Records from 1985 to 2017. Most recent: inspection, 3 August 2017.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 54
3 August 2017
Construction Oversight · Hull Examination · Plan Review "T" Boat
Physical examination · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 6229810
5 March 2014
Internal Structural Exam · Drydock Exam · Deficiency Check
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 4820554
6 October 2010
Annual Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 3864240
1 July 2008
Deficiency Check · Annual Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 3253846
30 June 2008
Hull Examination
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 3252902
7 September 2007
Annual Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 3051996
16 August 2006
Deficiency Check
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 2749529
11 July 2006
Hull Examination · COI Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 2708512
6 June 2006
Deadweight Survey
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 2672059
17 August 2005
Re-Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 2465048
10 June 2005
Administrative Inspection
Administrative · Sector Key West · USCG Southeast District (CGD-SE) · Activity 2385829
26 May 2005
Administrative Inspection · In-Service Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 2368616
12 January 2005
Deficiency Check · In-Service Inspection
Physical examination · Sector Key West · USCG Southeast District (CGD-SE) · Activity 2265297
19 August 2004
Hull Examination
Physical examination · MSD MARATHON · USCG Southeast District (CGD-SE) · Activity 2169921
7 July 2004
Re-Inspection · Deficiency Check
Physical examination · MSD MARATHON · USCG Southeast District (CGD-SE) · Activity 2124391
25 June 2003
MARPOL Annex V Examination · Re-Inspection
Physical examination · MSD MARATHON · USCG Southeast District (CGD-SE) · Activity 1826206
18 March 2003
Deficiency Check
Physical examination · MSD MARATHON · USCG Southeast District (CGD-SE) · Activity 1760761
24 July 2002
MARPOL Annex V Examination · Deficiency Check · Re-Inspection
Physical examination · MSD MARATHON · USCG Southeast District (CGD-SE) · Activity 1660414
2 July 2002
Hull Examination
Physical examination · MSD MARATHON · USCG Southeast District (CGD-SE) · Activity 1639756
11 August 2001
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1072648
11 July 2001
MARPOL Annex V Examination · COI Inspection
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1470037
3 August 2000
Re-Inspection · MARPOL Annex V Examination
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1440370
22 June 2000
Hull Examination
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1393463
25 August 1999
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1115364
3 August 1999
Re-Inspection · MARPOL Annex V Examination
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1404821
22 July 1998
MARPOL Annex V Examination · COI Inspection
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1129819
14 July 1998
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1129170
11 June 1998
Hull Examination
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1127381
6 October 1997
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 786283
3 July 1997
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 781764
1 July 1997
Re-Inspection · MARPOL Annex V Examination
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 780325
11 June 1996
Re-Inspection · Hull Examination
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 878899
28 July 1995
COI Inspection
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 883752
8 August 1994
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 868194
26 May 1994
Hull Examination · Deficiency Check · Re-Inspection
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1171028
15 December 1993
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1162924
8 November 1993
Re-Inspection
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1162862
21 June 1993
Re-Inspection · Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 846280
9 January 1993
Administrative
Administrative · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 829900
10 June 1992
COI Inspection · Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 943045
27 January 1992
Administrative
Administrative · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1269379
16 September 1991
Administrative
Administrative · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1310700
11 June 1991
Re-Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 934681
29 August 1990
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 921726
17 August 1990
Type not recorded
No type recorded · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1233464
26 July 1990
Re-Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 911988
27 June 1990
Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1236317
8 June 1989
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1342969
6 March 1989
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1198292
26 January 1989
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 897084
22 November 1988
COI Inspection · Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 896467
13 January 1988
Re-Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1325662
17 June 1987
Re-Inspection · Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1004411
12 December 1985
Initial Certification
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1299341
Construction/Loadline › Hull › Transverse Frame
Issued 5 March 2014
Resolved
Grind and renew 5 cracked welds #2 Starboard and cracked weld starboard bow outboard.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Accommodation/Occupational Safety › Occupational Safety › Deck Rail
Issued 5 March 2014
Resolved
Grind and renew cracked welds at deck rail stanchions one at starboard aft and two at port amidships.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Construction/Loadline › Hull › Bottom Plating
Issued 5 March 2014
Resolved
Repair pit in #1 Starboard space and three pits at #4 Port space.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Construction/Loadline › Hull › Side Shell
Issued 5 March 2014
Resolved
Submit repair proposal to crop and renew side shell the full length of the # 4 Starboard space inboard and outboard due to severe pitting. Conduct repairs upon approval.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Construction/Loadline › Hull › Transverse Frame
Issued 5 March 2014
Resolved
Submit repair proposal to crop and renew deck cross beam in the #6 Starboard space. Conduct repairs upon approval.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Construction/Loadline › Hull › Transverse Frame
Issued 5 March 2014
Resolved
Grind and renew cracked weld at aft deck/transom at the centerline.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Accommodation/Occupational Safety › Occupational Safety › Tripping/Falling Hazard
Issued 5 March 2014
Resolved
Renew seat cover #6 port space.
