Records from 2019 to 2026. Most recent: inspection, 27 April 2026.
Inspection history · 11
27 April 2026
Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 8356774
9 April 2025
Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 8108657
16 April 2024
Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 7895979
11 April 2023
COI Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 7661586
27 February 2023
Internal Structural Exam · Drydock Exam
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 7642444
12 August 2022
Administrative Inspection
Administrative · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 7531537
28 June 2022
Administrative Inspection
Administrative · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 7489766
19 May 2022
Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 7455115
4 May 2021
DAPI Audit · Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 7188745
4 March 2020
COI Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 7005931
12 December 2019
Construction Oversight · COI Inspection · Initial Certification
Physical examination · Marine Safety Unit Portland OR · USCG Northwest District (CGD-NW) · Activity 6871293
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 10 April 2025
Resolved
All cable and wiring must be installed with metal supports spaced not more than 24 inches apart, and in such a manner as to avoid chafing and other damage. Overhead light in vessel head has power cable hanging loose. Support cable with metal at least every 24 inches.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 24 April 2025
Resolved 29 April 2025
Resolution: Cabling has been mounted with metal support at least every 24".
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 19 May 2022
Resolved
Vessel is required to carry 2 hand bilge pumps. Current pumps onboard did not function due to a broken handle and 1 being to short to reach spaces intended to be dewatered. Provide 2 hand bilge pumps of proper length prior to carrying passengers.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 3 June 2022
Resolved 14 July 2022
Resolution: Proper pumps were added to vessel.
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 19 May 2022
Resolved
Port and Starboard navigation lights are installed behind cleats and obstructed and cannot display the proper arch of visibility when viewed from a side approach. Relocate lights or cleats prior to operating the vessel at night or during reduced visilbility.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 3 June 2022
Resolved 12 July 2022
Resolution: Lights mounts were relocated.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 19 May 2022
Resolved
Vessel had onboard a plastic trash can. Provide onboard non combustible trash cans.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 3 June 2022
Resolved 14 July 2022
Resolution: Metal cans were installed around vessel.
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 19 May 2022
Resolved
Vessel did not have onboard proof of radio inspections required by the Great Lakes Radio Argeement per 47 CFR 80
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 3 June 2022
Resolved 14 July 2022
Resolution: GLA inspection was completed.
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 19 May 2022
Resolved
Vessel is under 5 net tons and state registered. State registraion numbers where not displayed as required on the Port and Starbord forward portion of hull. Properly display numbers.
Condition: Placed in Improper Service
Action required: 16 - Rectify deficiencies w/in 14 days
Due 3 June 2022
Resolved 14 July 2022
Resolution: State numbers have been installed.
10 - Safety of Navigation › N/A - No Subsystem › Magnetic compass
Issued 19 May 2022
Resolved
Vessel is on a limited Great Lakes route and was not equipped with a Compass and light. Install a magnetic compass at the helm.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 3 June 2022
Resolved 12 July 2022
Resolution: Magnetic compass has been installed.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 19 May 2022
Resolved
1 of the 2 required Fire Extinguishers was located in the head and not readily accessible. Relocate to the accommodation space forward area.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 3 June 2022
Resolved 12 July 2022
Resolution: Fire extinguisher has been relocated.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 4 May 2021
Resolved
Life ring does not have the correct retroreflective tape, install correct type II retrofreflective tape as required by 46 CFR 164.018
Action required: 50 - Rectify deficiencies w/in 30 days
Due 4 June 2021
Resolved 2 June 2021
Resolution: Recieved a photo from the vessel of the life ring that had been replaced with the correct retro tape.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 4 May 2021
Resolved
Fuel system does not have quick closing shut off valve. Install shut off valve and mark properly as required by 46 CFR 185.608.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 4 June 2021
Resolved 2 June 2021
Resolution: The vessel sent photos detailed that the correct fuel shut off had been installed.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 4 May 2021
Resolved
Waste receptacles must be made out of noncombustible materials, remove combustible receptacles and replace.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 4 June 2021
Resolved 2 June 2021
Resolution: Recieved photos from the vessel of the correct type of waste basket installed on the vessel.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 4 March 2020
Resolved
Portable fire extinguisher in accomadation space not mounted.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 15 August 2020
Resolved 23 July 2020
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 4 March 2020
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Condition: Invalid
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 23 July 2020
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 4 March 2020
Resolved
HIN not posted to hull.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 23 July 2020
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 12 December 2019
Resolved
Complete a New-to-zone inspection and the attached worklist, to the satisfaction of attending Marine Inspector.
Action required: 701 - Prior to carriage of passengers/cargo