Records from 2017 to 2023. Most recent: inspection, 9 March 2023.
Documentation record
Tonnage as PSIX records it81429 - Convention (Subpart B), Gross Ton
81429 - Regulatory (Subpart C or D), Gross Ton
50978 - Convention (Subpart B), Net Ton
50978 - Regulatory (Subpart C or D), Net Ton
156458 - Dead Weight, Metric Ton
182655 - Displacement, Metric Ton
This hull's Official Number is not in the NVDC file dated 10 August 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.
Inspection history · 4
9 March 2023
Administrative Inspection · COC-TVE Renew · Deficiency Check · PSC B
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7647990
13 October 2018
COC-TVE Annual · ISPS II Exam · Ballast Water Examination
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6553828
22 January 2018
Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6341498
2 October 2017
Ballast Water Examination · COC-TVE Renew · ISPS II Exam
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 6278829
11 - Life Saving Appliances › N/A - No Subsystem › Lifeboats
Issued 9 March 2023
Resolved
Each survival craft shall be stowed in a state of continuous readiness so that two crew members can carry out preparations for embarkation and launching in less than 5 min. Ships's crew was unable to start port side life boat.
74 SOLAS (20) III/13.1.3 - 17AC
Action required: 17 - Rectify deficiencies prior to departure
Resolved 5 April 2023
Resolution: The injector to the lifeboat engine was replaced and the engine operationally tested.
02 - Structural Conditions › N/A - No Subsystem › Cargo tank vent system
Issued 9 March 2023
Resolved
The venting system shall be provided with devices to prevent the passage of flame into the cargo tanks. PSCO observed flame screens were deteriorated in the following locations: Port #5, Starboard #4 and #6 P/V valves, and PV breaker.
74 SOLAS (14) II-2/4.5.3.3 - 16AC
Action required: 16 - Rectify deficiencies w/in 14 days
Due 23 March 2023
Resolved 5 April 2023
Resolution: Flame screens were renewed.
02 - Structural Conditions › N/A - No Subsystem › Cargo tank vent system
Issued 9 March 2023
Resolved
The last 1.0 meter of vapor piping upstream of the vessel vapor connection and each end of the vapor hose must be painted in the sequence of red/yellow/red and labeled with the word vapor. PSCO observed vapor manifold connections missing .01 meter red band at end connection on all 4 vapor connection points.
46 CFR 39.2001(h) - 40AC
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 5 April 2023
Resolution: The last 0.1 meter on all four (4) vapor flanges, were painted red.
02 - Structural Conditions › N/A - No Subsystem › Cargo tank vent system
Issued 9 March 2023
Resolved
Each vessel vapor connection flange must have a permanent stud projecting outward that has a 12.7 mm diameter and is at least 25.4 mm long. It must be at the top of the flange face. midway between boltholes, and in the line with the bolthole pattern. Vessel's four VCS lines at manifold did not have stud at end of fitting.
46CFR39.2001(j) - 40AC
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 5 April 2023
Resolution: The studs on all four (4) of the faces of the vapor flanges, were welded inline with the bolthole pattern.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 9 March 2023
Resolved
In tankers, electrical equipment, cables and wiring shall not be installed in hazardous locations unless it conforms with standards not inferior to those acceptable to the organization. PSCO observed disconnected bonding straps in various locations out on deck (Zone 1) to include bunkering line.
74 SOLAS (14) II-1/45.11 - 40AC
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 5 April 2023
Resolution: The boding straps for the bunker piping, P/V valves, COW piping, were renewed.
Fire Fighting › Firemans Outfit › Protective Clothing
Issued 10 October 2017
Resolved
Fire-Fighters outfits shall complay with Fire Saftey Systems Code. Vessel personal equipment shall consist of the following protective clothing of material to protect the skin from heat radiating from fire and from burns and scalding by steam. Vessels fire fighting outfits do not protect ears and the skin on the back of the neck. 74SOLA14/II-2.10.1.1
Condition: Invalid
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Due 12 October 2018
Resolved 22 January 2018