Records from 1986 to 2025. Most recent: inspection, 5 March 2025.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 84
5 March 2025
Annual Inspection · MTSA Verification
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 8088510
24 January 2024
Drydock Exam · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7854188
9 January 2024
MTSA Verification · Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7845362
24 April 2023
In-Service Inspection · Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7674354
3 January 2023
MTSA Verification · COI Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7609100
20 January 2022
Internal Structural Exam · Hull Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7382864
6 January 2022
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7376380
6 January 2022
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7376393
20 January 2021
Annual Inspection · Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7126858
24 February 2020
Hull Examination · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6914296
19 February 2020
Administrative Inspection · Annual Inspection · MTSA Verification
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6911355
12 February 2019
MTSA Verification · Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6626317
1 February 2018
Internal Structural Exam · Drydock Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6362068
9 January 2018
Deficiency Check · COI Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6334528
12 September 2017
In-Service Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6271179
31 January 2017
Deficiency Check · Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6080109
4 February 2016
Drydock Exam · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5819949
5 January 2016
Annual Inspection · MTSA Verification
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5790960
27 February 2012
Internal Structural Exam · Deficiency Check · Hull Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 4252785
6 January 2012
Annual Inspection · MTSA Verification
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 4219977
6 January 2011
MTSA Verification · Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3922398
24 February 2010
Deficiency Check · Hull Examination · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3685208
13 January 2010
Annual Inspection · MTSA Verification
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3662779
12 May 2009
Administrative Inspection
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 3487602
18 February 2009
MTSA Verification · Annual Inspection · Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3420168
7 February 2008
Hull Examination · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3143564
2 January 2008
COI Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3123532
13 February 2007
Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 2871451
29 January 2007
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 2863347
29 March 2006
Annual Inspection · MARPOL Annex V Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 2612653
26 January 2006
Internal Structural Exam · Hull Examination
Physical examination · Sector Long Island Sound · USCG Northeast District (CGD-NE) · Activity 2573933
4 April 2005
Annual Inspection · MARPOL Annex V Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 2326325
28 September 2004
Plan Review (Other than "T")
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 2207639
23 August 2004
MTSA Verification
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 2174464
25 February 2004
Internal Structural Exam · Hull Examination · Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 2012703
15 January 2004
Annual Inspection · MARPOL Annex V Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1985195
25 November 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1954781
6 January 2003
MARPOL Annex V Examination · COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1733189
28 February 2002
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1489966
31 January 2002
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1482922
23 January 2001
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1057833
9 February 2000
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1403046
5 January 2000
COI Inspection · MARPOL Annex V Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1444254
26 February 1999
Plan Review "T" Boat
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 796872
6 January 1999
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1469233
15 January 1998
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 774781
15 January 1998
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1110480
8 January 1998
Re-Inspection · MARPOL Annex V Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 785870
9 January 1997
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1104702
29 January 1996
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1192095
11 January 1996
MARPOL Annex V Examination · COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 871006
10 January 1995
COI Inspection · MARPOL Annex V Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1148856
31 January 1994
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 853465
11 January 1994
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1163152
28 January 1993
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1138451
12 January 1993
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 828826
21 August 1992
Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1264913
18 March 1992
Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1269040
28 January 1992
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 961129
14 January 1992
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1266866
23 July 1991
Drydock Extension
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 941318
12 February 1991
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1225596
18 January 1991
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 905266
20 December 1990
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 909080
6 April 1990
Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 923120
27 March 1990
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 918308
19 January 1990
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 928761
11 January 1990
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1239039
11 January 1990
Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1242280
29 August 1989
Drydock Extension
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1036457
24 March 1989
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1343133
31 May 1988
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1195089
4 April 1988
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1301221
9 February 1988
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1328740
24 August 1987
Drydock Extension
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1031469
24 August 1987
Drydock Extension
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1338810
11 June 1987
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1029197
26 May 1987
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1337474
30 September 1986
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1313991
24 September 1986
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1005931
10 September 1986
Excursion Permit
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1271778
11 August 1986
Excursion Permit
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 987822
20 June 1986
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1303446
16 June 1986
Credit Drydock · Initial Certification · Initial Construction-Excluding Oversight
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 993278
07 - Fire Safety › N/A - No Subsystem › Evaluation of crew performance (fire drills)
Issued 5 March 2025
No resolution recorded
The owner, charterer, master, or managing operator shall instruct each crew member, upon first being employed and prior to getting underway for the first time on a particular vessel and at least once every three months, as to the duties that the crew member is expected to perform in an emergency including, but not limited to, the emergency instructions listed on the emergency instruction placard required by § 122.510, when applicable, the duties listed in the station bill required by § 122.514. Did not conduct drills during annual exam. Perform crew drills in the presence of attending MI.