Due 5 April 2014
Resolved 17 March 2014
Operations/Management › Bilge/Bilge System Management › Control of Excess Water
Issued 5 March 2014
Resolved
Dry all spaces prior to sea trials.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Construction/Loadline › Penetrations › Valve Flange
Issued 5 March 2014
Resolved
Install shut-off valve at toilet raw water thru-hull fitting.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Engineering › Bilge Water Management System › Pump
Issued 5 March 2014
Resolved
Mount and properly wire all electric bilge pumps and prove proper operation.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Electrical › Electrical Distribution System (service) › Wiring
Issued 5 March 2014
Resolved
Remove dead-end wires observed throughout the vessel spaces.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Construction/Loadline › Hull › Side Shell
Issued 5 March 2014
Resolved
Submit repair proposal for approval by the OCMI for permanent repairs to Port and Starboard hulls at the #5 space inboard and outboard to correct currently installed unapproved doubler plates. The doubler plates have been installed the length of the space from the keel up approx. 4 inches by 5 feet (times 4). Conduct repairs upon approval.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Deck/Cargo › Holds/Tanks › Coaming
Issued 5 March 2014
Resolved
Make permanent repairs to # 6 Starboard hatch coaming.
Action required: 701 - Prior to carriage of passengers/cargo
Due 5 April 2014
Resolved 17 March 2014
Navigation › Piloting/Steering › Inland Navigation Rules
Issued 6 October 2010
Resolved
KW01 Acquire navigation rules publication
Due 8 October 2010
Resolved 7 October 2010
Navigation › Piloting/Steering › Tide/Tidal Current Tables
Issued 6 October 2010
Resolved
KW02 Acquire 2010 Tides and Currents chart
Due 8 October 2010
Resolved 7 October 2010
Documentation › Certificates/Documents › Certificate of Inspection
Issued 6 October 2010
Resolved
KW03 Post COI in a conspicuous place
Due 6 October 2010
Resolved 7 October 2010
Documentation › Certificates/Documents › Stability Letter
Issued 6 October 2010
Resolved
KW03 Post COI in a conspicuous place
Due 6 October 2010
Resolved 7 October 2010
Fire Fighting › Fire Bucket › Lanyard
Issued 6 October 2010
Resolved
KW05 Attach lanyard to 01 fire bucket
Due 6 October 2010
Resolved 7 October 2010
Engineering › Bilge Water Management System › Interface Detector
Issued 6 October 2010
Resolved
KW06 Label bilge alarms with specific spaces, and alarms must be audible and visual.
Action required: 701 - Prior to carriage of passengers/cargo
Due 6 October 2010
Resolved 7 October 2010
Fire Fighting › Portable CO2 Fire Extinguisher › Number
Issued 6 October 2010
Resolved
KW07 Acquire 01 B-I fire extinguisher.
Action required: 701 - Prior to carriage of passengers/cargo
Due 6 October 2010
Resolved 7 October 2010
Lifesaving › Lifebuoys › Buoyant Lifeline
Issued 1 July 2008
Resolved
Replace grab lines on lifebuoy.
Due 9 July 2008
Resolved 7 July 2008
Lifesaving › Lifebuoys › Serviceable
Issued 1 July 2008
Resolved
Replace retroreflective tape on lifebuoy.
Due 9 July 2008
Resolved 7 July 2008
Fire Fighting › Fire Bucket › Quantity
Issued 1 July 2008
Resolved
Obtain (1) fire bucket with lanyard.
Due 1 July 2008
Resolved 1 July 2008
Communications › Radio Communications › EPIRB
Issued 11 July 2006
Resolved
Prove servicing of 406MHZ, type 1 EPIRB, vessel restricted to 3 nm from shore until complete.
Action required: 705 - Other - as specified
Due 11 August 2006
Resolved 14 July 2006
Construction/Loadline › Hull › Bottom Plating
Issued 11 July 2006
Resolved
Provide repair proposal and effect repairs to stress cracks in forward port and starboard compartments to the satisifaction of the attending Marine Inspector. To be completed at scheduled hull exam.
