← All vessels
VIKING ORION
VIKING ORION is a 2018 passenger vessel (inspected). The Coast Guard has recorded 44 inspections since 2018, most recently in June 2026, along with 28 deficiencies and 1 operational control.
Records from 2018 to 2026. Most recent: inspection, 15 June 2026.
- Built
- 2018
- Last inspected
- 15 June 2026
- Documentation
- Not in the documentation file of 10 September 2026
- Deficiencies
- 28 recorded · 0 without a recorded resolution
- Controls
- None recorded without a removal date
Identity
9796250 View on MarineTraffic leaves Maury; a third-party site, nothing from it is stored here
LAYQ7
1484198
Flag
NORWAY
—
Maury page id
psix-1484198
Inspections, by type
…with no type recorded4
Years with a record
9 calendar years (2018–2026)
The 44 inspections in the strip above, split by the kind of activity the US
Coast Guard recorded. Years with a record are calendar years in which a record exists, not
years in service. What Maury does not do.
Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 1977.
Documentation record
Tonnage as PSIX records it47861 - Simplified, Gross Ton
47861 - Convention (Subpart B), Gross Ton
3640 - Dead Weight, Ton
25662 - Displacement, Ton
18865 - Simplified, Net Ton
18865 - Convention (Subpart B), Net Ton
47861 - Convention (Subpart B), Gross Ton
3640 - Dead Weight, Ton
25662 - Displacement, Ton
18865 - Simplified, Net Ton
18865 - Convention (Subpart B), Net Ton
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.
Radio station licence
No FCC ship-station licence is recorded against this Official Number in the file of
6 September 2026. That is a fact about the licence file, not about the radio.
Inspection history · 44
15 June 2026
Deficiency Check
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 8405278
8 June 2026
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 8395116
6 June 2026
PSC B · Polar Code Examination · COC-CVE Quarterly
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 8382726
3 September 2025
COC-CVE Annual · PSC B
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 8225127
30 May 2025
COC-CVE Quarterly · PSC B
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 8147248
7 May 2025
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 8130537
17 September 2024
PSC A · COC-CVE Annual
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 8002190
7 May 2024
COC-CVE Quarterly · PSC B
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7904796
29 April 2024
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7908710
21 March 2024
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7905449
12 February 2024
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7872318
6 December 2023
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7842556
25 August 2023
ISPS Exam · Ballast Water Examination · COC-CVE Annual
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7776762
5 June 2023
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7762642
23 May 2023
PSC B · Ballast Water Examination · COC-CVE Quarterly
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7694359
17 May 2023
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7739528
12 May 2023
Type not recorded
No type recorded · Marine Safety Unit Kodiak · USCG Arctic District (CGD-A) · Activity 7705108
30 November 2022
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7602184
24 September 2022
PSC A · Deficiency Check · COC-CVE Annual · Ballast Water Examination
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7565099
24 August 2022
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7542962
10 August 2022
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7530062
29 July 2022
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7519794
21 June 2022
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7483472
16 June 2022
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7479777
24 May 2022
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 7465602
4 May 2022
Deficiency Check · Administrative Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7444217
25 April 2022
PSC B · COC-CVE Quarterly
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7437569
6 November 2021
Administrative Inspection
Administrative · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 7346493
20 October 2021
Deficiency Check
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7336127
6 October 2021
COC-CVE Annual · PSC B · Ballast Water Examination
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7327049
20 September 2021
Type not recorded
No type recorded · USCG Southeast District (dp) · USCG Southeast District (CGD-SE) · Activity 7316220
21 February 2020
Administrative Inspection
Administrative · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6913242
27 December 2019
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6879719
22 November 2019
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6860433
31 October 2019
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6846674
30 September 2019
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6825110
3 September 2019
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6802857
30 August 2019
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6799236
28 August 2019
Type not recorded
No type recorded · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6807848
2 August 2019
Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6770758
2 August 2019
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 6773712
16 May 2019
ISPS II Exam · COC-CVE Initial · Deficiency Check · Administrative Inspection
Physical examination · Sector Western Alaska and U.S. Arctic · USCG Arctic District (CGD-A) · Activity 6668637
13 February 2018
COC-CVE Initial · Administrative Inspection
Administrative · Activities Europe · Activity 6354232
9 January 2018
COC-CVE Initial Prep
Type not classified · Activities Europe · Activity 6334538
Deficiency record · 28
04 - Emergency Systems › N/A - No Subsystem › Abandon ship drills
Issued 6 June 2026
Resolved
Every crew member with assigned emergency duties shall be familiar with these duties before the voyage begins. During the abandon ship drill aft stairways guides deck 1 and deck 4 were unfamiliar with their required duties.
