Inspection history · 15
9 May 2008
Ballast Water Examination · PII Safety Exam · ISPS II Exam · MARPOL Annex I Examination · MARPOL Annex V Examination
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3098547
14 October 2007
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3080550
21 August 2007
Deficiency Check
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3034337
5 April 2007
NPV Safety Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2903115
27 November 2006
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 2829458
16 November 2006
Deficiency Check · PII Safety Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2826121
28 September 2006
Random ISPS/MTSA-No PSC
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 2788881
30 June 2006
Type not recorded
No type recorded · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 2696566
11 April 2006
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 2622976
20 March 2006
Type not recorded
No type recorded · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 2605966
2 January 2006
Deficiency Check
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 2561516
31 October 2005
PII Safety Exam · Deficiency Check · Ballast Water Examination · ISPS II Exam
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 2525826
23 February 2004
Annual Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 2012427
1 November 2002
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1699384
10 April 2002
Annual Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1603084
Lifesaving › Lifeboat › Inherent Buoyancy
Issued 5 April 2007
Resolved
Inflated chambers on rescue boat is leaking at faulty relief valve. Vessel has made adequate temp repair & will affect full repair to the satisfaction of class upon receiving parts. (50a)
Action required: 705 - Other - as specified
Due 5 May 2007
Resolved 21 August 2007
Resolution: Replaced with new rescue boat
Stability › Watertight Integrity › General
Issued 16 November 2006
Resolved
Watertight hatch iwo engine room does not seal properly due to bent overhead frame. Repair overhead frame to ensure proper seal of watertight door.
Action required: 705 - Other - as specified
Due 16 December 2006
Resolved 1 December 2006
Fire Fighting › Fire Hydrants › Material
Issued 16 November 2006
Resolved
Provide 3 spanner wrenches in engine room fire stations & 2 spanner wrenches for fire stations main deck.
Action required: 705 - Other - as specified
Due 16 December 2006
Resolved 1 December 2006
Navigation › Piloting/Steering › Maneuvering Information Fact Sheet
Issued 31 October 2005
Resolved
Provide Maneuvering Information Fact Sheet for vessel in accordance with 33CFR 164.35 to the satisfaction of the U.S. Coast Guard.
Condition: Unknown
Due 24 November 2005
Resolved 5 January 2006
Resolution: Vessel faxed copy of Maneuvering Facts Information sheet to unit.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 31 October 2005
Resolved
Replace medication that has expired with valid medicine prior to departure from port. ILO 147
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 31 October 2005
Resolution: Medication replaced.
Documentation › Safety/Response Plans/Programs
Issued 23 February 2004
Resolved
Replace both Fire Control Plans (2) prior to departure from Galveston, TX to the satisfaction of Certificate Issuing Authority IAW Solas 74 Ammended Chapter II-2 Reg 20. LEGACY COMPONENT DESC: Fire Control Plans
Action required: 17 - Rectify deficiencies prior to departure
Due 23 February 2004
Resolved 24 February 2004
Resolution: Both Fire Control Plans replace and approved by Certificated Issuing Authority.
Fire Fighting › Fire Hoses › Material
Issued 23 February 2004
Resolved
Replace all fire hoses throughout the ship with approved type prior to departure from the port of Galveston , TX to the satisfaction of Certificate Issuing Authority IAW with Solas 74 ammended Chapter II-2 Reg 4.7.1.
Action required: 17 - Rectify deficiencies prior to departure
Due 23 February 2004
Resolved 24 February 2004
Resolution: All fire hoses were replaced to the satisfaction of Certificate Issuing Authority.
Fire Fighting › Fire Hydrants › Location/Position
Issued 23 February 2004
Resolved
Fire station on portside boat deck not accessible due to work boat being in the way. Make fire station (and hose) accessible prior to departure from Galveston, TX to the satisfaction of Certificate Issuing Authority IAW Solas 74 Ammended Chapter II-2 Reg 2.7.
Action required: 17 - Rectify deficiencies prior to departure
Due 23 February 2004
Resolved 24 February 2004
Resolution: Vessel made fire station accesible by moving work boat to the satisfaction of the Certificate Issuing Authority.
Fire Fighting › Miscellaneous Items
Issued 23 February 2004
Resolved
Remove excess oil/fuel from engine room bilge prior to departure from the port of Galveston, TX IAW Solas 74 Ammended Chapter II-2 Reg 2.2.
