PRINCESS MONTEREY is a 2001 passenger vessel (inspected). The Coast Guard has recorded 57 inspections since 2001, most recently in September 2025, along with 168 deficiencies, 2 operational controls and 9 casualty investigations between 2002 and 2018.
Records from 2001 to 2025. Most recent: inspection, 4 September 2025.
- Built
- 2001
- Last inspected
- 4 September 2025
- Documentation
- Valid · documentation file of 10 September 2026
- Deficiencies
- 168 recorded · 0 without a recorded resolution
- Controls
- None recorded without a removal date
- Casualties
- 9 investigations · 2002–2018
Identity
1109154
8967632 View on MarineTraffic leaves Maury; a third-party site, nothing from it is stored here
WDL4752
23420
Flag
UNITED STATES
368134480
Maury page id
psix-23420
Inspections, by type
…with no type recorded8
Years with a record
21 calendar years (2001–2025)
The 57 inspections in the strip above, split by the kind of activity the US
Coast Guard recorded. Years with a record are calendar years in which a record exists, not
years in service. What Maury does not do.
Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 1977.
Documentation record
Registered dimensions (L × B × D)80.3 ft × 25.8 ft × 9.1 ft
Registered tonnagegross 92 / net 62
ITC dimensions (L × B × D)80.3 ft × 25.8 ft × 9.1 ft
ITC tonnagegross 170 / net 61
BuilderYANK MARINE INC · TUCKAHOE, NJ, UNITED STATES · built 2001
Hull materialAluminum
PropulsionDiesel Reduction
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portMONTEREY, CA
Trade endorsementsCoastwise, unrestricted, Fishery, Registry
DocumentationValid · issued 18 May 2026 · expires 31 May 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it92 - Regulatory (Subpart C or D), Gross Ton
170 - Convention (Subpart B), Gross Ton
62 - Regulatory (Subpart C or D), Net Ton
61 - Convention (Subpart B), Net Ton
170 - Convention (Subpart B), Gross Ton
62 - Regulatory (Subpart C or D), Net Ton
61 - Convention (Subpart B), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Radio station licence
WDL4752MMSI 368134480 · active · compulsorily equipped · granted 27 February 2020, expires 27 February 2030
WDI5027MMSI 367704430 · cancelled · compulsorily equipped · granted 24 November 2015, cancelled 31 January 2024
WDD9361MMSI 367310320 · expired · compulsorily equipped · granted 25 August 2007, cancelled 28 October 2017
WDA4951MMSI 366814920 · expired · compulsorily equipped · granted 12 June 2001, cancelled 13 August 2011
FCC Universal Licensing System ship-station file of 6 September 2026, matched to this hull on its
US Official Number. Status and dates are the file’s own. The licensee is not read from the file and is not shown.
A lapsed licence’s MMSI is still the number the vessel transmitted under while it was valid.
Inspection history · 57
4 September 2025
Deficiency Check · Annual Inspection · Internal Structural Exam
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8210816
31 October 2024
Administrative Inspection
Administrative · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8027415
9 October 2024
Administrative Inspection · Drydock Exam
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8060970
6 June 2024
Deficiency Check · Annual Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7929185
7 September 2023
Deficiency Check · Annual Inspection · Internal Structural Exam
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7785437
6 October 2022
Internal Structural Exam · Hull Examination · Deficiency Check · Drydock Exam
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7572729
7 September 2022
Internal Structural Exam · Deficiency Check · Annual Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7552550
9 June 2021
MTSA Verification · COI Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7174587
1 March 2021
Inclining Experiment
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7148209
15 December 2020
Administrative Inspection
Administrative · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 7111888
15 November 2019
Deficiency Check · Drydock Exam · Hull Examination
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6856489
28 May 2019
Administrative Inspection
Administrative · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6697142
13 March 2019
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6640014
13 August 2018
Administrative Inspection
Administrative · Navigation Center · Activity 6510911
27 July 2018
In-Service Inspection · Examination of Repairs
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6492655
27 July 2018
Type not recorded
No type recorded · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6519523
24 June 2018
In-Service Inspection · Deficiency Check
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6453741
24 June 2018
Type not recorded
No type recorded · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6458699
9 May 2018
Deficiency Check · Administrative Inspection
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6410398
16 April 2018
Annual Inspection · MTSA Verification
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6392174
12 February 2018
Hull Examination · Administrative Inspection · Internal Structural Exam
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6362565
4 January 2018
In-Service Inspection · Examination of Repairs · Administrative Inspection
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6336812
24 October 2017
In-Service Inspection · Damage Survey · Administrative Inspection · Examination of Repairs
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6298193
6 May 2017
Type not recorded
No type recorded · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6256866
15 March 2017
COI Inspection · Deficiency Check · MTSA Verification
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 6105736
30 March 2016
MTSA/ISPS Verification · COI Inspection · Hull Examination · Internal Structural Exam
Physical examination · Marine Safety Detachment Fort Macon · USCG East District (CGD-E) · Activity 5843979
6 May 2014
Damage Survey
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 4852989
6 May 2014
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 4879451
25 March 2014
Deficiency Check · In-Service Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 4825319
1 February 2012
Administrative Inspection
Administrative · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 4236081
21 July 2009
MTSA Verification · Administrative Inspection · DAPI Audit · Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3534008
10 July 2009
Examination of Repairs · Damage Survey
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3549333
16 April 2009
Administrative Inspection · Plan Review (Other than "T")
Administrative · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3453832
3 March 2009
Deficiency Check · Hull Examination · Internal Structural Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3430351
11 August 2008
Annual Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3295261
27 June 2007
Annual Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2961095
1 June 2007
Damage Survey
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2949384
1 June 2007
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2951431
29 May 2007
In-Service Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2945928
21 March 2007
Damage Survey
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2882855
21 March 2007
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2892427
5 March 2007
Drydock Extension · Hull Examination
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2880054
16 June 2006
In-Service Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2742309
6 June 2006
Deficiency Check · COI Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2667179
24 April 2006
Damage Survey
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2634584
11 May 2005
Deficiency Check · Annual Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 2352959
7 February 2005
Hull Examination
Physical examination · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 2294576
10 August 2004
MARPOL Annex V Examination · MTSA Verification · Annual Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 2161729
11 March 2004
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 2022948
14 October 2003
Administrative Inspection · Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1927698
23 July 2003
MARPOL Annex V Examination · Annual Inspection · Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1855255
16 April 2003
Internal Structural Exam · Hull Examination · Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1775242
13 August 2002
MARPOL Annex V Examination · Annual Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1666028
19 April 2002
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1608109
11 October 2001
Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1075551
18 June 2001
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1389429
12 June 2001
Hull Examination · COI Inspection · Plan Review "T" Boat
Physical examination · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 1467320
