard engine.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 5 February 2025
Resolution: A PSST has been completed. Amended COI has been provided.
05 - Radio Communications › N/A - No Subsystem › VHF radio installation
Issued 17 April 2023
Resolved
Comply with requirements of the FCC. DSC VHF radio function was not programmed.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 18 May 2023
Resolved 24 April 2023
Resolution: DSC VHF radio function was not programmed.
02 - Structural Conditions › N/A - No Subsystem › Stability/strength/loading information and instruments
Issued 30 March 2022
Resolved
Owner modified vessel canopy, increasing vessels sail area. Restore to original or complete a new stability test prior to carrying passengers.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 9 June 2022
Resolution: Canopy modification removed.
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 30 March 2022
Resolved
Vessels navigation lights were inoperative. Prove proper operation.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 9 June 2022
Resolution: Nav lights repaired and operational.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 28 February 2017
Resolved
COMPLETE A NEW TO ZONE INSPECTION AND THE ATTACHED WORKLIST DATED 28 FEB 2017 TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR PRIOR TO THE CARRIAGE OF PASSENGERS.
Action required: 701 - Prior to carriage of passengers/cargo
Due 28 March 2017
Resolved 30 March 2017