Records from 2017 to 2025. Most recent: inspection, 25 March 2025.
Inspection history · 14
25 March 2025
Deficiency Check · Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 8097163
25 March 2024
Administrative Inspection · Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7884550
27 April 2023
Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7670518
28 March 2022
Internal Structural Exam · Annual Inspection · Hull Examination · Administrative Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7401919
24 May 2021
Administrative Inspection · COI Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7190956
3 August 2020
Administrative Inspection
Administrative · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 7023431
3 May 2019
Deficiency Check · Administrative Inspection · Annual Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6675883
26 April 2018
Administrative Inspection
Administrative · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6400845
13 April 2018
Annual Inspection · Administrative Inspection · DAPI Audit
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6391009
20 March 2018
Examination of Repairs · Administrative Inspection
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6377403
23 May 2017
COI Inspection · Hull Examination · Administrative Inspection · Deficiency Check · Internal Structural Exam
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6156248
22 May 2017
Deficiency Check
Physical examination · Marine Safety Unit Portland OR · USCG Northwest District (CGD-NW) · Activity 6152681
15 May 2017
Administrative Inspection
Administrative · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 6147815
27 February 2017
Hull Examination · Inclining Experiment · Construction Oversight · Initial Certification
Physical examination · Marine Safety Unit Portland OR · USCG Northwest District (CGD-NW) · Activity 6144766
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 25 March 2025
Resolved
Propulsion machinery must be suitable in type and design for propulsion requirements of the hull in which it is installed and capable of operating at constant marine load under such requirements without exceeding its designed limitations. Stbd exhaust hose from center engine is leaking excessively. Repair prior to carrying passengers.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 7 April 2025
Resolution: Facetimed with O/O and verified water leak from Exhaust has been rectified.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 25 March 2025
Resolved
A submersible electric bilge pump may be used as a power bilge pump rprovided that A positive shutoff valve is installed at the hull penetration. Install positive shutoff valve at each bilge hose hull penetration.
Condition: Improper Installation
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 8 April 2025
Resolution: Received photo evidence of positive shutoff valves installed at each bilge overboard.
11 - Life Saving Appliances › N/A - No Subsystem › On board training and instructions
Issued 25 March 2025
Resolved
Placards containing instructions for the donning and use of the life jackets aboard the vessel must be posted in conspicuous places that are regularly accessible and visible to the crew and passengers. Several donning placards are peeling off. Renew lifejacket donning placards throughout the vessel.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 25 April 2025
Resolved 8 April 2025
Resolution: Received photo evidence of new lifejacket donning placards.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 11 April 2024
Resolved
An enclosed space containing machinery powered by gasoline must be equipped by flammable vapor detection device. The vapor detection device was not operable. Prove proper operation prior to carrying pax.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 13 May 2024
Resolution: Received video evidence of replaced and proper operation of vapour detection system.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 27 April 2023
Resolved
All engine exhaust pipes must be water cooled. Inspection found STBD engine inboard exhaust bellow leaking raw water.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 27 May 2023
Resolved 19 May 2023
Resolution: Cleared to the satisfaction of the Coast Guard marine inspector.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 7 May 2019
Resolved
Prove proper operation of engine room bilge high level visual and audio alarm.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 17 May 2019
Resolved 22 May 2019
Resolution: Deficiency cleared to the satisfaction of the marine inspector.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 7 May 2019
Resolved
Outfit ring life buoy with proper throw line.
Condition: Invalid
Action required: 705 - Other - as specified
Due 17 May 2019
Resolved 22 May 2019
Resolution: Deficiency cleared to the satisfaction of the marine inspector.
07 - Fire Safety › N/A - No Subsystem › Maintenance of Fire protection systems
Issued 7 May 2019
Resolved
Provide fixed fire system report with proper servicing and weights to service bottle in accordance with 46 CFR 176.810
Condition: Invalid
Action required: 705 - Other - as specified
Due 17 May 2019
Resolved 9 May 2019
Resolution: Deficiency was corrected to the satisfaction of a marine inspector.