Deficiency record · 168
07 - Fire Safety › N/A - No Subsystem › Operation of Fire protection systems
Issued 4 September 2025
Resolved
Shutoff valves, installed so as to close against the fuel flow, must be fitted in the fuel supply lines, one at the tank connection and one at the engine end of the fuel line to stop fuel flow when servicing accessories. The shutoff valve at the tank must be manually operable from outside the compartment in which the valve is located. The port fuel shutoff valve does not turn 90 degrees for full closure when activated remotely. 46 CFR 119.455(b)(3)
07 - Fire Safety › N/A - No Subsystem › Division - decks, bulkheads and penetrations
Issued 4 September 2025
Resolved
A-Class bulkheads… must be so insulated with approved structural insulation, so that, if subjected to the standard fire test for the applicable time period, the average temperature on the unexposed side does not rise more than 250 °F above the original temperature, nor does the temperature at any one point rise more than 325 °F above the original temperature… Penetrations must be designed or insulated to withstand the same temperature rise limits as the boundary penetrated. The A-60 Class bulkhead forward in the lazarette is missing sections of non-combustible insulation starboard of the CO2 bottles and inadequate foam is used to seal penetrations on both sides of same bulkhead and overhead aft of access ladder. 46 CFR 116.415(a)(2)
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 4 September 2025
Resolved
Nonconducting mats or grating must be provided on the deck in front of each switchboard. The nonconductive mat is missing. 46 CFR 120.330(g)
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance of Life Saving Appliances
Issued 4 September 2025
Resolved
Each ring life buoy on a vessel must, if on a vessel on an oceans or coastwise route, be orange in color. Two ring life buoys are excessively faded. 46 CFR 117.70(b)(5)
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance of Life Saving Appliances
Issued 4 September 2025
Resolved
Each life jacket must be marked with Type I retroreflective material approved in accordance with § 164.018 in subchapter Q of this chapter. Ten child lifejackets had retroreflective material that was worn and partially painted over. 46 CFR 122.604(h)
07 - Fire Safety › N/A - No Subsystem › Evaluation of crew performance (fire drills)
Issued 4 September 2025
Resolved
For a vessel described by 46 CFR 175.110(c), the training program in paragraph (a) of this section must address firefighting proficiency and must include (1) Training in the use and location of firefighting equipment and general firefighting knowledge, including: (i) Location of firefighting appliances and emergency escape routes; (ii) Types and sources of ignition; (iii) Flammable materials, fire hazards and spread of fire; (iv) The need for constant vigilance; (v) Actions to be taken on board; (vi) Fire and smoke detection and automatic systems on board; and (vii) Classification of fire and applicable extinguishing agents. Required training was not logged. 46 CFR 122.420
11 - Life Saving Appliances › N/A - No Subsystem › Launching arrangements for survival craft
Issued 4 September 2025
Resolved
Secured to the vessel by a painter with a float-free link permanently attached to the vessel except that a float-free link is not required if the vessel operates only on waters not as deep as the length of the painter. Painter on 2 of 4 IBA’s were found not connected to the weak link and would have prevented release in an emergency. 46 CFR 117.130
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 4 September 2025
Resolved
At each inspection for certification and at every other vessel inspection all observed unsafe practices, fire hazards, and other hazardous situations must be corrected and all required guards and protective devices must be in satisfactory condition. Both outboard heating piping lines in the lazarette were holed in several locations allowing the potential for excess water accumulation in this space. 46 CFR 115.830
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 4 September 2025
Resolved
Piping used in a vital system must meet 56.50 in subchapter F of this chapter. Lazarette bilge suction piping found with two sections of the piping joined with a 5” portion of non metallic material. Replace existing section of piping with material in accordance with the regulations. 46 CFR 119.710
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 31 October 2024
Resolved
A vessel that is exposed to salt water more than three months in any 12 month period since the last examination must undergo a drydock examination and an internal structural at least once every two years. The vessel has not completed a drydock examination within the last two years. Conduct satisfactory drydock examination prior to the carriage of passengers.
46 CFR 176.600(c)(1)
11 - Life Saving Appliances › N/A - No Subsystem › Stowage and provision of liferafts
Issued 6 June 2024
Resolved
The name of the vessel must be marked or painted in clearly legible letters on each life float paddle. Paddles for vessel's life floats did not have names. Label paddles properly to the satisfaction of the MI.
01 - Certificates & Documentation › 013 - Documents › Log-books/compulsory entries
Issued 6 June 2024
Resolved
For a vessel described by 46 CFR 114.100(e), the training program in paragraph (a) of this section must address firefighting proficiency. MI observed limited details in vessel's drill logs. Crew training program must address the listed firefighting proficiencies to improve crewmember training and proficiency, including egress training for each member on board.
02 - Structural Conditions › N/A - No Subsystem › Decks - cracking
Issued 6 June 2024
Resolved
At each initial and subsequent inspection for certification of a vessel, the owner shall be prepared to conduct tests and have the vessel ready for inspections of the hull structure and its appurtenances. Temporary patch observed in overhead of storage void. Outer side of patch is on starboard main weatherdeck and there is a weld seam visible. Patch inside void is 10 ft forward of access ladder a few inches from sideshell. Remove patch during next drydock and make available for MI inspection.
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 7 September 2023
Resolved
A vessel owner or operator may use an Alternative Security Program as approved under § 101.120 of this subchapter if: (a) The Alternative Security Program is appropriate to that class of vessel. Vessel’s security plan was found to be missing key elements needed in a vessel security plan and was deemed not appropriate for the class of the vessel. Vessel must update and renew their security plan to the satisfaction of the attending Marine Inspector, vessel will be restricted to less than 150 passengers until this deficiency is resolved.
33 CFR 104.140(a)
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 7 September 2023
Resolved
Vessels described by 46 CFR 114.110(e) must have an interconnected fire detection system in compliance with 46 CFR 181.450 installed in all enclosed areas where passengers and crew have routine access, including accommodation spaces and machinery spaces. Vessel was found to not have an interconnected fire detection system on board. Vessel must have interconnected fire detection system in the machinery space, main deck accommodation space, and the pilot house and to the satisfaction of the attending Marine Inspector, vessel will be restricted to Limited Coastwise routes until this is resolved.
46 CFR 114.110(e)
46 CFR 118.400(d)
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 7 September 2023
Resolved
Each portable fire extinguisher on a vessel must be of a type approved by the Commandant. The minimum number of portable fire extinguishers required on a vessel must be acceptable to the cognizant OCMI, but must be not less than the minimum number required by Table 118.500(a) of this section and other provisions of this section. There were multiple extinguishers found on the vessel that did not meet the requirements of Table 188.500(a) of the regulation. Vessel must review the requirements of table 118.500(a) and update and correct all portable fire extinguishers to the standard and the satisfaction of the attending Marine Inspector.
46 CFR 114.110(e)
46 CFR 118.500(a)
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 7 September 2023
Resolved
Each ring life buoy on a vessel must: (1) Be approved in accordance with § 160.050 in subchapter Q of this chapter, or other standard specified by the Commandant, including, but not limited to, approval series 160.150; (2) Be readily accessible; (3) Be stowed in a way that it can be rapidly cast loose; (4) Not be permanently secured in any way; and (5) If on a vessel on an oceans or coastwise route, be orange in color. Vessels port side lifebuoy was found worn where the orange coloring was degrading. Repair or replace the lifebuoy to the satisfaction of the attending Marine inspector.
