Inspection history · 24
1 July 2026
In-Service Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 8420281
6 May 2026
Annual Inspection · Internal Structural Exam
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 8343759
7 April 2026
Drydock Exam · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 8319042
25 March 2025
Internal Structural Exam · Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 8097499
4 June 2024
Deficiency Check
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7926998
2 May 2024
Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7905104
22 February 2024
Internal Structural Exam · Drydock Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7868384
2 August 2023
Administrative Inspection
Administrative · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7758796
8 May 2023
Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7684284
16 February 2023
Administrative Inspection
Administrative · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7637642
11 October 2022
Hull Examination · Examination of Repairs
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7575693
13 April 2022
COI Inspection · Internal Structural Exam
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7430021
20 March 2022
Type not recorded
No type recorded · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7415177
28 June 2021
Administrative Inspection · Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7282139
19 January 2021
Deficiency Check · Administrative Inspection · Internal Structural Exam
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7127743
1 June 2020
Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6965355
30 April 2020
Administrative Inspection
Administrative · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6946133
8 May 2019
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6684558
1 May 2019
Internal Structural Exam · Drydock Exam · Examination of Repairs
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6674923
12 April 2018
Deficiency Check · Annual Inspection · Administrative Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6390453
30 October 2017
Deficiency Check · Administrative Inspection
Physical examination · Navigation Center · Activity 6297760
18 April 2017
COI Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6127651
24 April 2016
Type not recorded
No type recorded · Station New York · USCG Northeast District (CGD-NE) · Activity 5861661
13 April 2016
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5853096
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance of Life Saving Appliances
Issued 25 March 2025
Resolved
Each disposable hydrostatic release unit must be marked w/an expiration date of two years after the date installed. EPIRB disposable hydrostatic release unit is expired.
46 CFR 185.740(b)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 April 2025
Resolved 31 March 2025
Resolution: Recieved picture of newly purchased EPIRB HRU.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 25 March 2025
Resolved
Vessels described by 46 CFR 175.110(c) must have an interconnected fire detection system in compliance with §181.450 installed in all enclosed areas where passengers and crew have routine access, including accommodation spaces and machinery spaces. Vessel did not have smoke detector at operating station.
46 CFR 181.405(c)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 April 2025
Resolved 2 April 2025
Resolution: New interconnected smoke detector placed at operating station and succesfuly tested.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 25 March 2025
Resolved
Except as provided otherwise in this subpart, all electrical equipment including motors, generators, controllers, distribution panels, etc., shall be drip-proof protected. The switchboard voltmeter and breaker panel were missing coverings.
46 CFR 183.10-10
(Old T)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 25 April 2025
Resolved 3 April 2025
Resolution: Voltmeter and switchboard panel have proper covering.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 25 March 2025
Resolved
The construction & arrangement of a vsl must allow the safe operation of the vsl in accordance w/ the terms of its COI. The starboard support beam in the fwd storage compartment has become detached at the deck. Submit repair proposal and correct.
46 CFR 177.100
Action required: 50 - Rectify deficiencies w/in 30 days
Due 25 April 2025
Resolved 2 April 2025
Resolution: Stanchion was gouged and properly welded to the deck.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 2 May 2024
Resolved
All vessels shall be provided with not less than two avenues of escape from all general areas accessible to the passengers or where the crew may be quartered or normally employed. Escape hatch was found broken, severely corroded and unable to open from inside the engine room space. Replace/repair escape hatch for engine room. 46 CFR 177.15-1
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 16 May 2024
Resolved 3 May 2024
Resolution: O/O sent photo evidence of satisfactory repair.
09 - Working and Living Conditions › 091 - Living Conditions › Electrical devices
Issued 2 May 2024
Resolved
Except as provided otherwise in this subpart, all electrical equipment including motors, generators, controllers, distribution panels, etc., shall be
dripproof protected...so constructed or protected
that its successful operation is not interfered with when subjected to falling moisture or dirt, and rotating or uninsulated parts cannot be inadvertently touched... Voltmeter for Generator #2 was exposed/uncovered; cover.
46 CFR 183.10-10(a)
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 16 May 2024
Resolved 4 June 2024
Resolution: Recieved pictures showing replacement of gauge
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 2 May 2024
Resolved
On a vessel on which the number of passengers permitted on upper decks is limited by stability criteria, as indicated by the vessel's stability letter, the maximum number of passengers allowed on an upper deck must be indicated by a durable marking of at least 25 millimeters (1 inch) numbers and letters at the entranceway to that deck. Vessels upper deck was not labeled with max pax count. 46 CFR 185.602(g)
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 16 May 2024
Resolved 4 June 2024
Resolution: recieved pictures showing upper deck label.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 8 May 2023
Resolved
All electrical installations shall be to the satisfaction of the Officer in Charge, Marine Inspection. Found cracked Amp meter on generator distribution panel on aft bulkhead in engine room. Replace/repair broken Amp meter.