07 - Fire Safety › N/A - No Subsystem › Ventilation
Issued 7 May 2019
Resolved
Prove proper operation of port engine room blower motor.
Action required: 10 - Deficiency Rectified
Due 7 May 2019
Resolved 7 May 2019
Resolution: Deficiency was corrected to the satisfaction of the attending marine inspector.
Lifesaving › Lifejacket/PFD (Type I) › Quantity
Issued 19 April 2018
Resolved
Ensure PFDs are on board in quantities specified on COI.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 27 April 2018
Resolution: Received email (photo) confirmation of sufficient numbers of PFDs onboard vessel.
Engineering › Bilge Water Management System › Hose
Issued 19 April 2018
Resolved
Ensure hand bilge pump discharge hose is long enough to discharge overboard.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 19 May 2018
Resolved 27 April 2018
Resolution: Received email (photo) documentation of lengthened discharge hose.
Engineering › Fuel Oil Storage/Transfer System › Piping
Issued 19 April 2018
Resolved
Add grounding conductor between metallic sections of fuel tank fill line spanning section of flexible hose.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 27 April 2018
Resolution: Received email confirmation (photos) showing bonding conductor added appropriately.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 8 May 2017
Resolved
Complete new to zone COI inspection for local operating area, IAW 46CFR 176.400
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Conducted COI/DDE/ISE in Branson, MO.
Documentation › Certificates/Documents › Certificate of Documentation (CG-1270)
Issued 8 May 2017
Resolved
Provide valid certificate of documentation IAW Part 67
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Verified COD was completed.
Operations/Management › Navigation Safety › Navigation Underway, General
Issued 8 May 2017
Resolved
Provide valid operator license for route and tonnage, IAW 46CFR 185.402
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Capt has appropriate endorsements for route.
Documentation › Certificates/Documents › Stability Letter
Issued 8 May 2017
Resolved
Provide valid stability letter for vessel, IAW 46CFR 176.306
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 12 June 2017
Resolution: Vsl received an approved Stability Ltr from MSC.
Operations/Management › Drug and Alcohol Testing › Proof of Enrollment
Issued 8 May 2017
Resolved
Provide proof of enrollment into approved drug and alchohol screening program, IAW 46CFR Part 16
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Capts and Deckhands are enrolled in DAPI.
Operations/Management › Drills/Instruction › Not Conducted
Issued 8 May 2017
Resolved
Log required emergency drills and instrution, IAW 46CFR 185.728
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Emergency drills conducted and logged.
Documentation › Markings/Placards › Capacity Marking
Issued 8 May 2017
Resolved
Display Small Passenger Vessel sticker, IAW 176.310
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 15 June 2017
Resolution: Issued SPV Sticker
Lifesaving › Lifejacket/PFD (Type I) › Quantity
Issued 8 May 2017
Resolved
Provide CG approved Type I life jackets for all passengers, and 10 percent Type I child life jackets, IAW 46CFR 180.71
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Verified 77 adult and 10 child lifejackets on board.
Lifesaving › Lifebuoys › Quantity
Issued 8 May 2017
Resolved
Provide ring buoy IAW 180.70
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Ring buoy and associated equipment present.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 8 May 2017
Resolved
Provide first aid kit, IAW 46CFR 184.710
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: First aid kit onboard.
Fire Fighting › Fire Bucket › Quantity
Issued 8 May 2017
Resolved
Provide three 2.5 gallong fire buckets, IAW 46CFR 181.610
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Verfied 3 fire buckets onboard.
Construction/Loadline › Markings › Vessel Name/Home Port
Issued 8 May 2017
Resolved
Provide hailing port on vessel, IAW part 67.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Verifed vsl name on the stern, and port and starboard sides of the vsl.
Electrical › Electrical Distribution System (service) › Wiring
Issued 8 May 2017
Resolved
Provide approved electrical drawings and respond accordingly to all comments and ensure they are addressed.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 22 May 2017
Navigation › Piloting/Steering › Marine Charts
Issued 8 May 2017
Resolved
Provide nautical publications for operating area, IAW 46CFR 184.420
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 May 2017
Resolution: Marine pubs present onboard.