74SOLAS20 III/19.2.1
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 3 September 2025
Resolved
74SOLAS 20 II-2/9.4.1.1.5.1
Fire doors in main vertical zone bulkheads, galley boundaries and stairway enclosures shall be self-closing and be capable of closing with an angle of inclination of up to 3.5 degrees opposing closure. Fire doors 5.1.06 and A.4.17 did not fully close when activated.
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 3 September 2025
Resolved
74SOLAS 20 II-2/10.6.1.1
FSS CODE Chp 8.2.4
Passenger ships carrying more than 36 passengers shall be equipped with an automatic sprinkler of an approved type complying with the requirements of the Fire Safety Systems Code in all control stations, accommodation and service spaces, including corridors and stairways. Pressure gauge on section valve A8 in fire zone 1 deck 5 was found inoperable.
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 17 September 2024
Resolved
Fire doors in main vertical zone bulkheads, galley boundaries and stairway enclosures, double-leaf doors equipped with a latch necessary for their fire integrity shall
have a latch that is automatically activated by the operation of the doors when released by the system. PSCO observed double leaf fire door B.4.07 in entrance to main laundry did
not close in sequence, preventing the door from closing completely.
74 SOLAS 20 11-219.4.1.1.5 12
07 - Fire Safety › N/A - No Subsystem › Operation of Fire protection systems
Issued 17 September 2024
Resolved
Fire detection and fire alarm systems, shall be kept in good order so as to ensure their required performance if a fire occurs. The pressure gauge on the following stop valve was inoperable; A3 Deck A FZ 1.
74 SOLAS (20) 11-2/14.2.1.1.2
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 17 September 2024
Resolved
Cables and wiring shall be installed and supported in such a manner as to avoid chafing and other damage. PSCO observed extension cord used in place of permanent electrical receptacle (Starlight Theater).
74 SOLAS (20) 11-1/45.5.5
07 - Fire Safety › N/A - No Subsystem › Means of escape
Issued 17 September 2024
Resolved
The following functional requirements shall be met escape routes shall be maintained in a safe condition. Sliding door to balcony in cabin 6108 was stuck in a closed position. The crew were able to open the sliding door with force. A guest should be able to open the door as the secondary means of escape with ease.
74 SOLAS (20) II-2/13.1.2
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 7 May 2024
Resolved
The construction of doors and door frames in "A" class divisions, withthe means of securing them when closed, shall provide resistance to fire as well as to the passage of smoke and flame equivalent to that of the bulkheads in which the doors are situated. PSCO's observed missing thumb lock on FSD B.1.16 with visible opening through the door, and FSD B.3.01 door failing to latch.
Cite: 74SOLAS 20 II-2/9.4.1.1.2
Def code: 07105
Action: 10C
07 - Fire Safety › N/A - No Subsystem › Means of escape
Issued 7 May 2024
Resolved
The following functional requirements shall be met escape routes shall be maintained in a sfe condition, clear of obstacles. PSCO's observed storage of hazardous material in escape route.
cite: 74SOLAS20II-2/13.1.2
Code: 07120
Action: 10c
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 13 September 2023
Resolved
The construction of doors and door frames in "a" class divisions with the means of securing them when closed, shall provide resistance to fire as well as to the passage of smoke and flame equivalent to that of the bulkheads in which the doors are situated. Multiple class A doors (4.1.03, 3.2.10, 4.4.6, 2.4.12) did not latch. 74SOLAS20 II-2/9.4.1.1.2
07 - Fire Safety › N/A - No Subsystem › Operation of Fire protection systems
Issued 13 September 2023
Resolved
Fire protection systems and fire-fighting systems and appliances shall be maintained ready for use. Fire appliance cabinet door (2.1.06 & 2.1.07) containing fire hose and fire extinguisher can not be opened due to a missing door handle. 74SOLAS20 II-2/14.1.1
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 13 September 2023
Resolved
Waste receptacles shall be constructed of non-combustible materials with no openings in the sides or bottom. Vessel uses plastic garbage cans as receptacles for combustible material (plastic, paper) in the following spaces; crew bar, deck 1 main galley and the world cafe galley. 74SOLAS20 II-2/4.4.2
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 13 September 2023
Resolved
Doors and door frames in "b' class divisions and means of securing them shall provide a method of clsure which shall have resistance to fire equvalent to that of the divisions. Class B-15 door (deck 7, zone 4) in the starboard pantry space locatin IVO aft explorer lounge does not latch. 74SOLAS20 II-2/9.4.1.2.1
11 - Life Saving Appliances › N/A - No Subsystem › On board training and instructions
Issued 13 September 2023
Resolved
Every crew member with assigned emergency duties shall be familiar with these duties before the voyage begins. Starboard side rescue boat 2nd in command was unfamiliar with the procedures to keep the rescue boat started. 74SOLAS20 III/19.2.1
07 - Fire Safety › N/A - No Subsystem › Operation of Fire protection systems
Issued 13 September 2023
Resolved