Condition: Invalid
Action required: 701 - Prior to carriage of passengers/cargo
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 5 March 2025
No resolution recorded
Each individual bilge suction must be fitted with a suitable strainer having an open area of not less than three times that of the suction pipe. In addition, a mud box or basket strainer must be fitted in an accessible position between the bilge suction manifold and the pump. MI observed bilge suction strainer in void space #3 deteriorated. Renew as original.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 5 March 2025
No resolution recorded
Doors in A-Class fire control boundaries must meet the following additional requirements:
(1) A door in a bulkhead required to be A-60, A-30, or A-15 Class must be of hollow steel or equivalent material construction, solidly filled with approved structural insulation, and capable of meeting the requirements of an A-15 Class bulkhead"
MI observed fire door between machinery and engine room not meeting fire control boundary with 1/2 inch gap under fire door. Submit repair plan.
Condition: Improper Installation
Action required: 701 - Prior to carriage of passengers/cargo
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 5 March 2025
No resolution recorded
Each portable fire extinguisher on a vessel must be of a type approved by the Commandant. The minimum number of portable fire extinguishers required on a vessel must be acceptable to the cognizant OCMI, but must be not less than the minimum number required by table 1 to § 118.500(b) and other provisions of this section. 03 portable fire extinguishers removed for hydrostatic testing.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 9 January 2024
Resolved
All pressure vessels other than unfired steam boilers shall be protected by pressure relieving devices. The pressure vessel in the pilot house does not have a pressure relief valve.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 February 2024
Resolved 22 January 2024
Resolution: The operator added the required pressure relieving device on the pressure vessel.
04 - Emergency Systems › N/A - No Subsystem › Emergency, lighting, batteries and switches
Issued 9 January 2024
Resolved
Batteries shall be secured against shifting with motion of the boat. The battery located in the pilot house under the helm were not secured to prevent movement. 46 CFR 183.05-20(b) OLD T
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 February 2024
Resolved 22 January 2024
Resolution: The operator secured the battery to prevent movement.
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 9 January 2024
Resolved
Double doors capable of independent operation and latching may have a clearance between the doors of not more than 3.2 millimeters(0.125 inches). However if one door must always be closed first, means shall be provided to ensure that the doors close in the proper order.
Action required: 10 - Deficiency Rectified
Due 9 January 2024
Resolved 9 January 2024
04 - Emergency Systems › N/A - No Subsystem › Functionality of Safety Systems
Issued 24 April 2023
Resolved
Before getting underway on a voyage or as soon as practicable thereafter, the master of a vessel shall ensure that suitable public announcements are made informing all passengers of the following:(1) The location of emergency exits, survival craft embarkation areas, and ring life buoys;(2) The stowage location(s) of life jackets;(3) Either:(i) The proper method of donning and adjusting life jackets of the type(s) carried on the vessel including a demonstration of the proper donning of a lifejacket, or(ii) That passengers may contact a crew member for a demonstration as appropriate,(4) The location of the instruction placards for life jackets and other lifesaving devices;(5) That all passengers will be required to don life jackets when possible hazardous conditions exist, as directed by the master; and(6) If the vessel is operating with reduced manning or equipment requirements in § 176.114 of this chapter.