46 CFR 117.70(b)(5)
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 7 September 2023
Resolved
Each rescue boat and ring life buoy must be marked with Type II retroreflective material approved in accordance with § 164.018 in subchapter Q of this chapter, or other standard specified by the Commandant. The arrangement of the retroreflective material applied after March 11, 1996, must be as specified by IMO Resolution A.658(16). The vessels reflective material on the lifebuoys was found degraded and not up to the specifications of type II retroreflective material. Vessel must replace the reflective material on the lifebuoys to the satisfaction of the attending Marine Inspector.
46 CFR 122.604(i)
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 7 September 2023
Resolved
Spanner wrenches must be provided for each fire hydrant required by this regulation. Existing vessels must comply with this requirement by January 18, 2017. Port side fire station is missing a spanner wrench. Vessel must replace the missing spanner wrench to the satisfaction of the Marine Inspector.
46 CFR 118.310(e)
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 7 September 2023
Resolved
The master of the vessel shall ensure that: (c) The EPIRB test is required by paragraph (a) shall be logged or otherwise documented, as applicable. Vessel logbook was found with multiple missing EPIRB tests along with other important entries. Vessel Master and crew were educated on the importance of logging the critical information as well as when they need to be logging the information.
46 CFR 122.728(c)
02 - Structural Conditions › N/A - No Subsystem › Hull - cracking
Issued 6 October 2022
Resolved
At each initial and subsequent inspection for certification of a vessel, the owner or managing operator shall be prepared to conduct tests and have the vessel ready for inspections of the hull structure and its appurtenances. Cracked and missing welds were noted in the forepeak and fore most storage room. Locations were marked appropriately within the space and need repaired.
46 CFR 115.802(a)
02 - Structural Conditions › N/A - No Subsystem › Hull - cracking
Issued 6 October 2022
Resolved
At each initial and subsequent inspection for certification of a vessel, the owner or managing operator shall be prepared to conduct tests and have the vessel ready for inspections of the hull structure and its appurtenances. Two pieces of longitudinal framing were missing in the STBD side overhead in the forepeak.
46 CFR 115.802(a)
07 - Fire Safety › N/A - No Subsystem › Maintenance of Fire protection systems
Issued 7 September 2022
Resolved
At each initial and subsequent inspection for certification, the owner or managing operator shall be prepared to conduct tests and have the vessel ready for inspection of its fire protection equipment, including the following: Inspection of fixed gas fire extinguishing system to check for excessive corrosion and general condition. CO2 cylinders have a large amount of corrosion on the bottom as the steel cylinders are mounted on an aluminum tray. Operator states that cylinders have not been weighed or moved in over two years.
46 CFR 115.810(a)(1)
07 - Fire Safety › N/A - No Subsystem › Maintenance of Fire protection systems
Issued 7 September 2022
Resolved
At each initial and subsequent inspection for certification, the owner or managing operator shall be prepared to conduct tests and have the vessel ready for inspection of its fire protection equipment, including the following: For fixed gas fire extinguishing systems, the inspections and tests required by Table 115.810(b). During inspection, operator could not show inspector’s report documenting tests completed IAW requirements in table referenced.
46 CFR 115.810(b)(2)
07 - Fire Safety › N/A - No Subsystem › Ventilation
Issued 7 September 2022
Resolved
At each initial and subsequent inspection for certification, the owner or managing operator shall be prepared to conduct tests and have the vessel ready for inspection of its fire protection equipment, including the following: Inspection and testing of smoke and fire detecting systems (including sensors and alarms) and fire confining appliances (such as fire screen doors and fire dampers). Operator could not show evidence of testing of detection system.
46 CFR 115.810(a)(7)
07 - Fire Safety › N/A - No Subsystem › Ventilation
Issued 7 September 2022
Resolved
A device must be provided to automatically shut down power ventilation serving the protected space and engines that draw intake air from the protected space prior to release of the extinguishing agent into the space. Engine room has powered ventilation that is not on the pressure switch circuit and will not shut down upon activation of CO2 system. 46 CFR 118.410(b)(10)
07 - Fire Safety › N/A - No Subsystem › Fire control plan
Issued 7 September 2022
Resolved
A fire control plan (FCP) must be posted on the vessel in a location that is accessible and visible to all passengers. The plan must show escape routes, areas of refuge, embarkation stations, the location of fire protection/emergency equipment, compartment titles and hazard classification of accommodation and service spaces, and structural fire protection boundaries. Vessel has a Fire Control Plan that is not approved by OCMI and is not visible to all passengers. Additionally, several modifications to the vessel has been made since the current FCP was developed. Submit new plan for review by Marine Safety Center and approval by OCMI.
46 CFR 116.530
07 - Fire Safety › N/A - No Subsystem › Division - decks, bulkheads and penetrations
Issued 7 September 2022
Resolved
Fire load calculations must be submitted by the owner for review to the Marine Safety Center when: A space is designated as a low risk accommodation space by the owner; or the cognizant OCMI determines, based on the quantity of combustibles, that the fire load present in a high risk accommodations space may exceed 37.5 kg (7.5 pounds) of combustibles per square meter (square foot) of deck area. Vessel is using unapproved Fire Control Plan that was developed using fire load calculations that were done before extensive remodeling took place. Boundaries have been moved, flooring has been installed, and furniture has been installed; all of which raises concerns about fire load calculations. Submit calculations to Marine Safety Center for review and approval by OCMI.
46 CFR 116.427(a)
07 - Fire Safety › N/A - No Subsystem › Division - decks, bulkheads and penetrations
Issued 7 September 2022
Resolved
A-Class bulkheads or decks must be composed of steel or equivalent material, suitably stiffened and made intact with the main structure of the vessel, such as the shell, structural bulkheads, and decks. They must be so constructed that, if subjected to the standard fire test, they are capable of preventing the passage of smoke and flame for 1 hour. In addition, they must be so insulated with approved structural insulation, bulkhead panels, or deck covering so that, if subjected to the standard fire test for the applicable time period listed below, the average temperature on the unexposed side does not rise more than (250 °F) above the original temperature, nor does the temperature at any one point, including any joint, rise more than (325 °F) above the original temperature: A-60 Class – 60 minutes. Vessel does not have boundaries in lazarette that meet this requirement. Fire Control Plan lists this space a A-60 boundary.
46 CFR 116.415(a)(2)(i)
07 - Fire Safety › N/A - No Subsystem › Division - decks, bulkheads and penetrations
Issued 7 September 2022
Resolved
Penetrations in A-Class fire control boundaries for electrical cables, pipes, trunks, ducts, etc. must be constructed to prevent the passage of flame and smoke for one hour. In addition, the penetration must be designed or insulated so that it will withstand the same temperature rise limits as the boundary penetrated. A-60 boundary materials are missing in engine room in way of cable and piping penetrations leading out of engine room.