Action required: 17 - Rectify deficiencies prior to departure
Due 23 February 2004
Resolved 24 February 2004
Resolution: Bilges were cleaned to the satisfaction of Certificate Issuing Authority.
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 23 February 2004
Resolved
Provide one half of lifebuoys (4) with self igniting lights prior to departure from Galveston, TX to the satisfaction of Certificate Issuing Authority IAW Solas 74 Ammended Chapter III Reg 7.1.3.
Action required: 17 - Rectify deficiencies prior to departure
Due 23 February 2004
Resolved 24 February 2004
Resolution: One half of lifebuoys fitted with self igniting lights to the satisfaction of Certificate Issuing Authority.
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 23 February 2004
Resolved
Repair Oily Water Separator prior to departure from Galveston, TX to the satisfaction of Certificate Issuing Authority IAW MARPOL 73/78 Annex I Reg 16 (1).
Action required: 17 - Rectify deficiencies prior to departure
Due 23 February 2004
Resolved 24 February 2004
Resolution: Certificate Issuing Authority verified operation of Oily Water Separator.
Documentation › Certificates/Documents
Issued 10 April 2002
Resolved
PROVIDE CERTIFICATE OF REGISTRY PRIOR TO NEXT US PORT
Action required: 15 - Rectify deficiencies by next port
Due 31 October 2002
Resolved 31 October 2002
Resolution: VESSEL PROVIDED VALID CERTIFICATE OF REGISTRY
Navigation › Piloting/Steering
Issued 10 April 2002
Resolved
PROVIDE STEERING GEAR INSTRUCTIONS ON BRIDGE PRIOR TO NEXT US PORT.
Condition: Unknown
Action required: 15 - Rectify deficiencies by next port
Resolved 31 October 2002
Resolution: STEERING GEAR INSTRUCTIONS POSTED ON BRIDGE.
Navigation › Piloting/Steering
Issued 10 April 2002
Resolved
PROVIDE MANEUVERING FACTS SHEET ON BRIDGE PRIOR TO NEXT US PORT. LEGACY COMPONENT DESC: Maneuvering Information Fact Sheet
Action required: 15 - Rectify deficiencies by next port
Resolved 31 October 2002
Resolution: MANEUVERING FACTS SHEET NOT REQUIRED DUE TO GROSS TONNAGE LESS THAN 1600
Documentation › Manuals/Policy Documentation
Issued 10 April 2002
Resolved
PROVIDE SOPEP PRIOR TO NEXT US PORT
Action required: 15 - Rectify deficiencies by next port
Due 31 October 2002
Resolved 31 October 2002
Resolution: VESSEL PROVIDED VALID SOPEP
Lifesaving › Launching Appliances
Issued 10 April 2002
Resolved
REPAIR OR REPLACE DAVIT LIMIT SWITCH PRIOR TO NEXT US PORT LEGACY COMPONENT DESC: Davit
Condition: Unknown
Action required: 15 - Rectify deficiencies by next port
Resolved 31 October 2002
Resolution: VESSEL DEMONSTRATED PROPER OPERATION OF DAVIT LIMIT SWITCH
Documentation › Certificates/Documents
Issued 10 April 2002
Resolved
PROVIDE CERTIFICATE OF REGISTRY
Condition: Unknown
Action required: 15 - Rectify deficiencies by next port
Resolved 31 October 2002
Resolution: VESSEL PROVIDED VALID CERTIFICATE OF REGISTRY
Navigation › Piloting/Steering
Issued 10 April 2002
Resolved
PROVIDE STEERING GEAR INSTRUCTION WITH BLOCK DIAGRAM
Condition: Unknown
Action required: 15 - Rectify deficiencies by next port
Resolved 31 October 2002
Resolution: STEERING GEAR INSTRUCTION POSTED ON BRIDGE
Navigation › Piloting/Steering
Issued 10 April 2002
Resolved
PROVIDE MANEUVERING FACTS SHEET LEGACY COMPONENT DESC: Maneuvering Information Fact Sheet
Condition: Unknown
Action required: 15 - Rectify deficiencies by next port
Resolved 31 October 2002
Resolution: MANEUVERING FACTS SHEET NOT REQUIRED DUE TO GROSS TONNAGE LESS THAN 1600.
Operations/Management › Pollution
Issued 10 April 2002
Resolved
PROVIDE SOPEP LEGACY COMPONENT DESC: Removal Methods/Procedures
Condition: Unknown
Action required: 15 - Rectify deficiencies by next port
Resolved 31 October 2002
Resolution: VESSEL PROVIDED VALID SOPEP