Action required: 705 - Other - as specified
Due 21 July 2006
Resolved 24 July 2006
Documentation › Certificates/Documents › FCC SSL
Issued 11 July 2006
Resolved
Provide proof of valid FCC Radio Safety Certificate.
Action required: 705 - Other - as specified
Due 11 August 2006
Resolved 16 August 2006
Lifesaving › Lifebuoys › Buoyant Lifeline
Issued 11 July 2006
Resolved
Replace UV damaged lifeline on lifebuoy.
Action required: 705 - Other - as specified
Due 11 August 2006
Resolved 14 July 2006
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 17 August 2005
Resolved
Prove proper operation of vessels navigation lights.
Action required: 705 - Other - as specified
Due 17 August 2005
Resolved 17 August 2005
Navigation › Piloting/Steering › Coast Guard Light List
Issued 27 December 2004
Resolved
Provide Coast Guard Light List.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 January 2005
Navigation › Piloting/Steering › Local Notices to Mariners
Issued 27 December 2004
Resolved
Provide Local Notice to Mariners.
Action required: 705 - Other - as specified
Resolved 14 January 2005
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 27 December 2004
Resolved
Attach lanyard to waterlight using brass clip.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 January 2005
Documentation › Markings/Placards › Vessel Number (state)
Issued 27 December 2004
Resolved
Properly mount Emergency Broadcast Placard in vicinity of VHF radio.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 January 2005
Documentation › Markings/Placards › Lifejacket Placard
Issued 27 December 2004
Resolved
Provide lifejacket donning placard and mount appropriately.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 January 2005
Fire Fighting › Remote Fuel Shutoff › General
Issued 27 December 2004
Resolved
Repair or replace fuel shut-off valve access hatch and properly mark the same.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 January 2005
Lifesaving › Lifefloat › Retroreflective Material
Issued 27 December 2004
Resolved
Replace retroreflective material in way of lifefloat.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 January 2005
Lifesaving › Lifefloat › Paddle
Issued 27 December 2004
Resolved
Properly lash paddles to lifefloat.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 January 2005
Communications › Alarms/Indicators › Bilge Alarm
Issued 7 July 2004
Resolved
Repair or replace port and starboard aft high-water alarms.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 7 July 2004
Engineering › Bilge Water Management System › Pump
Issued 7 July 2004
Resolved
Repair or replace port side #5 automatic bilge pump.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 7 July 2004
Communications › Radio Communications › EPIRB
Issued 24 July 2002
Resolved
Renew battery & hydrostatic release for EPIRB.
Action required: 705 - Other - as specified
Due 7 August 2002
Resolved 13 August 2002
Resolution: Corrected.
Engineering › Bilge Water Management System › Pump
Issued 24 July 2002
Resolved
Renew bilge pump in stbd. #2 compartment.
Action required: 705 - Other - as specified
Due 7 August 2002
Resolved 13 August 2002
Resolution: Corrected.
Lifesaving › Lifejacket/PFD (Type I) › Retroreflective Material
Issued 24 July 2002
Resolved
Thoroughly clean all PFD's and renew retroreflective tape as needed.
Action required: 705 - Other - as specified
Due 7 August 2002
Resolved 13 August 2002
Resolution: Corrected.
Documentation › Certificates/Documents
Issued 24 July 2002
Resolved
Provide a valid FCC Radio Operator's Permit. LEGACY COMPONENT DESC: FCC SSL
Action required: 705 - Other - as specified
Due 7 August 2002
Resolved 18 March 2003
Resolution: Recieved a fax copy of Quick-Form Application for Radio Operator Permit with certification of course completion from Flynn Smith.
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 24 July 2002
Resolved
Repair waterlight for ring buoy.
Action required: 705 - Other - as specified
Due 7 August 2002
Resolved 13 August 2002
Resolution: Corrected.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 24 July 2002
Resolved
Provide a USCG approved first aid kit.
Action required: 705 - Other - as specified
Due 7 August 2002
Resolved 13 August 2002
Resolution: Corrected.
Communications › Alarms/Indicators › Bilge Alarm
Issued 24 July 2002
Resolved
Repair bilge high level alarms in port & stbd. aft compartments.
Action required: 705 - Other - as specified
Due 7 August 2002
Resolved 13 August 2002
Resolution: Corrected.