46 CFR 116.415(a)(2)(ii)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Gauges, thermometers, etc
Issued 7 September 2022
Resolved
Sight-flow glasses may be used in lubricating-oil systems provided it has been demonstrated, to the satisfaction of the Commanding Officer, Marine Safety Center, that they can withstand exposure to a flame at a temperature of 927 °C (1700 °F) for one hour, without failure or appreciable leakage. Lube oil tank sight glass has been replaced with a flexible clear PVC tubing. Replace to original design to satisfaction of attending marine inspector.
46 CFR 56.50-80(h)
09 - Working and Living Conditions › 092 - Working Conditions › Lighting (Working spaces)
Issued 7 September 2022
Resolved
Electrical equipment on a vessel must be installed and maintained to: Prevent electrical ignition of flammable vapors. Vessel has installed in engine room a portable, temporary, clipped on, non-UL listed light, and utilizes an uncovered bulb in the engine room.
46 CFR 120.200(d)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 7 September 2022
Resolved
At each inspection for certification and at every other vessel inspection the bilges and other spaces may be examined to see that there is no excessive accumulation of oil, trash, debris, or other matter that might create a fire hazard, clog bilge pumping systems, or block emergency escapes. Engine rooms were found with bilges containing excessive amounts of oil and temporary catches for oil. Determine the cause of oil accumulation and make repairs to satisfaction of OCMI.
46 CFR 115.830(b)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 7 September 2022
Resolved
Tests must verify that automated vital systems are designed, constructed, and operate in accordance with all applicable requirements of part 62 of this subchapter. The tests must be based upon the failure analysis, if required by § 62.20-3(b) of this subchapter, functional performance requirements, and the Periodic Safety tests of § 61.40-6. Tests must be performed immediately after the installation of the automated equipment or before the issuance of the initial Certificate of Inspection. Vessel has installed electronic engine controls and does not have an approved set of Design Verification Test Procedures, Qualitative
Failure Analysis, or Periodic Safety Test Procedures.
46 CFR 61.40-3
03 - Water/Weathertight Conditions › N/A - No Subsystem › Scuppers, inlets and discharges
Issued 7 September 2022
Resolved
The OCMI may require an inspection and testing whenever a repair or alteration is undertaken. Vessel has installed a thru hull penetration in the bottom shell of the hull that attempts to make watertight by use of epoxy and composite material. Penetration is under fuel tank. Vessel to submit repair proposal that includes returning hull scantlings and watertight. Once approved, vessel to have properly installed equipment prior to next credit drydock.
46 CFR 115.700(d)
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 7 September 2022
Resolved
Electrical equipment used in the following locations must be dripproof: A machinery Space. Engine electronic control modules for port and starboard main engines have wire bundle drip shields that are not placed on connections properly. Additionally, it looks like excessive dust and debris may have entered wire bundle female connection. Clear of debris and properly install drip shields to satisfaction of attending marine inspector.
46 CFR 120.210(a)(1)
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 7 September 2022
Resolved
C'-Class bulkheads must be constructed to prevent the passage of smoke between adjacent areas. Penetrations in C'-Class boundaries for electrical cables, pipes, trunks, ducts, etc. must be constructed so as to preserve the smoke-tight integrity of the boundary. There three holes in the stairs leading to upper deck. Holes are in a C-Class boundary according to Fire Control Plan.
46 CFR 116.415(a)(2)(vi)
09 - Working and Living Conditions › 091 - Living Conditions › Medical Equipment
Issued 7 September 2022
Resolved
A vessel must carry either a first-aid kit approved under approval series 160.041 or a kit with equivalent contents and instructions. Eyewash and aspirin are expired and must be replaced.
46 CFR 121.710
05 - Radio Communications › N/A - No Subsystem › Satellite EPIRB 406MHz/1.6GHz
Issued 7 September 2022
Resolved
Each vessel that operates on the high seas, or that operates beyond three miles from the coastline of the Great Lakes, must have on board an FCC Type Accepted Category 1, 406 MHz EPIRB, installed to automatically float free and activate. EPIRB battery and hydrostatic release were expired.
46 CFR 117.64
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 7 September 2022
Resolved
The number and identification of the items stowed inside, and their sizes, must be marked in clearly legible letters and numbers on each container for life jackets and immersion suits. Child life jacket storage container is labeled for 25 instead of the required 26 life jackets.
46 CFR 122.604
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 7 September 2022
Resolved
Portable fire extinguishers must be located so that they are clearly visible and readily accessible from the space being protected. The installation and location must be to the satisfaction of the cognizant [name withheld] fire extinguishers in the galley and operating station must be stored in suitable mounting bracket.
46 CFR 118.520
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 7 September 2022
Resolved
Carbon dioxide warning signs. Each entrance to a space storing carbon dioxide cylinders, a space protected by carbon dioxide systems, or any space into which carbon dioxide might migrate must be conspicuously marked as follows: (1) Spaces storing carbon dioxide - “CARBON DIOXIDE GAS CAN CAUSE INJURY OR DEATH. VENTILATE THE AREA BEFORE ENTERING. A HIGH CONCENTRATION CAN OCCUR IN THIS AREA AND CAN CAUSE SUFFOCATION.” (2)Spaces protected by carbon dioxide - “CARBON DIOXIDE GAS CAN CAUSE INJURY OR DEATH. WHEN ALARM OPERATES OR WINTERGREEN SCENT IS DETECTED, DO NOT ENTER UNTIL VENTILATED. LOCK OUT SYSTEM WHEN SERVICING.” Carbon dioxide warning signs are not posted. Verbiage from 46 CFR 122.612(i)(1) must be posted at entrance to lazarette and verbiage from 46 CFR 122.612(i)(2) must be posted at the entrance to the engine room.
46 CFR 122.612(i)(1)(2)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 7 September 2022
Resolved
The arrangement of a vessel must allow the safe operation of the vessel giving consideration to protection against fire. Open and unsecured plastic bottle of hydraulic fluid is being used as overfill for steering system and placed on top of pilot house console. Remove overfill line and plastic bottle from the pilot house.
46 CFR 116.100(a)
09 - Working and Living Conditions › 091 - Living Conditions › Pipes, wires (insulation)
Issued 7 September 2022
Resolved
Electrical equipment on a vessel must be installed and maintained to protect passengers and crew from electrical hazards originating in electrical equipment. Multiple dead end and unused wires are stowed behind pilot house console. Remove all unnecessary wires and dead end wires from space.
46 CFR 120.220(b)
02 - Structural Conditions › N/A - No Subsystem › Bulkheads - cracking
Issued 7 September 2022
Resolved
The construction and arrangement of a vessel must allow for the safe operation of the vessel giving consideration to provisions for a seaworthy hull. Significant hole was made on the starboard bulkhead of the pilot house with insulation exposed to the weather. Ensure weather tight boundary in bulkhead.
08 - Alarms › N/A - No Subsystem › Engineers' alarm
Issued 7 September 2022
Resolved
Alterations to machinery or equipment that affect the safety of the vessel must not be made without the approval of the OCMI, except during an emergency. Alarms for the bow and stern thrusters are covered in duct tape, minimizing the operation and intent of the alarm. Remove tape from alarm.