Vessel's passenger safety orientation script did not include all of the required information.
46 CFR 185.506(a), 16c
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 May 2023
Resolved 2 May 2023
Resolution: Resolved via pictures
07 - Fire Safety › N/A - No Subsystem › Maintenance of Fire protection systems
Issued 24 April 2023
Resolved
The owner, managing operator, or a qualified servicing facility as applicable must conduct the following inspections and tests: (1) Portable and semi-portable extinguishers must be inspected and maintained in accordance with NFPA 10 (incorporated by reference, see § 175.600 of this chapter) as amended here: (ii) Monthly inspections required by NFPA 10 may be conducted by the owner, operator, person-in-charge, or a designated member of the crew.
No portable extinguishers are being subjected to monthly inspection.
46 CFR 176.810(b), 16c
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 May 2023
Resolved 2 May 2023
Resolution: Resolved via pictures
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 20 January 2021
Resolved
All cable and wire must be installed with metal supports spaced not more than 610 millimeters (24 inches) apart, and in such a manner as to avoid chafing and other damage. The use of plastic tie wraps must be limited to bundling or retention of multiple cable installations, and not used as a means of support. Install metal supports in engine room and engine room vestibule.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 February 2021
Resolved 30 March 2021
Resolution: Metal supports were installed and plastic tie wraps were removed.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 20 January 2021
Resolved
Electrical equipment on a vessel must be installed and maintained to protect passengers, crew, other persons, and the vessel from electrical hazards, including fire, caused by or originating in electrical equipment, and electrical shock. Replace missing bulb and cover on main distribution panel in engine room.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 February 2021
Resolved 30 March 2021
Resolution: Missing bulb on main distribution panel was replaced.
02 - Structural Conditions › N/A - No Subsystem › Bulkhead strength
Issued 24 February 2020
Resolved
KY02: Replace the doubler on the port side, side shell IVO where vessel rubs on fender at the pier (submit plan proposal for new plate thickness, size and possible frame changes).
Action required: 705 - Other - as specified
Resolved 4 March 2020
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 19 February 2020
Resolved
Replace the missing steel clips for the windows that have aluminum frames.
46CFR72.05-30(a)
Action required: 705 - Other - as specified
Due 1 August 2020
Resolved 20 January 2022
Resolution: Vessel rep notified CG the clips are on backorder from the company, will have them installed by 8/1/20, special note added.
20Jan22 verified fire clips have been installed
07 - Fire Safety › N/A - No Subsystem › Division - decks, bulkheads and penetrations
Issued 19 February 2020
Resolved
Replace the missing insulation on the soft patches in the engine room overhead.
Action required: 705 - Other - as specified
Due 20 April 2020
Resolved 28 February 2020
Resolution: Completed the instalation, all sat.
Documentation › Certificates/Documents › FCC Safety Radiotelephony Certificate
Issued 9 January 2018
Resolved
Provide Safety Radiotelephony Certificate. Restricted to less than 1000ft from shore.
Action required: 705 - Other - as specified
Resolved 16 January 2018
Resolution: Received documentation from vessel of unexpired FCC Radiotelephony Certificate.
Navigation › Piloting/Steering › Coast Guard Light List
Issued 9 January 2018
Resolved
Provide 2018 Coast Pilot and Light List publications.
Action required: 705 - Other - as specified
Due 31 January 2018
Resolved 23 February 2018
Resolution: Confirmed 2018 publications aboard the vessel.
Fire Fighting › Ventilation Systems › Exhaust Ducts (Galley Ranges)
Issued 9 January 2018
Resolved
Clean grease from galley extraction hood.