46 CFR 183.01-15
old "T"
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 May 2023
Resolved 11 October 2023
Resolution: O/O provided picture of replaced amp meter
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 8 May 2023
Resolved
All vessels shall be provided with not less than two avenues of escape from all general areas accessible to the passengers or where the crew may be quartered or normally employed. Escape hatch was found broken, severely corroded and unable to open from inside the engine room space. Replace/repair escape hatch for engine room.
46 CFR 177.15-1
Old "T"
Action required: 16 - Rectify deficiencies w/in 14 days
Due 22 May 2023
Resolved 11 October 2023
Resolution: O/O provided video of repaired emergency espcape hatch in use.
09 - Working and Living Conditions › 092 - Working Conditions › Protection machinery
Issued 13 April 2022
Resolved
No guards were protecting alternator belts on all 03 main engines. 46 CFR 177.35-15(Old T)
Condition: Design Flaw
Action required: 50 - Rectify deficiencies w/in 30 days
Due 13 May 2022
Resolved 27 April 2022
Resolution: Received photographic satisfactory evidence of repair.
11 - Life Saving Appliances › N/A - No Subsystem › Stowage and provision of liferafts
Issued 13 April 2022
Resolved
Lifefloat grabline's were secured using zipties. Replace is material that is easily broken when pulled. 46 CFR 180.175(d)
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2022
Resolved 27 April 2022
Resolution: Received photographic satisfactory evidence of repair.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 13 April 2022
Resolved
Secure dead end wires behind operating station. 46 CFR 183.05-50(b)
(Old T)
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2022
Resolved 27 April 2022
Resolution: Received photographic satisfactory evidence of repair.
11 - Life Saving Appliances › N/A - No Subsystem › Stowage and provision of liferafts
Issued 28 June 2021
Resolved
IBA onboard was not attached to the vessel by weak link. This was corrected prior to the end of the inspection.
Action required: 17 - Rectify deficiencies prior to departure
Due 28 June 2021
Resolved 28 June 2021
Resolution: Corrected prior to the end of the inspection.
09 - Working and Living Conditions › 092 - Working Conditions › Machinery
Issued 19 January 2021
Resolved
Hydro pneumatic tank in the workshop is currently secured with bungees. Provide permanent means of securing.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 29 January 2021
Resolution: Tank secured by aluminum bar attachment.
02 - Structural Conditions › N/A - No Subsystem › Bulkheads - cracking
Issued 19 January 2021
Resolved
Cracks identified in bulwark attachment to deck starboard side aft and in steering compartment scuttle on main deck. Repair cracks prior to credit drydock.
Action required: 705 - Other - as specified
Resolved 29 January 2021
Resolution: Cracks repaired.
02 - Structural Conditions › N/A - No Subsystem › Hull - corrosion
Issued 19 January 2021
Resolved
Pitting identified in steering compartment. Gauge and repair as indicated by gauging results prior to credit drydock.
Action required: 705 - Other - as specified
Resolved 25 January 2021
Resolution: Plating cropped and replaced.
05 - Radio Communications › N/A - No Subsystem › Operation/maintenance
Issued 9 June 2020
Resolved
Input lat/long position into radio
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 July 2020
Resolved 11 June 2020
Resolution: Verified lat/long input in radio.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 9 June 2020
Resolved
Label fuel shutoff valves
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 July 2020
Resolved 11 June 2020
Resolution: Fuel shutoffs labeled.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 9 June 2020
Resolved
Repair minor fuel leak on port engine fuel filter union
Action required: 16 - Rectify deficiencies w/in 14 days
Due 23 June 2020
Resolved 11 June 2020
Resolution: Fuel leak repaired
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 9 June 2020
Resolved
Remove dead end wiring, install wire hangers on aft overhead and drill .25" drainage holes in handrails every 5 ft where wire passes through.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 July 2020
Resolved 11 June 2020
Resolution: Holes drilled in handrails.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 8 May 2019
Resolved
A vesel must carry one floating waterlight, which must be approved IAW 46 CFR 161.010. The waterlight was not marked and Marine Inspector could not verify type approval.
Action required: 10 - Deficiency Rectified
Resolved 8 May 2019
Resolution: Lifebuoy light was replaced.