Construction/Loadline › Hull
Issued 2 July 2002
Resolved
Crop and renew #1 and #2 bottom longitudinal frames in way of the #2 starboard compartment. LEGACY COMPONENT DESC: Longitudinal Frame
Condition: Design Flaw
Action required: 705 - Other - as specified
Resolved 15 July 2002
Resolution: Corrected
Construction/Loadline › Hull
Issued 2 July 2002
Resolved
Vee/grind fillet welds on #3 and #4 bottom longitudinal frames in way of the #2 compartment starboard side. LEGACY COMPONENT DESC: Longitudinal Frame
Condition: Unknown
Action required: 705 - Other - as specified
Resolved 15 July 2002
Resolution: Corrected
Construction/Loadline › Structures
Issued 2 July 2002
Resolved
Crop and renew 9th stanchion and rubrail on both the port and starboard side in way of the main deck. LEGACY COMPONENT DESC: Superstructure
Condition: Design Flaw
Action required: 705 - Other - as specified
Resolved 15 July 2002
Resolution: Corrected
Accommodation/Occupational Safety › Occupational Safety
Issued 2 July 2002
Resolved
Install mesh/dodgers/ or courses between the top rail and main deck so that no space is greater than 4 inches. LEGACY COMPONENT DESC: Deck Rail
Condition: Improper Installation
Action required: 705 - Other - as specified
Resolved 15 July 2002
Resolution: Corrected
Construction/Loadline
Issued 11 July 2001
Resolved
Make permanent repairs to trannsom in way of trim tab motors, port and starboard and remove foam sealant.
Condition: Unknown
Due 11 September 2001
Resolved 24 July 2002
Resolution: Corrected.
Navigation
Issued 11 July 2001
Resolved
Provide the following publications on board vessel: Coast Guard Light List and Coast Guard Coast Pilot.
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Deck/Cargo
Issued 11 July 2001
Resolved
Provide mousing for all ground tackle shackles.
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Lifesaving
Issued 11 July 2001
Resolved
Prior to carrying passengers, replace deteriorated netting in 12 person life float and properly mount floating light. Relocate 100 ft painter to more suitable location.
Condition: Unknown
Due 11 August 2001
Resolved 1 August 2001
Electrical
Issued 11 July 2001
Resolved
Remove all deadend wires.
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Electrical
Issued 11 July 2001
Resolved
Properly install wires leading from positive side of battery in accordance with 46 CFR 183.
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Lifesaving
Issued 3 August 1999
Resolved
Renew hydrostatic release for EPIRB.
Condition: Unknown
Due 3 August 1999
Resolved 3 August 1999
Lifesaving
Issued 3 August 1999
Resolved
Provide proof of enrollment for the mate in the vessel's drug consortium.
Condition: Unknown
Due 3 August 1999
Resolved 3 August 1999
Construction/Loadline
Issued 3 August 1999
Resolved
Repair elec bilge pumps in the #3 & 4 port compartments.
Condition: Unknown
Due 3 August 1999
Resolved 3 August 1999
Construction/Loadline
Issued 3 August 1999
Resolved
Install high water alarms in the #4 stbd & port/stbd aft compartments.
Condition: Unknown
Due 3 August 1999
Resolved 3 August 1999
Lifesaving
Issued 3 August 1999
Resolved
Start log for emergency drills & inspection of L/S Equipment.
Condition: Unknown
Due 3 August 1999
Resolved 3 August 1999
Navigation
Issued 22 July 1998
Resolved
Unable to transmit on the VHF radio. Limited route on COI to no more than 1000' from shore until repair/renewal is completed and witnessed by an attending inspector.
Condition: Unknown
Due 24 July 1998
Resolved 29 July 1998
Construction/Loadline
Issued 22 July 1998
Resolved
Fuse connector for the #4S Bilge pump is loose, causing an intermittent connection during the use of the system. Required to repair/renew by 05AUG98.