Action required: 705 - Other - as specified
Due 16 January 2018
Resolved 3 April 2018
Resolution: Attested to properly cleaned galley hood.
Electrical › Electrical Distribution System (service) › Ground Detection
Issued 9 January 2018
Resolved
Trace and remove ground from 120V system.
Action required: 705 - Other - as specified
Due 16 January 2018
Resolved 23 February 2018
Resolution: Confirmed ground was cleared from 120V system.
Electrical › Electrical Distribution System (emergency) › Junction Box
Issued 9 January 2018
Resolved
Enclose wires for high water alarms in junction boxes in bow thruster and pumproom spaces.
Action required: 705 - Other - as specified
Due 31 January 2018
Resolved 19 March 2018
Resolution: Received documentation from [name withheld] attesting to enclosed wires in requested spaces.
Communications › Radio Communications › VHF Radiotelephone
Issued 31 January 2017
Resolved
1) Enter MMSI number into VHF/DSC capable marine radio.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 28 February 2017
Resolved 17 April 2017
Fire Fighting › Structural - A Class Divisions › Fire Doors
Issued 5 January 2016
Resolved
AF01- Repair hole in bottom fire door leading to the galley.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 4 February 2016
Resolved 4 February 2016
Resolution: Attended vessel, fire door was replaced.
Electrical › Electrical Distribution System (service) › Distribution Panel Bus
Issued 5 January 2016
Resolved
AF02- Remove electrical outlet on distribution panel in refrigeration void.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 4 February 2016
Resolved 4 February 2016
Resolution: attended vessel the outlet was removed.
Fire Fighting › Grease Extraction Hood › General
Issued 5 January 2016
Resolved
AF03- Clean galley hood.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 4 February 2016
Resolved 12 January 2016
Resolution: Received an email with a receipt showing that the owner hired a third party to clean all the galley hoods on the vessel.
Construction/Loadline › Structures › Deck Plating
Issued 24 February 2010
Resolved
Crop and renew wasted section of decking in way of gray water pump on the port side of the galley.
Condition: Unknown
Action required: 705 - Other - as specified
Due 24 March 2010
Resolved 10 March 2010
Resolution: Wasted deck removed and replaced. Deficiency cleared.
Construction/Loadline › Structures › Deck Plating
Issued 24 February 2010
Resolved
Crop and renew wasted section of decking in way of fire station #6 on the port side of the galley.
Condition: Unknown
Action required: 705 - Other - as specified
Due 24 March 2010
Resolved 10 March 2010
Resolution: Wasted deck removed and replaced. Deficiency cleared.
Fire Fighting › Grease Extraction Hood › General
Issued 13 January 2010
Resolved
Clean entire galley vent exhaust to satifaction of the Coast Guard
Due 28 February 2010
Resolved 24 February 2010
Resolution: Inspected and verified clean galley exhaust ventilation over stoves and fryers.
Lifesaving › Lifejacket/PFD (Type I) › Condition
Issued 2 January 2008
Resolved
Airbladders in lifejackets failed. Replace in-kind 432 adult and 46 child life jackets. Vessel is reduced to 160 PAX.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 3 January 2008
Resolution: Vessel replaced in-kind 432 adult and 46 child lifejackets.
Fire Fighting › Grease Extraction Hood › General
Issued 29 January 2007
Resolved
Galley ventilation duck riser IWO the exhaust fan is full of grease (aprox 5 gal). Remove combustible material from duck in this area. 46CFR176.25-50
Action required: 705 - Other - as specified
Due 2 February 2007
Resolved 1 February 2007
Fire Fighting › Structural - A Class Divisions › Doors
Issued 29 January 2007
Resolved
Engine room fire door was found tied back in the opened position. Remove FSD hold backs. 46CFR176.25-50.
Was corrected on the spot, def left outstanding to ensure future compliance.
