Records from 2017 to 2023. Most recent: inspection, 8 May 2023.
Inspection history · 5
8 May 2023
Deficiency Check
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 7683718
13 April 2023
PSC B
Physical examination · Sector Virginia · USCG East District (CGD-E) · Activity 7659768
12 April 2023
Type not recorded
No type recorded · Sector Virginia · USCG East District (CGD-E) · Activity 7667084
24 October 2020
Deficiency Check · PSC B
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7083371
30 November 2017
PII Safety Exam · ISPS II Exam · Ballast Water Examination
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6315494
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 13 April 2023
Resolved
The following functional requirements shall be met: means shall be provided to control leaks of flammable liquids. PSCO observed oil soaked lagging and wet fuel oil surrounding booster pump.
74 SOLAS (09)II-2, Reg. 4.1
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 8 May 2023
Resolution: Received Flag inspector reprot attesting to the repairs of the oil soaked lagging.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 13 April 2023
Resolved
The arrangements for the storage, distribution and utilization of oil shall be such to ensure the safety of ship and persons on board. PSCO observed hydraulic oil leaking onto electrical wiring in solenoid locker in E/R.
74 SOLAS (2009)II-2 Reg. 4.2.3.1
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 8 May 2023
Resolution: Received Flag inspector report from 13 APR 23 attesting to the hydraulic leak in solenoid locker.
02 - Structural Conditions › N/A - No Subsystem › Closing devices/watertight doors
Issued 13 April 2023
Resolved
Fire protection systems shall be maintained ready for use. PSCO observed inoperable class-A door on upper deck to stairway, and class-B door in ECR to electronics workshop.
74 SOLAS (2009)II-2 Reg.14.1.2
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 8 May 2023
Resolution: Received Flag inspector report on 14 APR 23 attesting to the repair of the class A door on upper deck and class B door in ECR.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 24 October 2020
Resolved
99101 - The master or PIC of any vessel w/ ballast tanks that operates in U.S. waters must maintain a Ballast Water Management (BWM) plan and follow the vessel's strategy. The vessel's NBIC report for arrival to Baltimore, MD on 24OCT2020 indicates the vessel used E/R method on the FPTK tank although the vessel's BWM plan states only flow-through method should be used on the FPTK tank. 33 CFR 151.2050
Action required: 10 - Deficiency Rectified
Resolved 24 October 2020
Resolution: Discrepancy brought to the attention of the master during exam for future compliance.
10 - Safety of Navigation › N/A - No Subsystem › Electronic charts (ECDIS)
Issued 24 October 2020
Resolved
10112 - Back-up arrangements to meet the functional requirements of sub paragraph .4, if this function is partly or fully fulfilled by electronic means. PSCO was notified that one of the vessel''s ECDIS was inoperable and paper charts were not available onboard during the exam. 74SOLAS(14V/19.2.1.5
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2020
Resolution: Received documentation showing the charts were delivered to the vsl.