46 CFR 115.700(a)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 7 September 2022
Resolved
Nonmetallic piping materials, including nonmetallic flexible hose assemblies, must meet the requirements of § 56.60-25 in subchapter F of this chapter. Vessel has a length of piping from a thru-hull to the sewage raw water pump. Submit piping diagram repair proposal that meets 56.50-25 requirements for approval by OCMI.
46 CFR 119.720
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 7 September 2022
Resolved
Non-metallic flexible hose must be in accordance with SAE J1942. 46 CFR 56-60.25(b). Vessel had unauthorized tank truck hoses on both port and starboard engines. Replace with an approved hose.
46 CFR 119.720
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 7 September 2022
Resolved
At each inspection for certification and at every other vessel inspection all observed unsafe practices…and other hazardous situations must be corrected. Vessel has installed an air compressor/receiver in the engine room. Equipment is installed with undersized hardware that is under excessive strain.
46 CFR 115.830(a)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 7 September 2022
Resolved
Nonferrous metallic piping materials are acceptable for use in the following: non-vital systems. Bilge pump piping under fuel tank uses a 12” section of flexible hose material to connect piping to strainer.
46 CFR 119.730(a)(1)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 7 September 2022
Resolved
At each inspection for certification and at every other vessel inspection all observed unsafe practices…and other hazardous situations must be corrected. Bilge high level alarms in lazarette and storage void can get stuck in the up position.
46 CFR 115.830(a)
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 7 September 2022
Resolved
At each inspection for certification and at every other vessel inspection all observed unsafe practices, fire hazards, and other hazardous situations must be corrected. Explosive MAP gas cylinder was found in storage void.
46 CFR 115.830(a)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 7 September 2022
Resolved
Sluice valves are not permitted in watertight bulkheads. Bilge piping leading to forepeak and through collision bulkhead is fitted with a sluice (gate) valve.
46 CFR 119.500(a)
04 - Emergency Systems › N/A - No Subsystem › Emergency fire pump and its pipes
Issued 7 September 2022
Resolved
At each initial and subsequent inspection for certification of a vessel, the owner or managing operator shall be prepared to conduct tests and have the vessel ready for inspections of…piping systems, including the following: Operational test of all overboard discharge and intake valves and watertight bulkhead pipe penetration valves. During testing of the fire pump/ bilge pump system, raw water intake valve was found stuck open. After several tries, operator was able to close valve.
46 CFR 115.804(g)
04 - Emergency Systems › N/A - No Subsystem › Emergency fire pump and its pipes
Issued 7 September 2022
Resolved
The fire pump must be capable of delivering a single hose stream from the highest hydrant, through the hose and nozzle required by § 118.320 of this part, at a pitot tube pressure of 345 kPa (50 psi). During testing of the fire pump, 50 psi could not be reached. Marine Inspector found that overboard discharge valve could not close all the way due to an improperly maintained/stuck ball valve and an installation to ball valve that has handle hitting the bulkhead before fully seated in the closed position. After several attempts, operator was able to close valve. Subsequently, fire pump pressure was able to reach the minimum 50 psi.
46 CFR 118.300(b)
09 - Working and Living Conditions › 092 - Working Conditions › Pipes, wires (insulation)
Issued 7 September 2022
Resolved
Penetrations and openings in watertight bulkheads must have a means to make them watertight. Cable penetrations must be made watertight.
46 CFR 171.114(a)(2)
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 7 September 2022
Resolved
All cable and wire must be installed with metal supports spaced not more than 24 inches. The use of plastic tie wraps must be limited to bundling and not used as a means of support. Plastic ties and rope was observed in the engineroom in multiple places as a means of support of cable, wire and hoses. Properly support cable, wiring and hoses.
46 CFR 120.340(b)(4)
09 - Working and Living Conditions › 092 - Working Conditions › Safe means of access
Issued 9 June 2021
Resolved
On a vessel on which the number of passengers permitted on upper decks is limited by stability criteria, as indicated by the vessel's stability letter, the maximum number of passengers allowed on an upper deck must be indicated by a durable marking of at least 1 inch numbers and letters at the entranceway to that deck. Upper deck restricted to 166 passengers as per stability letter not marked.
11 - Life Saving Appliances › N/A - No Subsystem › Operation of Life Saving Appliances
Issued 9 June 2021
Resolved
Each survival craft must be: stowed so that when the vessel sinks the survival craft floats free and, if inflatable, inflates automatically. Hydrostatic release was improperly connected on 01 IBA preventing its automatic release.
07 - Fire Safety › N/A - No Subsystem › Means of escape
Issued 9 June 2021
Resolved
Each door, hatch, or scuttle, used as a means of escape, must be capable of being opened by one person, from either side. Emergency escape hatch in storage void seized from the inside.
11 - Life Saving Appliances › N/A - No Subsystem › Stowage and provision of liferafts
Issued 9 June 2021
Resolved
Life floats must not be stowed in tiers more than 4 high. When stowed in tiers, the separate units must be kept apart by spacers. Life floats were not separated by spacers.
11 - Life Saving Appliances › N/A - No Subsystem › Inflatable liferafts
Issued 13 March 2019
Resolved
Passed service date.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 13 March 2019
Resolved
missing 86 pmls
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 13 March 2019
Resolved
Hand rails 01 deck aft do not meet 39.5 after MOD.
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 13 March 2019
Resolved
VSL Security Plan not onboard and outdated. Vsl rep stated the vessel will remain in DD until sold. If vessel is placed into the water a new plan will need to be submitted and approved.
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Emergency preparedness
Issued 13 March 2019
Resolved
Conducted underway drills prior to carring passengers.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 13 March 2019
Resolved
Out of service date.
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 13 March 2019
Resolved
Life jacket storage adrift, need to be properly secured 02 deck.
05 - Radio Communications › N/A - No Subsystem › VHF EPIRB
Issued 13 March 2019
Resolved
Hydro release out of date.
10 - Safety of Navigation › N/A - No Subsystem › Automatic Identification System (AIS)
Issued 13 August 2018
Resolved
The vessel is currently broadcasting (1) Zero Draft, (2) Ship Type missing.
Engineering › Gasoline Engine (auxiliary) › Fuel Intake (2 stroke)
Issued 25 June 2018
Resolved
Port F/O supple hose from filter to gov. wasted. Port SSDG.
Engineering › Diesel Engine (propulsion-reduction gear) › Waste Heat Recovery
Issued 25 June 2018
Resolved
Port and STBD MDE exp. tank pressure caps leaking.
Engineering › Diesel Engine (propulsion-reduction gear) › Nozzle, Injection (fuel injection)
Issued 24 June 2018
Resolved
Vessel loss propulsion during mooring on port engine. Would not allow for start up during, initial attemps. Captain was able to start moring after, engine did start and ran at idle next morning. Company is trouble shooting.
Engineering › Generator (propulsion-electric) › Winding
Issued 24 June 2018
Resolved
The port generator set was recently installed improperly, mounting bolts are missing.
Engineering › Gasoline Engine (auxiliary) › Fuel Intake (2 stroke)
Issued 24 June 2018
Resolved
Port SSDG return F/O hose is worn and wasted.