Action required: 705 - Other - as specified
Due 1 March 2007
Resolved 13 February 2007
Engineering › Fuel Oil Service System › Hose
Issued 29 January 2007
Resolved
Bow thruster engine hose in fuel and oil service are dry, cracked, and beyond a reasonable service life, or of improper material and leaking. Replace as needed IAW 46CFR182,20-40
Action required: 705 - Other - as specified
Due 1 March 2007
Resolved 13 February 2007
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 29 January 2007
Resolved
Bow thruster engine is missing insulation on the exhaust manifold and turbocharger. Restore insulation IAW 46CFR182.15-20
Action required: 705 - Other - as specified
Due 1 March 2007
Resolved 13 February 2007
Electrical › Electrical Distribution System (service) › Cable
Issued 29 January 2007
Resolved
Main engine block heaters are powered by temp cords fed through existing cableways. Remove the temp cords and install IAW 46CFR120.340
Action required: 705 - Other - as specified
Due 1 March 2007
Resolved 13 February 2007
Personnel › Training › Familiarization Training
Issued 29 January 2007
Resolved
Log crew training IAW 46CFR122.420
Action required: 705 - Other - as specified
Due 1 March 2007
Resolved 13 February 2007
Electrical › Electric Supply System (service)
Issued 23 January 2002
Resolved
Provide a shore side receptacle for the shore power tie on the vessel. LEGACY COMPONENT DESC: Cable
Due 22 February 2002
Resolved 15 January 2004
Resolution: Vessel installed a breaker for shore power at the main distribution panel. Shore power source also had a proper interlock.
Fire Fighting › Combustible Materials
Issued 23 January 2002
Resolved
Remove carpet from stairwell bulkheads in aft section of the accommodation space. LEGACY COMPONENT DESC: Partial Bulkheads/Decks
Due 22 February 2002
Resolved 13 March 2002
Resolution: New carpet installed and old removed.
Fire Fighting › Structural - A Class Divisions
Issued 23 January 2002
Resolved
Replace glass in fire doors to galley with wire mesh fire safety glass. LEGACY COMPONENT DESC: Openings - Doors
Due 22 February 2002
Resolved 28 February 2002
Resolution: Safety glass installed.
Engineering › Bilge Water Management System
Issued 23 January 2002
Resolved
Prove proper operation of the bilge pump and piping system. LEGACY COMPONENT DESC: Pump
Due 22 February 2002
Resolved 13 March 2002
Resolution: System test sat.
Navigation › Collision/Grounding Avoidance
Issued 23 January 2002
Resolved
Install a 360 degree all white anchor light. LEGACY COMPONENT DESC: Navigation Lights
Due 22 February 2002
Resolved 28 February 2002
Resolution: All around white light installed and tested sat.
Lifesaving
Issued 23 January 2001
Resolved
Free all life jacket locker latches for unhindered access to life jackets in storage compartments.
Condition: Unknown
Due 23 February 2001
Resolved 7 February 2001
Construction/Loadline
Issued 9 February 2000
Resolved
Have gauging report examined by the attending marine inspector prior to floating off dry-dock.
Condition: Unknown
Due 14 February 2000
Resolved 11 February 2000
Construction/Loadline
Issued 9 February 2000
Resolved
Provide gauging report for bilge hull plating in compartment #7 (Bay 1), compartment #6 (beneath sewage tank), and compartment #5 (entire galley compartment). Provide gauging report for sea chests in compartment #7 (Bay 1).
Condition: Unknown
Due 11 February 2000
Resolved 11 February 2000
Construction/Loadline
Issued 15 January 1998
Resolved
PROVIDE DRAFT MARKS ON THE BOW AND STERN OF THE VESSEL.
Condition: Unknown
Due 15 February 1998
Resolved 11 March 1998
Lifesaving
Issued 8 January 1998
Resolved
PROCURE ALUMINUM SPLINT FOR BRIDGE FIRST AID KIT.