Fire protection systems and fire-fighting appliances shall be maintained ready for use. Temperature liquid in one ampule (starboard bunkering station) was missing fluid. 74SOLAS20 II-2/14.1.1
07 - Fire Safety › N/A - No Subsystem › Means of escape
Issued 13 September 2023
Resolved
Above the bulkhead deck there shall be at least two means of escape from each main vertical zone or similarly restricted space or group of spaces, at least one of which shall give access to a stariway forming a vertical escape. Door A.1.48, which is marjed as forming part of the escape route, was found locked, preventing a secondary means of escape. 74SOLAS20 II-2/13.3.2.2
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 13 September 2023
Resolved
A fixed fire-fighting system, required by this chapter shall comply with the provisions of the Fire Safety Systems code. (FSS Code CH9.2.4.2.5)A gauge indicating the pressure in the system shall be provided at each section stop valve and at a central station. pressure guage at section valuve (A7) does not indicate accurate pressure reading in the system. 74SOLAS20 II-2/10.4.1.1
11 - Life Saving Appliances › N/A - No Subsystem › On board training and instructions
Issued 23 May 2023
Resolved
Every crew member with assigned emergency duties shall be familiar with these duties before the voyage begins. PSCOs observed multiple stairway guides who were unfamiliar with directing passengers to the correct muster stations if they did not have their key card. 74 SOLAS 20 III/19.2.1
05 - Radio Communications › N/A - No Subsystem › Operation of GMDSS equipment
Issued 24 September 2022
Resolved
Every ship shall be provided with a receiver capable of receiving international NAVTEX service broadcast. NAVTEX is inoperable. SOLAS 20 IV/7
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 24 September 2022
Resolved
Fire doors in main vertical zone bulkheads, galley boundaries and stairway enclosures...shall satisfy the following requirements: the doors shall be self-closing and be capable of closing with an angle of incliniation of up to 3.5 degrees opposing enclosures. FSD 7.3.01, in a main vertical zone bulkhead, did not latch upon closure. SOLAS 20 II-2/9.4.1.1.5.1
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 24 September 2022
Resolved
Fire doors in main vertical zone bulkheads, galley boundaries and stairway enclosures...shall satisfy the following requirements: the approximate time of closure for hinged fire doors shall be no more than 40s and no less than 10s from the beginning of their movement with the ship in the upright position. FSD 6.2.06, for a stairway enclosure, closed in less than 10s. SOLAS 20 II-2/9.4.1.1.5.2
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 25 April 2022
Resolved
-The ring, lines, and letters shall be painted in contrasting colors of the background.
-PSCO observed vessel's deckline to be painted white, the same color as the hull.
-ICLL 66 1/6
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 25 April 2022
Resolved
-The arrangemetns for the storage, distribution and utilization of oil used shall be such as to ensure the safety of the ship and persons onboard
-PSCO discovered ecess oil accumulation on lagging in engine room.
-74SOLAS(20) II-2/4.2.2
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 25 April 2022
Resolved
-Openings in bulkheaqds and decks in passenger ships shall be self-closing and capable of closing with an angle of inclination up to 3.5 degrees opposing closure.
-PSCO discovered Fire Screen Door # 2.1.11 did not close all the way and latch on its own.
-74SOLAS(20) II-2/9.4
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 6 October 2021
Resolved
The distance from the hot surfaces to the combustible materials shall be at least 500 mm or the combustible materials shall be protected. Heating element for owner's suite sauna does not meet those requirements. SOLAS 20 II-2/9.2.2.3.4.3 16AC
07 - Fire Safety › N/A - No Subsystem › Means of escape
Issued 6 October 2021
Resolved
Additionally escape route signs and fire equipment location markings shall be of photo luminescent material or marked by lighting. escape route signage on AFT pool deck does not exist. Signage for secondary means of escape from explorer lounge does not exist. SOLAS 20 II-2/13.3.2.5.1 16AC
07 - Fire Safety › N/A - No Subsystem › Means of escape
Issued 6 October 2021
Resolved
Stairways and ladders shall be arranged to provide ready means of escape to the life boat and life raft embarkation deck from all passengers and crew spaces and from spaces in which the crew is normally employed. a Room-in-room configuration was identified in the back office located on deck 01. The primary escape route from the HR office, crew purser office, hotel purser office, beverage manager office and director office leading to an other accommodation space. No audible alarm is installed to notify crew. SOLAS 20 II-2/13.3.1.1 50AC
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 16 May 2019
Resolved
Transfer procedures required must contain a list of each product + items found under 155.750(a). Transfer procedures were found incomplete.
Ownership record
The Coast Guard's documentation record for this hull -- the Abstract of Title,
with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National
Vessel Documentation Center, files it here with its date, and every reader of this page gets it.