Lifesaving › Work Vest › Condition
Issued 9 May 2018
Resolved
Provide proper size lifevest for MOB drill.
Operations/Management › Lifesaving › Op Readiness/Maintenance/Inspection
Issued 9 May 2018
Resolved
Properly secure rescue plat form while conducting MOB drill.
Engineering › Diesel Engine (propulsion-reduction gear) › Exhaust Manifold
Issued 12 February 2018
Resolved
The owner made modifications to the vessels MDE approved exhaust piping system. Prove proper operation of the modified system as currently installed.
Fire Fighting › Structural - A Class Divisions › Doors
Issued 12 February 2018
Resolved
The vessels main engine room and rudder room hatchs are not insulated iaw approved drawnings, no means of securing, and is not air tight, that would other wise prevent smoke or co2 if activated egress from inside the protected space.
Construction/Loadline › Hull › Weld
Issued 24 October 2017
Resolved
Vessel has an approx. 30" crack along weld at port side (amid ship) open passenger deck on previous welding insert. See narrative for details.
Engineering › Compressed Air System (control) › Compressor
Issued 15 March 2017
Resolved
IAW 46 CFR 54.01-5(4) Class II; III Pressure vessels that have a net internal volume of less than 5 ft3 must be stamped with either the ASME "U" or "UM" symbol. The existing pressure vessel does not have a "U' stamp; shows signs of corrosion. Replace with approved pressure vessel.
Fire Fighting › Structural Fire Protection - General › Structural Bulkhead Construction
Issued 15 March 2017
Resolved
Repair structural fire protection in engine room and tankroom where indicated.
Electrical › Electric Supply System (service) › Cable
Issued 15 March 2017
Resolved
Install guard over a/c - d/c converters atop batteries port and STBD sides. Exposed cable connections.
Electrical › Electric Supply System (service) › Battery Charger
Issued 15 March 2017
Resolved
Install drip shield for charge on stbd side of engine room where indicated.
Electrical › Lighting (service) › Lighting Branch Circuit
Issued 15 March 2017
Resolved
Provide DATA on LED rope lighting on second deck passenger area.
Fire Fighting › Structural - A Class Divisions › Store-rooms
Issued 15 March 2017
Resolved
Remove all spray foam "Great Stuff" from bulkhead penetrations throughout vessel as indicated. Install approved fire stop.
Construction/Loadline › Structures › Transverse Bulkhead
Issued 15 March 2017
Resolved
Repair cracked weld in Rod room where indicated. STBD side first bulkhead on the fwd side.
Electrical › Electric Supply System (service) › Cable
Issued 15 March 2017
Resolved
Remove all dead end cables in engine room as indicated.
Navigation › Collision/Grounding Avoidance › Radar
Issued 15 March 2017
Resolved
Repair #1 Radar, will not turn on.
Operations/Management › Drills/Instruction › Abandon Ship
Issued 15 March 2017
Resolved
Conduct drills. MOB, SECURITY, and FIRE. Unable to conduct underway drills due to weather.
Engineering › Shafting/Propeller Arrangements › Coupling
Issued 6 May 2014
Resolved
Found STBD shaft missing shaft key in coupling hub. Conduct repairs and operational test to be witness by Coast guard Marine Inspector.
Engineering › Engine Controls (Electric/Electronic) › Actuator
Issued 14 April 2014
Resolved
Demonstrate proper operation of primary shift actuators on both engines IAW 46 CFR 115.804(a).
Engineering › Shafting/Propeller Arrangements › Coupling
Issued 14 April 2014
Resolved
Align starboard engine with shaft IAW 46 CFR 119.200(a).
Engineering › Diesel Engine (propulsion-direct drive) › Gear/Clutch Starter (electric)
Issued 25 March 2014
Resolved
Prove proper operation of propulsion machinery once repairs are complete IAW 46 CFR 119.200.
Stability › Watertight Integrity › General
Issued 25 March 2014
Resolved
Repair starboard shaft seal to ensure watertight integrity is maintained IAW 46 CFR 116.100(a).
Fire Fighting › Remote Fuel Shutoff › General
Issued 25 March 2014
Resolved
Ensure remote fuel shutoffs completely close the valves in the supply piping IAW 46 CFR 119.455(b)(3).
Lifesaving › Lifejacket/PFD (General) › Marking
Issued 25 March 2014
Resolved
Ensure lifejackets are marked with only the current name of the vessel IAW 46 CFR 122.604(b).
Engineering › Diesel Engine (propulsion-direct drive) › Charge Air Cooling
Issued 25 March 2014
Resolved
Determine purpose of permanently installed fan pointing at the aft end of the port engine IAW 46 CFR 115.830(a).
Engineering › Freshwater System (jacketwater cooling) › Filter
Issued 25 March 2014
Resolved
Repair drip leak on starboard generator raw water strainer IAW 46 CFR 119.420.
Construction/Loadline › Hull › Stiffener
Issued 25 March 2014
Resolved
Repair cracked weld on inboard side of starboard rudder post supports IAW 46 CFR 116.100(a).
Lifesaving › Lifefloat › Quantity
Issued 21 July 2009
Resolved
The vessels passenger count to a total of 188 passengers when operating under a coastwise route until four additional lifefloats are placed onboard and stowed in accordance with 46 CFR 117.130 and 117.137 respectively.
Pollution Prevention/Response › Prevention Equipment › Sewage System Piping
Issued 21 July 2009
Resolved
Repair leak in sewage pipe overboard discharge.
Construction/Loadline › Hull › Bottom Plating
Issued 10 July 2009
Resolved
MAKE PERMANENT REPAIR TO FRACTURED BOTTOM PLATING ABOVE PORT PROPELLER PRIOR TO CARRYING PASSENGER FOR HIRE.
Engineering › Steering Gear System › Piping
Issued 3 March 2009
Resolved
Repair hydraulic leaks IWO stbd. aft steering gear in steering compartment.
Engineering › Shafting/Propeller Arrangements › Propeller Shaft
Issued 3 March 2009
Resolved
Realign stbd. propulsion shaft after repairs to the broken stbd. intermediate strut are made.
Stability › Incline Test › General
Issued 3 March 2009
Resolved
Provide a letter from a Recognized [name withheld] attesting to the vsl's current stability and structural strength created from unauthorized modifications and alterations during second deck window installations.
Lifesaving › Lifejacket/PFD (Type I) › Lights
Issued 11 August 2008
Resolved
Vessel was missing lights on all PFD's on 2nd deck (approximately 121 adult & 10 child). Vessel required to have all PFD's onboard fitted with approved lights prior to operating 20 nm or more or by 12SEP08.
Engineering › Fuel Oil Service System › Piping
Issued 11 August 2008
Resolved
Vessel to replace missing flame bowl IWO STBD engine.
Accommodation/Occupational Safety › Washroom/Toilet › Toilet
Issued 11 August 2008
Resolved
Vessel to repair broken support bracket for the vessel's MSD (type III) overboard PVC piping and replace worn piping; piping shows signs of wear from rubbing against deck long.