Condition: Unknown
Due 22 January 1998
Resolved 15 January 1998
Lifesaving
Issued 8 January 1998
Resolved
PROVIDE TOPSIDE MARKING FOR GALLEY ESCAPE SCUTTLE.
Condition: Unknown
Due 22 January 1998
Resolved 15 January 1998
Lifesaving
Issued 9 January 1997
Resolved
PROVIDE RETRO-REFLECTIVE TAPE FOR FORWARD TWO LIFE RINGS.
Condition: Unknown
Due 23 January 1997
Resolved 23 January 1997
Electrical
Issued 9 January 1997
Resolved
PROVIDE CHAFING GEAR FOR ELECTRICAL WIRE RUNNING THROUGH #3 VOID.
Condition: Unknown
Due 16 January 1997
Resolved 23 January 1997
Construction/Loadline
Issued 9 January 1997
Resolved
REMOVE UN-USED BILGE LINE IN #4 VOID
Condition: Unknown
Due 16 January 1997
Resolved 23 January 1997
Unknown
Issued 9 January 1997
Resolved
PROVIDE EMERGENCY BROADCAST PLACARD
Condition: Unknown
Due 16 January 1997
Resolved 23 January 1997
Construction/Loadline
Issued 9 January 1997
Resolved
PROVIDE TAG ON BILGE MANIFOLD FOR #3 BILGE LINE.
Condition: Unknown
Due 16 January 1997
Resolved 23 January 1997
Deck/Cargo
Issued 9 January 1997
Resolved
REPLACE V BELT ON BOW THRUSTER ENGINE
Condition: Unknown
Due 16 January 1997
Resolved 23 January 1997
Electrical
Issued 9 January 1997
Resolved
REPLACE TURBO CHARGER SEAL ON STBD GENERATOR.
Condition: Unknown
Due 16 January 1997
Resolved 23 January 1997
Engineering
Issued 11 January 1994
Resolved
PERMANENTLY REPAIR EXHAUST LEAK ON PORT MAIN DIESEL ENGINE IN E/R.
Condition: Unknown
Due 11 January 1994
Resolved 11 January 1994
Unknown
Issued 12 January 1993
Resolved
REPLACE MACHINE GUARDS ON PORT AND STBD AIR HANDLERS.
Condition: Unknown
Due 9 February 1993
Resolved 9 February 1993
Electrical
Issued 12 January 1993
Resolved
REMOVE TWO DEAD END WIRES ABOVE DAY TANK IN ENGINEROOM OR ROUTE THEM INTO AJUNCTION BOX.
Condition: Unknown
Due 9 February 1993
Resolved 9 February 1993
Electrical
Issued 12 January 1993
Resolved
REPAIR EMERGENCY LIGHT ON MAIN DECK, PORT SIDE BY AMIDSHIP DOORWAY._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 9 February 1993
Resolved 9 February 1993
Electrical
Issued 12 January 1993
Resolved
REPAIR WIRE TO LIGHT ON STBD BULKHEAD BY ENTRANCE TO COMPARTMENT WHICH HOLDS HOT WATER TANKS.
Condition: Unknown
Due 9 February 1993
Resolved 9 February 1993
Electrical
Issued 12 January 1993
Resolved
REPAIR/REPLACE PRESSURE GAUGE ON #1 GENERATOR FUEL FILTER._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 9 February 1993
Resolved 9 February 1993
Electrical
Issued 12 January 1993
Resolved
REPAIR/REPLACE SENDING UNIT FOR LOW LUBE OIL PRESSURE SHUTDOWN FOR #1 GENERATOR.
Condition: Unknown
Due 9 February 1993
Resolved 9 February 1993
Electrical
Issued 12 January 1993
Resolved
REPLACE POWER CORD ON SMALL REEFER IN GALLEY WITH A GROUNDED CORD.
