Records from 2023 to 2026. Most recent: inspection, 3 June 2026.
Documentation record
Registered dimensions (L × B × D)159.2 ft × 46.0 ft × 12.3 ft
Registered tonnagegross 99 / net 68
ITC dimensions (L × B × D)159.2 ft × 46.0 ft × 12.3 ft
ITC tonnagegross 843 / net 264
BuilderCONRAD SHIPYARD LLC · MORGAN CITY, LA, UNITED STATES · built 2025
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeUNSPECIFIED
Hull configurationUNSPECIFIED
Hailing portCEIBA, PR
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 4 December 2025 · expires 31 December 2026
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it843 - Convention (Subpart B), Gross Ton
99 - Regulatory (Subpart C or D), Gross Ton
264 - Convention (Subpart B), Net Ton
68 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Insulation wetted through (oil)
Issued 27 January 2026
Resolved
The design of all exhaust systems must ensure minimum risk of injury to personnel. Protection must be provided in compliance with § 116.970 of this chapter at such locations where persons or equipment might come in contact with an exhaust pipe. All the lagging covering the starboard side exhaust piping was saturated in transmission hydraulic oil. Clean the oil from all the lagging in all affected areas by the hydraulic oil. 46 CFR 116.970/ 119.430(a). Code 17C.
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 28 January 2026
Resolution: Lagging was removed and new lagging installed.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Insulation wetted through (oil)
Issued 27 January 2026
Resolved
The design of all exhaust systems must ensure minimum risk of injury to personnel. Protection must be provided in compliance with § 116.970 of this chapter at such locations where persons or equipment might come in contact with an exhaust pipe. Remove the affected (burned) lagging and provide a 3rd party contractor report if needs replacement or it can still be used only if undamaged by the fire, and if is unsaturated by hydraulic oil, and make sure all exposed areas are covered by the lagging. 46 CFR 116.970/ 46 CFR 119.430 (a)/ Code 17C.
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 28 January 2026
Resolution: New lagging was installed, and all oil saturated lagging was removed and disposed.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 27 January 2026
Resolved
Propulsion machinery must be suitable in type and design for propulsion requirements of the hull in which it is installed and capable of operating at constant marine load under such requirements without exceeding its designed limitations. Prove proper operation of starboard side main diesel engine transmission during sea trial to the satisfaction of an attending USCG Marine Inspector. 46 CFR 119.200/ Code 17C.
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 28 January 2026
Resolution: Conducted a long sea trial of 45 minutes and all propulsion engine was found operational without concerns or alarms.
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 27 January 2026
Resolved
At every other vessel inspection the bilges and other spaces may be examined to see that there is no excessive accumulation of oil, trash, debris, or other matter that might create a fire hazard, clog bilge pumping systems. Clean the following areas around, adjacent above and below of the the starboard main diesel engine, exhaust piping, and all equipment that got in contact with all transmission hydraulic oil deposits that leaked:
a. bilge
b. above deck
c. deck covers
d. starboard sideshell
e. Electrical components
f. Any other areas affected by the oil leak
46 CFR 115.80(b) Code 17C.
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 28 January 2026
Resolution: Engine room was cleaed with degreasers and removed by vacuum truck for disposal.
04 - Emergency Systems › N/A - No Subsystem › Abandon ship drills
Issued 13 November 2025
Resolved
At each initial and subsequent inspection for certification, the marine inspector may require that an abandon ship or man over board drill be held under simulated emergency conditions to be specified by the inspector. Once the vessel has arrived in Puerto Rico, they shall coordinate with the local Coast Guard office to perform an abandon ship drill and a man overboard drill with the crew operating the vessel.
46 CFR 115.808 (g) - 701(c)
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 13 January 2026
Resolution: Drills conducted satisfactory.
04 - Emergency Systems › N/A - No Subsystem › Fire drills
Issued 13 November 2025
Resolved
At each initial and subsequent inspection for certification, the marine inspector may require that a fire drill be held under simulated emergency conditions specified by the inspector. Once the vessel has arrived in Puerto Rico, they shall coordinate with the local Coast Guard office to perform a fire drill with the crew operating the vessel.
46 CFR 115.810(d) - 701 C
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 13 January 2026
Resolution: Fire drill conducted satisfactory.
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 13 November 2025
Resolved
The Rules concerning shapes shall be complied with by day. Vessel only had one black ball day shape. Vessel must have three on board to be in compliance with Inland Nav Rules.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 17 November 2025
Resolution: Verified 2 missing day shapes.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 13 November 2025
Resolved
Remote fuel shutoff stations must be marked in clearly legible letters at least 25 millimeters (1 inch) high indicating purpose of the valve and direction of operations.
46 CFR 122.608 - 701 C
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 13 January 2026
Resolution: Corrected.
04 - Emergency Systems › N/A - No Subsystem › Public address system
Issued 13 November 2025
Resolved
A vessel must be operated in accordance with applicable laws and regulations and in such a manner as to afford adequate precaution against hazards that might endanger the vessel and the persons being transported. The PA panel needs to be labeled.
46 CFR 118.400(d) - 701 C
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 17 November 2025
Resolution: Verified PA panel labeling.
04 - Emergency Systems › N/A - No Subsystem › Emergency, lighting, batteries and switches
Issued 13 November 2025
Resolved
Electrical equipment on a vessel must be installed and maintained to:
(a) Provide services necessary for safety under normal and emergency conditions. Back up batteries for the fire control panel were expired.
46CFR120.200 - 701C
Action required: 17 - Rectify deficiencies prior to departure
Resolved 17 November 2025
Resolution: Verified new batteries.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 30 October 2023
Resolved
All microprocessor or computer based systems must meet the requirements of part 62 in subchapter F of this chapter. The following plans must be submitted to the Coast Guard for approval: Design Verification test procedures. Current DVTP Test #5 "Local/manual operation of transmission" was not IAW test result. Neutral and station indicators were incorrect. O/O must re-submit amendments to the USCG Marine Safety Center for approval.
46CFR121.620(d)
46CFR62.20-1(a)(7)
Action required: 705 - Other - as specified
Due 15 February 2026
Resolved 6 February 2026
Resolution: Submitted to MSC.