MAURY USCG vessel records
← All vessels

MARAN GAS ULYSSES

MARAN GAS ULYSSES is a 2017 tank ship. The Coast Guard has recorded 12 inspections since 2017, most recently in July 2026, along with 1 deficiency.

Records from 2017 to 2026. Most recent: inspection, 28 July 2026.

Built
2017
Last inspected
28 July 2026
Documentation
Not in the documentation file of 10 August 2026
Controls
None recorded without a removal date

Identity

9709491
1431665
Flag
GREECE
Maury page id
psix-1431665

Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Tank Ship class in Maury's sources begin in 2016.

Inspections, by type

…with no type recorded4
Years with a record 8 calendar years (2017–2026)
Every line above is a count of records the US Coast Guard wrote, or a date it recorded. The counts in the strip above are the same counts; this table splits the inspections by the kind of activity recorded. A blank resolution means none was recorded in this data; it does not establish that a deficiency is outstanding. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Documentation record

Tonnage as PSIX records it113502 - Convention (Subpart B), Gross Ton
92621 - Dead Weight, Metric Ton
128190 - Displacement, Metric Ton
37136 - Convention (Subpart B), Net Ton
This hull's Official Number is not in the NVDC file dated 10 August 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.
Vessel history report

A report is not offered for this hull. Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. What a sparse-record report looks like.

Inspection history · 12

28 July 2026 PSC B · COC-GAS Renew
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8463246
1 August 2025 COC-GAS Annual · PSC B
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 8196454
18 March 2025 Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 8090606
5 August 2024 PSC B · COC-GAS Renew
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7965044
25 July 2023 PSC B · COC-GAS Annual
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7745736
1 July 2022 PSC B · COC-GAS Renew
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7485887
23 June 2021 Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7225052
25 February 2021 COC-GAS Renew · PSC B · Ballast Water Examination
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7143113
24 February 2021 Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7144782
17 February 2021 Type not recorded
No type recorded · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 7141728
31 August 2019 ISPS II Exam · COC-GAS Renew · Ballast Water Examination · COE-Offshore
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6794917
7 December 2017 COC-GAS Renew · Ballast Water Examination · ISPS II Exam
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6318559

Deficiency record · 1

07 - Fire Safety › N/A - No Subsystem › Operation of Fire protection systems
Issued 2 July 2022 Resolved
Ships carrying flammable or toxic products, a water spray system for cooling, fire prevention and crew protection should be installed. Spray system for above locations was inoperable due to secured valve. IGC(93)/11.3.1.4
Action required: 10 - Deficiency Rectified
Due 2 July 2022
Resolved 2 July 2022
Resolution: Def rectified on the spot.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.