Engineering › Freshwater System (jacketwater cooling) › Hose
Issued 11 August 2008
Resolved
Vessel missing one of the two required hose clamps IWO port engine's cooling water hose; add additional hose clamp on hose.
Fire Fighting › Fire Pumps › Suction Valve
Issued 11 August 2008
Resolved
Fire pump gauge found frozen during testing; gauge stuck on 20psi; replace frozen pressure gauge.
Construction/Loadline › Structures › Longitudinal Bulkhead
Issued 11 August 2008
Resolved
Weld fractures (5) on Port and Stbd. #1 & 2 longitudinal deck frames IWO sewage compartment.
Engineering › Sea-water System (primary cooling) › Sea Chest
Issued 27 June 2007
Resolved
INSTALL HANDLE ON FWD SEA CHEST SUPPLY VALVE.
Electrical › Electric Supply System (service) › Battery Installation
Issued 27 June 2007
Resolved
INSTALL LOCK WASHERS ON SUPPLY BATTERIES.
Documentation › Certificates/Documents › FCC SSL
Issued 27 June 2007
Resolved
PROVIDE FCC STATION LICENSE.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 27 June 2007
Resolved
UPDATE FIRST AID KIT.
Fire Fighting › Structural Fire Protection - General › Hull Construction
Issued 27 June 2007
Resolved
PROVIDE MISSING INSULATION IWO MACHINERY & LAZARETTE WHERE MISSING PER SFP PLAN (A-60 BULKHEADS AND SIDES TO WATERLINE).
Fire Fighting › Structural Fire Protection - General › Superstructure Construction
Issued 27 June 2007
Resolved
REPLACE EMERGENCY FUEL CUTOFF ACCESS COVERS W METALLIC A-0 MATERIAL.
Documentation › Safety/Response Plans/Programs › Fire Control Plans
Issued 27 June 2007
Resolved
UPDATE FIRE CONTROL PLAN TO MEET 46 CFR 116.520 THRU 116.530. (PFD LOCATION & NUMBER, AFT PULL BOX, SFP UNDER PILOT HOUSE)
Documentation › Safety/Response Plans/Programs › General Arrangement Plans
Issued 27 June 2007
Resolved
PROVIDE UPDATED PASSENGER COUNT DETERMINATION SHOWING CURRENT CONFIGURATION. (FIXED SEATING & DECK AREA)
Construction/Loadline › Hull › Bottom Plating
Issued 1 June 2007
Resolved
Conduct an underwater survey by a third party dive company, prior to operation.
Operations/Management › Vessel Safety Management › Maintenance of Ship/Equipment
Issued 21 March 2007
Resolved
The vessel shall be dry-docked to determine the cause of the fracture to the stbd shaft and to ensure that no other damage exists with any other hull, shaft, steering or propulsion component/system. No component on the vessel shall be removed or replaced without notification to the cognizant [name withheld], a satisfactory test of the vessel's propulsion/steering shall be conducted.
Fire Fighting › Fixed Fire Detection System › Manually Operated Call Points
Issued 6 June 2006
Resolved
Replace all Fire-Lite pull stations on main deck to Notifier pull stations (Model BGX-101L) as per Coast Guard approved plan dated 18APR01. POC fire rep installed the wrong style pull stations.
Fire Fighting › Fixed Fire Detection System › Manually Operated Call Points
Issued 6 June 2006
Resolved
Repair STBD AFT Notifier pull station. Pull station has a short in wire and the repair company can not repair until 09JUN06. This vessel has two other pull stations with-in 15 feet, so allowed to operate with 1 of 5 being OOC. Will follow-up during DEF check sched for 14JUN06.
Fire Fighting › Fixed Fire Detection System › Manually Operated Call Points
Issued 6 June 2006
Resolved
Repair PORT FWD pull station to signal/ID properly at control panel. When energized, the STBD signal shows up on the control panel.
Fire Fighting › Fixed Fire Detection System › Manually Operated Call Points
Issued 6 June 2006
Resolved
Position STBD pull station, when replaced, to work properly. When installed, they placed the pull station to close to the shelf, and enables the pull station to operate. Unable to pull the switch down to activate alarm.
Documentation › Certificates/Documents › FCC SSL
Issued 6 June 2006
Resolved
Provide a FCC Station License for vessel. When new license was issued last year, the FCC inspector issued a bridge-to-bridge license instead of the station license.
Lifesaving › Buoyant Apparatus › Retroreflective Material
Issued 6 June 2006
Resolved
Replace retro reflective material on life floats as needed.
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 6 June 2006
Resolved
Replace stern light with proper navigational light IAW 46CFR120.420 (72COLREGS) (UL1104 approved), prior to night time operation. Crew had installed a normal light fixture.
Fire Fighting › Structural - A Class Divisions › Aux Spaces (little/no fire risk)
Issued 6 June 2006
Resolved
Replace insulation in overhead, as needed, in rudder room and tank room.
Construction/Loadline › Penetrations › Pipe Flange
Issued 6 June 2006
Resolved
Remove un-used black iron pipes for old hydraulic system and properly seal penetrations. Old system was never removed and could cause problems in BLKHD penetrations being of dissimilar metal.
Fire Fighting › Fire Main › Condition
Issued 6 June 2006
Resolved
Remove PVC patch and properly repair OVBD DISCH pipe from fire/bilge pump. Crew had installed a temp PVC pipe coupler on the DISCH line.
Fire Fighting › Fixed Fire Detection System › Approval
Issued 27 April 2006
Resolved
PROVIDE CG APPROVED PLANS FOR INSTALLED NOTIFIER AFP-200 FIRE PROTECTIVE SYSTEM.
Accommodation/Occupational Safety › Other Accommodation Spaces › Open Deck Space
Issued 11 May 2005
Resolved
Label upper deck ladder ways to show maximum passengers of 216.
Lifesaving › Lifejacket/PFD (General) › Storage
Issued 11 May 2005
Resolved
Stow life preservers throughout accommodation spaces IAW 46CFR117.78. All jackets are stowed on the main deck.
Engineering › Diesel Engine (propulsion-reduction gear) › Piping (exhaust)
Issued 11 May 2005
Resolved
Repair water leak on PMDE exhaust muffler/cooler. Water leaking from the underside of muffler/cooler box. Found a doubler and an excess hatch on the bottom identifying previous problems.
Engineering › Diesel Engine (propulsion-electric) › Air Silencer
Issued 11 May 2005
Resolved
Repair leak on STBD GENSET water muffler. Water leaking from side, through fiberglass muffler.
Lifesaving › Lifefloat › Capacity
Issued 11 May 2005
Resolved
Provide lifefloats for 50 persons to meet required 50% LF capacity. They only have two 50 person LR (100 persons) and need enough for 50 more passengers to carry 298 persons.
Documentation › Manuals/Policy Documentation › Maneuvering Information
Issued 11 May 2005
Resolved
Provide and post Senior Dech Hand letters on bridge.
