Records from 2017 to 2026. Most recent: inspection, 23 February 2026.
Inspection history · 20
23 February 2026
Type not recorded
No type recorded · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8314586
22 February 2026
In-Service Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8313986
22 February 2026
Type not recorded
No type recorded · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8314328
21 July 2025
PSC B · Deficiency Check
Physical examination · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 8188122
11 July 2025
Administrative Inspection
Administrative · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 8186425
7 August 2023
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 7762205
10 May 2023
PSC B
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7680108
18 June 2020
PSC B
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6973650
11 October 2018
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6558947
25 September 2018
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6548245
21 July 2018
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6486258
16 July 2018
In-Service Inspection · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6480966
5 July 2018
Ballast Water Examination · PII Safety Exam · ISPS II Exam
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6467138
4 July 2018
Type not recorded
No type recorded · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6466712
2 July 2018
Type not recorded
No type recorded · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6464882
2 June 2017
Deficiency Check
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 6163800
1 June 2017
Ballast Water Examination
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 6162399
1 June 2017
Type not recorded
No type recorded · Sector Mobile · USCG Heartland District (CGD-H) · Activity 6168962
25 May 2017
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6155198
27 February 2017
PII Safety Exam · ISPS II Exam · Ballast Water Examination
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6092017
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 22 February 2026
Resolved
In addition to the requirements contained elsewhere in the present regulations, ships shall be designed, constructed and maintained in compliance with the structural, mechanical & electrical requirements. PSO received report that vessel experienced a loss of power twice while inbound to the port of Baltimore.
SOLAS II-I/3-1
Condition: Design Flaw
Action required: 60 - Rectify deficiencies prior to movement
Due 22 February 2026
Resolved 25 February 2026
Resolution: Class Attested to repair. See Class report.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Covers (hatchway-, portable-, tarpaulins, etc.)
Issued 21 July 2025
Resolved
03105 The construction and the means for securing the weather tightness of cargo and other hatchways in positions 1 and 2. Hydraulic piping for cargo hold #4 is currently being serviced making the hatch inoperable. ICLL 1/14.1 40ac
Condition: Improper/Lack of Maintenance
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Due 22 July 2025
Resolved 22 July 2025
Resolution: Repairs made to hatch cover for cargo hold #4 attested to by class.
07 - Fire Safety › N/A - No Subsystem › Fire control plan
Issued 21 July 2025
Resolved
07122 Fire plan and booklets shall be kept up to date, any alterations thereto shall be recorded as soon as practicable. The rope room has been modified as an ISPS room, resulting in the "A" class boundary being modified. 74SOLAS24 II-2/15.2.4.1 40ac
Condition: Improper Installation
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Due 22 July 2025
Resolved 30 July 2025
Resolution: Ship submitted satisfacotry class report attesting to the repairs to the room.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 21 July 2025
Resolved
Where necessary, non conducting mats or gratings shall be provided at the front and rear of the switchboard. Switchboard behind the ECR had storage underneath and was missing non conductive matting. 74SOLAS(24) II-1/45.2 10c
Condition: Improper Installation
Action required: 10 - Deficiency Rectified
Due 21 July 2025
Resolved 21 July 2025
Resolution: The storage was removed and the matting was installed.
Operations/Management › Ballast Water Managment › Alternative Management Method
Issued 1 June 2017
Resolved
Master must ensure that the ballast water discharge standard. Crew discharged raw untreated ballast water into North America ECA Waters in the Port of Mobile, Alabama without utilizing the approved onboard treatment system.
Condition: Placed in Improper Service
Action required: 60 - Rectify deficiencies prior to movement
Due 2 June 2017
Resolved 2 June 2017
Resolution: Vessel utilized onboard ballast water treatment sytem to conduct the rest of the ballast water discharge.