Condition: Unknown
Due 28 July 1998
Resolved 29 July 1998
Construction/Loadline
Issued 11 June 1998
Resolved
Repair stress crack in starboard fwd. compartment to frame member at haul out in JUL 98._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 11 June 1998
Resolved 11 June 1998
Accommodation/Occupational Safety
Issued 11 June 1998
Resolved
Remove MSD discharge valve for CG inspection at haul out in JUL 98._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 11 June 1998
Resolved 11 June 1998
Navigation
Issued 1 July 1997
Resolved
Provide copy of rules of the road, tide and current tables, coast pilot, light list and T-regs._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 7 July 1997
Resolved 29 July 1997
Lifesaving
Issued 1 July 1997
Resolved
Provide retro-reflective tape on the ring buoy and 12 adult PFDs._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 7 July 1997
Resolved 29 July 1997
Lifesaving
Issued 1 July 1997
Resolved
Provide 8 adult and 4 child PFDs._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 7 July 1997
Resolved 29 July 1997
Lifesaving
Issued 1 July 1997
Resolved
Mark capacity of persons on life float._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 7 July 1997
Resolved 29 July 1997
Lifesaving
Issued 1 July 1997
Resolved
Provide a proper first aid kit._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 7 July 1997
Resolved 29 July 1997
Documentation
Issued 1 July 1997
Resolved
Provide a vessel log book._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 7 July 1997
Resolved 29 July 1997
Documentation
Issued 1 July 1997
Resolved
Provide proof of FCC operators permit._x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 1 July 1997
Resolved 1 July 1997
Lifesaving
Issued 1 July 1997
Resolved
Provide a life jacket donning and emergency broadcast placard and post emergency check off list._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 7 July 1997
Resolved 29 July 1997
Lifesaving
Issued 28 July 1995
Resolved
Provide proof of valid drug testing program.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Lifesaving
Issued 28 July 1995
Resolved
Re-locate stanchions for life float to allow proper stowage and lash paddles to inside netting of life float._x001C_
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Lifesaving
Issued 28 July 1995
Resolved
Post emergency check-off list.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Engineering
Issued 28 July 1995
Resolved
Free-up emer. fuel shutoff valves.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Lifesaving
Issued 28 July 1995
Resolved
Re-stencil emer. fuel shutoffs.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Documentation
Issued 28 July 1995
Resolved
Post stability letter.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Accommodation/Occupational Safety
Issued 28 July 1995
Resolved
Provide means to lock sewage overboard valve closed when operating within territorial waters.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Electrical
Issued 28 July 1995
Resolved
Re-wire bilge pumps using proper (crimp type) connectors.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Lifesaving
Issued 28 July 1995
Resolved
Provide 2 additional adult PFD's. Limited to not more than 38 total personsuntil completed.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Lifesaving
Issued 28 July 1995
Resolved
Provide 5 orange and 3 red hand held flares to replace expired flares.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Lifesaving
Issued 28 July 1995
Resolved
Re-stencil ring buoy with vessel's name and attach painter and approved waterlight.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Documentation
Issued 28 July 1995
Resolved
Provide FCC operators license.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Construction/Loadline
Issued 28 July 1995
Resolved
Repair bilge pump for 2nd compt. from bow port side.
Condition: Unknown
Due 2 August 1995
Resolved 2 August 1995
Construction/Loadline
Issued 26 May 1994
Resolved
Make repairs to #2 and #3 bottom longitudinals in #2 stbd void.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Construction/Loadline
Issued 26 May 1994
Resolved
Repair crack in side strap in #2 port void.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Engineering
Issued 26 May 1994
Resolved
Install bonding wire on fuel fill hose.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Engineering
Issued 26 May 1994
Resolved
Replace rubber fuel line under deck with one made of copper, copper-nickel,or nickel-copper with a minimum wall thickness of .035".
Condition: Unknown
Due 26 May 1994
Resolved 26 May 1994
Engineering
Issued 26 May 1994
Resolved
Replace fuel tank vent hose.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Accommodation/Occupational Safety
Issued 26 May 1994
Resolved
Install valve in MSD inlet line next to hull thru hull.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Engineering
Issued 26 May 1994
Resolved
Replace fuel tank vent screen with proper type.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Construction/Loadline
Issued 26 May 1994
Resolved
Repair 4" crack at bow where previous dive ladder hit hull.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Construction/Loadline
Issued 26 May 1994
Resolved
Repair 2 cracks in new dive ladder bracket.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Documentation
Issued 26 May 1994
Resolved
Provide valid FCC Radiotelephone Certificate.
Condition: Unknown
Due 26 May 1994
Resolved 26 May 1994
Lifesaving
Issued 26 May 1994
Resolved
Modify lifefloat light bracket so it does not hit lifefloat.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Fire Fighting
Issued 26 May 1994
Resolved
Provide suitable hand fire pump or equivalent.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Lifesaving
Issued 26 May 1994
Resolved
Replace webbing straps on lifefloat.
Condition: Unknown
Due 1 June 1994
Resolved 1 June 1994
Lifesaving
Issued 8 November 1993
Resolved
STENCIL STOWAGE OF CHILD PFDS USING 1" LETTERS.