Engineering › Steering Gear System › Hydraulic Hose
Issued 11 May 2005
Resolved
Repair STBD steering ram hydraulic hose leak. Outboard hose fitting is wasted and leaking fluid.
Engineering › Diesel Engine (propulsion-reduction gear) › Cylinder Head
Issued 11 May 2005
Resolved
Provide an oil fill cap for PMDE, inboard valve cover. They have duct tape of fill port to prevent oil from spalshing out.
Fire Fighting › Ventilation Systems › Duct Hatches
Issued 11 May 2005
Resolved
Properly stow or mount engine room vent covers, and identify location on fire control plan. Covers were just laying by each vent and the crew didn't know where they were going to stow them at the time of inspection. POC stated that they may place them in the old galley area.
Electrical › Electric Supply System (service) › Cable
Issued 11 May 2005
Resolved
Update electrical drawing w/new air conditioners and the removal of the grill. They have removed the old grill and have added two air conditioners.
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 11 May 2005
Resolved
Properly attach float light to ring life buoy IAW 46CFR117.70(d)(2)&(3). Line from light had no clip and was tied to ring.
Accommodation/Occupational Safety › Other Accommodation Spaces › Open Deck Space
Issued 11 May 2005
Resolved
Post all required security and safety placerds. They are painting vessel and all placards are on the bridge.
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 11 May 2005
Resolved
Update fire control plan to show the removal of the upper deck seating area. FC Plan shows fixed seating on upper deck that has been removed. Measured rail for approved passenger capacity, ALL SAT. POC is going to put self-standing PVC tables and chairs that are removable.
Fire Fighting › Fixed Fire Detection System › Heat Detectors
Issued 11 May 2005
Resolved
Prove proper operation of the heat detection system. Third party was onboard to demonstrate system, but could not get it to work. Third party stated that it worked two days prior.
Communications › Radio Communications › EPIRB
Issued 11 May 2005
Resolved
Provide or prove new EPIRB is registered to vessel. POC had a new EPIRB that is properly marked and dated, but not registered.
Documentation › Certificates/Documents › FCC SSL
Issued 11 May 2005
Resolved
Provide an FCC Station License for vessel. They have a safety certificate and a bridge-to-bridge certificate.
Construction/Loadline › Hull › Side Shell
Issued 11 May 2005
Resolved
Prior to the completion of your next credit dry dock, crop and renew aluminum areas IWO the two eye pads bolted on the PORT side. Submit a repair proposal and new mooring arrangements for approval, prior to any work to be conducted.
Lifesaving › Lifejacket/PFD (Type I) › Lights
Issued 10 August 2004
Resolved
Install lights on 13 child lifejackets.
Pollution Prevention/Response › Prevention Equipment
Issued 14 October 2003
Resolved
Close and secure sewage system discharge valve. LEGACY COMPONENT DESC: Sewage System Valve
Engineering › Bilge Water Management System › Piping
Issued 14 October 2003
Resolved
Remove temporary bilge piping system from sewage tanks.
Accommodation/Occupational Safety › Occupational Safety
Issued 14 October 2003
Resolved
Properly secure port passenger gate aft. LEGACY COMPONENT DESC: Deck Rail
Documentation › Safety/Response Plans/Programs
Issued 23 July 2003
Resolved
Provide Fire Control Plan LEGACY COMPONENT DESC: Fire Control Plans
Documentation › Safety/Response Plans/Programs
Issued 23 July 2003
Resolved
Provide Passenger Evacuation Plan LEGACY COMPONENT DESC: Passenger Evacuation Plan
Stability › Watertight Integrity
Issued 23 July 2003
Resolved
Install gasket on watertight hatch for fwd void space. LEGACY COMPONENT DESC: Hatch
Electrical › Electrical Distribution System (service)
Issued 23 July 2003
Resolved
Properly mount electrical outlet box. LEGACY COMPONENT DESC: Junction Box
Pollution Prevention/Response › Prevention Equipment
Issued 23 July 2003
Resolved
Repair leaking MSD valve. LEGACY COMPONENT DESC: Marine Sanitation Device, Type III
Documentation › Manuals/Policy Documentation
Issued 23 July 2003
Resolved
Provide updated Nav Rules, Coast Pilot, and Light List. LEGACY COMPONENT DESC: Nav Publications
Engineering › Fuel Oil Service System
Issued 23 July 2003
Resolved
Replace wasted flame impingement bowl under fuel strainer. LEGACY COMPONENT DESC: Discharge Strainer
Lifesaving › Lifejacket/PFD (Type I)
Issued 23 July 2003
Resolved
Eleven (11) child lifejackes missing lights LEGACY COMPONENT DESC: Lights
Electrical › Electrical Distribution System (service)
Issued 23 July 2003
Resolved
Provide blanks for missing breakers in stbd operators distribution box. LEGACY COMPONENT DESC: Panelboard
Accommodation/Occupational Safety › Occupational Safety
Issued 23 July 2003
Resolved
V/W cracked bulwarks stiffners at deck #10, 19, 20 on port side LEGACY COMPONENT DESC: Deck Rail
Accommodation/Occupational Safety › Occupational Safety
Issued 23 July 2003
Resolved
V/W cracked bulwarks stiffners #8, 9, and 10 on stbd side. LEGACY COMPONENT DESC: Deck Rail
Documentation
Issued 18 June 2001
Resolved
Comply with FCC requirement for installed of marine radio. Provide copy of cert upon issuance.
Lifesaving
Issued 18 June 2001
Resolved
Provide first aid kit with all components listed in 46 CFR 160.041.
Navigation
Issued 18 June 2001
Resolved
Provide proper size bell for vessel. (Vessel is 80.3 ft therefore requires a 12" bell).
Casualty record · 9
19 April 2002Routine · role: Involved in a Marine Casualty · activity 1608109
21 March 2007Routine · role: Involved in a Marine Casualty · activity 2892427
1 June 2007Routine · role: Involved in a Marine Casualty · activity 2951431
29 April 2012Routine · role: Involved in a Marine Casualty · activity 4313675
8 December 2012Routine · role: Involved in a Marine Casualty · activity 4500319
6 May 2014Routine · role: Involved in a Marine Casualty · activity 4879451
6 May 2017Routine · role: Involved in a Marine Casualty · activity 6256866
24 June 2018Routine · role: Involved in a Marine Casualty · activity 6458699
27 July 2018Routine · role: Involved in a Marine Casualty · activity 6519523
Each line is an incident investigation the Coast Guard recorded with this hull among the vessels involved, with the date and the classification the Coast Guard gave it, and the bridge, lock or dam the investigation names where it names one. Involvement is not fault. The investigation narrative is not published. Source: IIR, through 2026.
Recorded names · 3
ROYAL SUNSHINE (2002), ROYAL EXPRESS III (2007–2014), CRYSTAL COAST LADY (2017–2018). Names as the Coast Guard recorded them in incident records, with the years they appear; some are renames and some are spelling variants.
Ownership record
The Coast Guard's documentation record for this hull -- the Abstract of Title,
with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National
Vessel Documentation Center, files it here with its date, and every reader of this page gets it.