Records from 1986 to 1993. Most recent: inspection, 30 October 1993.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 24
30 October 1993
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 832331
30 October 1993
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1144915
20 October 1993
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 361611
20 October 1993
Certificate of Compliance
Administrative · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1436812
26 September 1993
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 361275
7 October 1992
Certificate of Compliance
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 942881
13 September 1992
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 353080
25 October 1991
Damage Survey · Certificate of Compliance
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 935575
15 April 1991
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 437877
12 October 1990
Certificate of Compliance
Administrative · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 926588
26 June 1990
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 337860
1 May 1990
Type not recorded
No type recorded · COTP NEW YORK · USCG Northeast District (CGD-NE) · Activity 510143
30 September 1989
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 332845
30 September 1989
Certificate of Compliance
Administrative · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1313873
18 September 1988
Certificate of Compliance
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1041889
3 May 1988
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 478154
30 October 1987
Type not recorded
No type recorded · COTP NEW YORK · USCG Northeast District (CGD-NE) · Activity 319283
23 August 1987
Certificate of Compliance
Administrative · MSO PORTLAND MAINE · USCG Northeast District (CGD-NE) · Activity 1338909
22 August 1987
Type not recorded
No type recorded · MSO PORTLAND MAINE · USCG Northeast District (CGD-NE) · Activity 318018
5 May 1987
MARPOL Annex II Examination
Physical examination · MIO PHILADELPHIA · USCG East District (CGD-E) · Activity 1331467
18 February 1987
Type not recorded
No type recorded · MSO PORTLAND MAINE · USCG Northeast District (CGD-NE) · Activity 538514
4 February 1987
Administrative
Administrative · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1311559
31 July 1986
Type not recorded
No type recorded · MIO PHILADELPHIA · USCG East District (CGD-E) · Activity 310460
30 July 1986
Type not recorded
No type recorded · COTP PHILADELPHIA · USCG East District (CGD-E) · Activity 442012
Deck/Cargo
Issued 20 October 1993
Resolved
Prior to using #2 cargo pump renew soft patched seal cooling line.
Condition: Unknown
Due 3 December 1993
Resolved 3 December 1993
Fire Fighting
Issued 20 October 1993
Resolved
Reinstall belt guard on emergency fire pump by next US port
Condition: Unknown
Due 3 December 1993
Resolved 3 December 1993
Deck/Cargo
Issued 20 October 1993
Resolved
Provide 30x30 mesh flamescreens in number 1 center pv valve, 4 ballast tankvents and port & starboard fuel oil vents by next US port.
Condition: Unknown
Due 3 December 1993
Resolved 3 December 1993
Construction/Loadline
Issued 20 October 1993
Resolved
Make permanent repairs to epoxy patch on slop tank transfer line above valve #542 in pump room by next US port.
Condition: Unknown
Due 3 December 1993
Resolved 3 December 1993
Engineering
Issued 20 October 1993
Resolved
Hydro-test bunker lines at 1.5 times working pressure. Provide copy of test report at next US port entry.
Condition: Unknown
Due 3 December 1993
Resolved 3 December 1993
Fire Fighting
Issued 20 October 1993
Resolved
Provide 1 new fire hose in place of leaking hose prior to departing port
Condition: Unknown
Due 3 December 1993
Resolved 3 December 1993
Deck/Cargo
Issued 12 October 1990
Resolved
PRIOR TO RETURNING TO U.S. WATERS VESSEL MUST REPLACE MISSING DEFLECTOR SHIELDS ON PV VALVES.
Condition: Unknown
Due 12 October 1990
Resolved 12 October 1990
Fire Fighting
Issued 12 October 1990
Resolved
PRIOR TO DEPARTING THE COTP PHILADELPHIA ZONE VESSEL MUST HAVE ONBOARD FOUR COMPLETE SETS OF OPERATIONAL SELF-CONTAINED BREATHING APPARATUSES.
Condition: Unknown
Due 12 October 1990
Resolved 12 October 1990
Deck/Cargo
Issued 12 October 1990
Resolved
PRIOR TO RETURNING TO U.S. WATERS VESSEL MUST REPLACE FLAME SCREENS ON FORWARD FUEL OIL VENTS.
Condition: Unknown
Due 12 October 1990
Resolved 12 October 1990
Navigation
Issued 22 August 1987
Resolved
VESSEL'S ARPA INOPERATIVE 33CFR 163.37(A). ISSUED DEVIATION TO ALLOW VESSEL TO DEPART WITH ARPA INOPERATIVE, TO BE CORRECTED PRIOR TO NEXT US PORT.
Condition: Unknown
Due 22 August 1987
Resolved 22 August 1987
Deck/Cargo
Issued 31 July 1986
Resolved
REPLACE ALL FIBERGLASS TANK CLEANING HATCH COVERS WITH STEEL HATCH COVERS OR EQUIVALENT. OR SUMMIT TEST DATA TO COMMANDANT G-MTH-4, SHOWING EQUIVALENCY TO STEEL BY A 1 HOUR BURN TEST. DUE AT NEXT DRY DOCK NO LATER THAN 01 JAN 87. REG. 58, CHAP.II-2, 1981 AMMEND. TO SOLAS 1974.
Condition: Unknown
Due 31 July 1986
Resolved 31 July 1986