Registered dimensions (L × B × D)58.0 ft × 24.0 ft × 7.0 ft
Registered tonnagegross 90 / net 65
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderBOLLINGER MACH SHIP & SHP · LOCKPORT, LA, UNITED STATES · built 1981
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portNEW ORLEANS, LA
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 8 August 2026 · expires 30 September 2027
Service, as the file records itOffshore Supply Vessel
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it90 - Regulatory (Subpart C or D), Gross Ton
65 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 26
8 February 2023
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7627033
8 February 2023
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7634206
23 February 2021
COI Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7127741
21 May 2020
Annual Inspection · Drydock Exam
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6945370
18 March 2019
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6644632
5 March 2018
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6366322
16 March 2017
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6095521
2 March 2016
MTSA Verification · COI Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5822757
19 June 2014
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4890348
26 July 2012
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4356217
3 February 2011
COI Inspection · Deficiency Check · Administrative Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3926852
18 May 2005
COI Inspection · Internal Structural Exam · Hull Examination
Physical examination · MIDET EAST BANK DETAIL · USCG Heartland District (CGD-H) · Activity 2361118
15 July 2002
Annual Inspection
Physical examination · MIDET EAST BANK DETAIL · USCG Heartland District (CGD-H) · Activity 1646329
4 June 2001
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1473384
19 May 2000
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1453758
14 June 1999
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1442852
11 December 1998
Hull Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1393004
14 May 1998
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1472112
4 August 1997
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1454466
22 May 1996
Hull Examination · COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1438434
28 April 1995
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1396309
27 April 1994
COI Inspection · Hull Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1359781
24 September 1992
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1254660
25 February 1992
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 952159
11 December 1991
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1259574
16 September 1991
Initial Certification · Hull Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 937957
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 21 May 2020
No resolution recorded
Contact Sector New Orleans for a full Inspection for Certification prior to operations.
Action required: 17 - Rectify deficiencies prior to departure
Construction/Loadline › Penetrations › Gasket
Issued 16 March 2017
Resolved
Engine room escape hatch has gap in gasket. Make hatch watertight.
Action required: 17 - Rectify deficiencies prior to departure
Due 16 March 2017
Resolved 29 March 2017
Resolution: Operator installed new watertight seal in hatch.
Engineering › Compressed Air System (start air) › Valve
Issued 16 March 2017
Resolved
Air receiver has no relief valve. Compressor has 2 small ones, but none on bottle. Install proper relief valve.
Condition: Invalid
Action required: 17 - Rectify deficiencies prior to departure
Due 16 March 2017
Resolved 11 May 2017
Resolution: Vessel representative upon further inspection of air receivers, noted safety relief valve was placed at the rear piping of the air receiver prior to piping entering the compressor.
Operations/Management › Drills/Instruction › Abandon Ship
Issued 16 March 2017
No resolution recorded
Crew not available at inspection. Vessel is currently laid up. Provide crew and conduct satisfactory drills prior to operating. Also conduct all operational tests to MDE's, steering, crane, leg tilt alarms and fire pump.
Action required: 17 - Rectify deficiencies prior to departure
Due 16 March 2017 — due date passed with no resolution recorded
Resolution: Requirement extended until the expiration of the COI on 02Mar2021 or before the vessel gets underway. This includes the air receiver internal examination.
Electrical › Electrical Distribution System (service) › Metallic Enclosure/Frame
Issued 26 July 2012
Resolved
Engine room main electrical distribution panel box has a broken door latch and missing a blank off plate to a breaker switch slot.
Action required: 705 - Other - as specified
Due 26 August 2012
Resolved 31 July 2012
Resolution: Door repaired and blank breaker installed.
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 26 July 2012
Resolved
Vessel is missing "Not Under Command" navigation lighting.
Action required: 705 - Other - as specified
Due 26 August 2012
Resolved 31 July 2012
Resolution: Not under command lights installed
Navigation › Piloting/Steering › Compass Deviation Table
Issued 26 July 2012
Resolved
Vessel is missing compass deviation table.
Action required: 705 - Other - as specified
Due 26 August 2012
Resolved 31 July 2012
Resolution: Compass deviation card provided
Engineering › Fuel Oil Service System › Hose
Issued 26 July 2012
Resolved
Replace all non SAE J1942 compliant fuel hoses on main engines and generators.
Action required: 705 - Other - as specified
Due 26 August 2012
Resolved 31 July 2012
Resolution: Hoses replaced with SAE-J-1942 approved hoses.
Navigation › Piloting/Steering › Local Notices to Mariners
Issued 26 July 2012
Resolved
Vessel is missing Local Notice to Mariners.
Action required: 705 - Other - as specified
Due 26 August 2012
Resolved 31 July 2012
Resolution: Updated Notice to Mariners proved
Operations/Management › Drug and Alcohol Testing › Employee Coverage
Issued 3 February 2011
Resolved
Prior to operating have all crew members enrolled in drug testing program.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 19 June 2014
Resolution: During Annual exam, verified that the crew was part of a random drug testing program.
Operations/Management › Drills/Instruction › Not Conducted
Issued 3 February 2011
Resolved
Prior to operating, conduct safety drills.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 19 June 2014
Resolution: During Annual Exam, performed man overboard and fire drill with vessel''s crew.
Stability › Intact Stability (when using lifting gear) › General
Issued 3 February 2011
Resolved
Provide operations manual to OCMI for approval. Manual to be approved prior to operating.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 13 December 2012
Resolution: Operations Manual reviewed and stamped approved.
Documentation
Issued 16 September 1991
Resolved
SUBMIT STABILITY CALCULATIONS TO COMMANDANT, G-MARINE SAFETY CENTER, WASH.,D.C. FOR REVIEW AND APPROVAL AS PER 46CFR 174 SUBPART C.
Condition: Unknown
Due 16 September 1991
Resolved 16 September 1991
Documentation
Issued 16 September 1991
Resolved
SUBMIT AND PROVIDE ON BOARD VESSEL AN APPROVED COPY OF VESSELS OPERATING MANUAL. TO BE REVIEWED BY [name withheld] AND FORWARDED TO COMMANDANT, G- MARINE SAFETY CENTER, WASH., D.C. MANUAL TO MEET REQUIREMENTS OF 46CFR 109.121.
Condition: Unknown
Due 16 September 1991
Resolved 16 September 1991