Condition: Unknown
Due 9 February 1993
Resolved 9 February 1993
Electrical
Issued 18 January 1991
Resolved
PROVE PROPER OPERATION OF #2 STARBOARD GENERATOR OVERSPEED.
Condition: Unknown
Due 18 January 1991
Resolved 18 January 1991
Fire Fighting
Issued 19 January 1990
Resolved
PROVIDE PROPER PLANS AND EXPLANATION OF MECHANISM FOR THE FIRE SCREEN DOOR FOR GALLEY ENTRANCE FROM THE MAIN DECK.
Condition: Unknown
Due 19 January 1990
Resolved 19 January 1990
Accommodation/Occupational Safety
Issued 26 May 1987
Resolved
SUBMIT PLANS FOR REVIEW FOR PROPER INSTALLATION OF DECORATIVE LIGHT OR REMOVE PRESENTLY INSTALLED DECORATIVE LIGHTS.
Condition: Unknown
Due 26 May 1987
Resolved 26 May 1987
Fire Fighting
Issued 20 June 1986
Resolved
PROVIDE PROOF OF COMPLIANCE WITH THE USCG APP'D PLANS & COMMENT LETTERS RE-GARDING STRUCTURAL FIRE PROTECTION. PROVIDE MANUFACTURERS OR U.L. LABELING OF ALL FLOOR, WALL AND OVERHEAD COVERINGS AND ANY ADHESIVES USED DURING INSTALLATION.
Condition: Unknown
Due 20 June 1986
Resolved 20 June 1986
Fire Fighting
Issued 16 June 1986
Resolved
PROVIDE PERMANENT LABELLING ON THE MAIN DECK FORWARD FIRE STATION AND THE SECOND DECK FORWARD STARBOARD FIRE STATION.
Condition: Unknown
Due 16 June 1986
Resolved 16 June 1986
Unknown
Issued 16 June 1986
Resolved
PROVIDE PERMANENT LABELLING FOR EACH RESTROOM ENTRANCE THAT INDICATES THE APPROPRIATE GENDER.
Condition: Unknown
Due 16 June 1986
Resolved 16 June 1986
Unknown
Issued 16 June 1986
Resolved
NO GALLEY EQUIPMENT IS TO BE USED UNTIL THE INSTALLED FIXED FIRE EXTIN- GUISHING SYSTEM IS PROVEN SATISFACTORY TO THE COGNIZANT [name withheld] EQUIPMENT SERVICED BY THE VENT HOOD SYSTEM IN WHICH THE EXTIN- GUISHING SYSTEM IS INSTALLED.
Condition: Unknown
Due 16 June 1986
Resolved 16 June 1986
Unknown
Issued 16 June 1986
Resolved
PROVE THE SATISFACTORY INSTALLATION AND OPERATION OF THE ON BOARD COMMUNI- CATION SYSTEM.
Condition: Unknown
Due 16 June 1986
Resolved 16 June 1986
Unknown
Issued 16 June 1986
Resolved
PROVE PROPER LIGHTING AT ALL DECK HOUSE EXITS REQUIRING EMERGENCY LIGHTING.
Condition: Unknown
Due 16 June 1986
Resolved 16 June 1986
Documentation
Issued 16 June 1986
Resolved
PROVIDE THE ORIGINAL STABILITY LETTER TO THE COGNIZANT [name withheld], VESSEL MAY NOT CARRY PASSENGERS.
Condition: Unknown
Due 16 June 1986
Resolved 16 June 1986
Unknown
Issued 16 June 1986
Resolved
PROVE COMPLIANCE WITH THE USCG APPROVED PLANS AND COMMENT LETTERS REGARDINGSTRUCTURAL FIRE PROTECTION, INCLUDING MANUFACTURER'S OR UL LABELLING OF ALLFLOOR, WALL AND OVERHEAD COVERINGS AND ANY ADHESIVES USED DURING INSTALLA- TION.
Condition: Unknown
Due 16 June 1986
Resolved 16 June 1986