Records from 2017 to 2018. Most recent: inspection, 25 June 2018.
Inspection history · 11
25 June 2018
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6512645
10 May 2018
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6410942
2 May 2018
In-Service Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6458547
1 May 2018
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6411373
27 April 2018
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6400579
7 March 2018
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6389056
25 February 2018
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6381546
31 January 2018
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 6375517
2 December 2017
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 6319210
10 October 2017
In-Service Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6284742
2 October 2017
Deficiency Check · COC-MODU Renew
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6279819
14 - Pollution Prevention › 146 - MARPOL Annex VI › Other (MARPOL Annex VI)
Issued 2 May 2018
Resolved
No parts list was presented at time of inspection with each tech files since 2009.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 23 May 2018
Resolution: Vessel provided satisfactory evidence of clearence of defs.
11 - Life Saving Appliances › N/A - No Subsystem › Operational readiness of lifesaving appliances
Issued 2 May 2018
Resolved
Lifeboat #2 was found to have an air regulator that was leaking at the manifold.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 23 May 2018
Resolution: Vessel provided satisfactory evidence of clearence of defs.
Documentation › Logs/Records › Logbook/Record (unofficial)
Issued 17 October 2017
Resolved
Multiple instances were evident that the vessels Lock out Tag Out (LOTO) system does not ensure that tags were removed by the person who placed the tag. Additionally, LOTO was being used to place out of service components and equipment for purposes other than repair work. Audit the existing LOTO/installed tags and correct as necessary.
Action required: 705 - Other - as specified
Due 16 November 2017
Resolved 7 December 2017
Resolution: Demonstratable evidence provided by Chief Engineer [name withheld]
Lifesaving › Launching Appliances › Davit
Issued 16 October 2017
Resolved
Per 10.18.2 of the 1989 MODU Code, before a unit leaves port and at all times during operations and transit, all life-saving appliances should be in working order and ready for immediate use. The davit sheave for lifeboat #1 was frozen and unable to function safely. Lifeboat #1 shall be placed out of service until all components are made serviceable.
Condition: Improper/Lack of Maintenance
Action required: 66 - Prior to drilling or production operations
Due 17 November 2017
Resolved 18 October 2017
Lifesaving › Lifeboat › Self-contained Air Support System
Issued 16 October 2017
Resolved
Extended to 7Jan18. RSM. Per 10.18.2 of the 1989 MODU Code, before a unit leaves port and at all times during operation and transit, all life-saving appliances should be in working order ready for immediate use. Multiple air bottles were found leaking (low psi), regulators were improperly set and/or leaking, gas charges for doors were depleted, doors lacked gaskets,
Action required: 705 - Other - as specified
Due 7 January 2018
Resolved 7 January 2018
Resolution: Received email from Master about clearance with documentation.
Operations/Management › Lifesaving › Op Readiness/Maintenance/Inspection
Issued 16 October 2017
Resolved
Per 14.12.5 of the 1989 MODU Code, each lifeboat should, as far as practicable, be launched with its assigned crew aboard and manuevered in the water at least once every 3 months. Per paragraph 11 of MSC Circular 1486 Annex, supplemental training cannot take the place of launching when favorable weather conditions are provided during the 3 month period. Lifeboats were not launched once every 3 months as required. Provide evidence of launching all lifeboats.
Action required: 705 - Other - as specified
Due 17 October 2017
Resolved 7 December 2017
Resolution: Demonstratable evidence provided by Chief Engineer [name withheld]
Fire Fighting › Structural - A Class Divisions › Corridors
Issued 16 October 2017
Resolved
Extended to 7Mar18. RSM. Per 9.1.3 of the 1989 MODU Code, the minimum fire integrity of bulkheads and decks should be as prescribed in tables 9-1 and 9-2. Bulkheads should prevent the passage of flame/smoke and per 3.6.1 shall ensure watertight integrity of enclosed compartments. Multiple marine cable transits and doors were incorrectly installed using unapproved materials and/or lacked original packing that reduced their fire integrity. Survey all marine cable transits, doors, and other components to ensure fire integrity is provided.
Action required: 705 - Other - as specified
Due 7 March 2018
Resolved 7 January 2018
Resolution: Received email from master annotating clearance via service report.