Condition: Unknown
Due 8 December 1993
Resolved 15 December 1993
Fire Fighting
Issued 8 November 1993
Resolved
SERVICE ONE B-II FIRE EXTINGUISHER.
Condition: Unknown
Due 8 December 1993
Resolved 15 December 1993
Construction/Loadline
Issued 21 June 1993
Resolved
Make permanent weld repairs to fractured bottom longitudinal frames; 3 located in 2nd compartment port side, 4 located in 3rd compartment port side, 7 located 2nd compartment starboard side, and 2 located in 3rd compartment starboard side.
Condition: Unknown
Due 1 July 1993
Resolved 1 July 1993
Lifesaving
Issued 21 June 1993
Resolved
Provide 2 paddles for lifefloat.
Condition: Unknown
Due 1 July 1993
Resolved 1 July 1993
Lifesaving
Issued 21 June 1993
Resolved
Repair waterlight for lifefloat.
Condition: Unknown
Due 1 July 1993
Resolved 1 July 1993
Engineering
Issued 21 June 1993
Resolved
Repair emergency fuel shutoffs.
Condition: Unknown
Due 1 July 1993
Resolved 1 July 1993
Accommodation/Occupational Safety
Issued 21 June 1993
Resolved
Repair fractured welds on rail stantion, starboard side aft.
Condition: Unknown
Due 1 July 1993
Resolved 1 July 1993
Fire Fighting
Issued 26 July 1990
Resolved
PROVIDE AN ADDITIONAL B-II FIRE EXTINGUISHER W/MARINE BRACKET.
Condition: Unknown
Due 26 July 1990
Resolved 26 July 1990
Fire Fighting
Issued 26 July 1990
Resolved
PROVIDE A HAND BILGE/FIRE PUMP W/ SUFFICENT HOSE.
Condition: Unknown
Due 26 July 1990
Resolved 26 July 1990
Construction/Loadline
Issued 27 June 1990
Resolved
CREDIT DRYDOCK DUE 27DEC91. CONTACT USCG PRIOR TO THIS DATE TO SCHEDULE THIS INSPECTION.
Condition: Unknown
Due 27 June 1990
Resolved 27 June 1990
Documentation
Issued 22 November 1988
Resolved
PROVIDE FCC RADIO SAFETY CERTIFICATE.
Condition: Unknown
Due 22 November 1988
Resolved 22 November 1988
Lifesaving
Issued 22 November 1988
Resolved
INSTALL 12' LENGTH PENDENTS TIE LINES ON ALL GRABLINE ATTCHMENTS FOR LIFE FLOAT. TIE LINES ARE TO BE OF DARK COLOR & RESISTANT TO UV LIGHT. MUST BE COMPLETED PRIOR TO CARRYING PASSENGERS.
Condition: Unknown
Due 22 November 1988
Resolved 22 November 1988
Fire Fighting
Issued 22 November 1988
Resolved
PROVIDE ONE B-II (1016) DRY CHEM FIRE EXTINGUISHER. MUST BE COMPLETED PRIOR TO CARRYING PASSENGERS.
Condition: Unknown
Due 22 November 1988
Resolved 22 November 1988
Accommodation/Occupational Safety
Issued 22 November 1988
Resolved
INSTALL POSITIVE ACTION SHUT-OFF VALVE & METAL THRU HULL FITTING FOR SINK OVERBOARD.
Condition: Unknown
Due 22 November 1988
Resolved 22 November 1988
Deck/Cargo
Issued 22 November 1988
Resolved
REMOVE HOSE FROM VALVE TO THRU HULL AND INSTALL SHUT-OFF VALVE TO METALLIC PIPING FOR HOLDING TANK OVERBOARD.
Condition: Unknown
Due 22 November 1988
Resolved 22 November 1988
Deck/Cargo
Issued 22 November 1988
Resolved
INSTALL HOSE CLAMPS ON BOTH ENDS OF ALL BILGE DISCHARGE LINES.
Condition: Unknown
Due 22 November 1988
Resolved 22 November 1988
Lifesaving
Issued 13 January 1988
Resolved
PROVIDE PORTABLE HAND HELD FLASHLIGHT FOR AN EMERGENCY LIGHT PRIOR TO CARRYING PASSENGERS.
Condition: Unknown
Due 13 January 1988
Resolved 13 January 1988
Electrical
Issued 13 January 1988
Resolved
REPAIR OR PROPERLY REMOVE DEAD END CABLES TO PORT BLOWER.
Condition: Unknown
Due 13 January 1988
Resolved 13 January 1988