Passenger (Inspected) · Passenger Ship class · Built 1980s · USCG Southeast District (CGD-SE) · Other hulls named FRIENDLY FISHERMAN
FRIENDLY FISHERMAN is a 1987 passenger vessel (inspected). The Coast Guard has recorded 94 inspections since 1987, most recently in December 2025, along with 240 deficiencies and 9 casualty investigations between 2007 and 2025.
Records from 1987 to 2025. Most recent: inspection, 11 December 2025.
- Built
- 1987
- Last inspected
- 11 December 2025
- Documentation
- Valid · documentation file of 10 September 2026
- Deficiencies
- 240 recorded · 0 without a recorded resolution
- Controls
- None recorded without a removal date
- Casualties
- 9 investigations · 2007–2025
Identity
917625
WDD4379
289918
Flag
UNITED STATES
367143950, 367775020
Maury page id
psix-289918
Inspections, by type
…with no type recorded15
Years with a record
35 calendar years (1987–2025)
The 94 inspections in the strip above, split by the kind of activity the US
Coast Guard recorded. Years with a record are calendar years in which a record exists, not
years in service. What Maury does not do.
Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 1977.
Documentation record
Registered dimensions (L × B × D)75.0 ft × 22.0 ft × 8.9 ft
Registered tonnagegross 98 / net 78
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderDUCKWORTH BOATS INC · TARPON SPRINGS, FL, UNITED STATES · built 1987
Hull materialAluminum
PropulsionDiesel Reduction
Hull shapeShip
Hull configurationMonohull
Hailing portTARPON SPRINGS, FL
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 17 March 2026 · expires 31 March 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it98 - Simplified, Gross Ton
78 - Simplified, Net Ton
78 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Radio station licence
WDJ4162MMSI 367775020 · active · voluntarily equipped · granted 28 February 2017, expires 28 February 2027 · licensed under a name not among this hull’s recorded names (not shown)
WDD4379MMSI 367143950 · active · compulsorily equipped · granted 14 September 2016, expires 6 October 2026
WCF7445MMSI not assigned · expired · compulsorily equipped · granted 12 May 1994, cancelled 18 July 2004
FCC Universal Licensing System ship-station file of 6 September 2026, matched to this hull on its
US Official Number. Status and dates are the file’s own. The licensee is not read from the file and is not shown.
A lapsed licence’s MMSI is still the number the vessel transmitted under while it was valid.
Inspection history · 94
11 December 2025
Vessel Attendance · Annual Inspection · Deficiency Check · Administrative Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 8271836
18 February 2025
Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 8073989
6 January 2025
Administrative Inspection
Administrative · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 8058627
5 January 2025
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 8076216
20 December 2024
Hull Examination · Internal Structural Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 8049667
6 December 2023
Annual Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7827566
14 November 2023
In-Service Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7807606
14 September 2023
Administrative Inspection
Administrative · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7791385
1 July 2023
Deficiency Check · Administrative Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7728093
1 July 2023
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7744913
9 January 2023
Deficiency Check · Internal Structural Exam · Hull Examination
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7605116
8 November 2022
COI Inspection · Deficiency Check · Plan Review "T" Boat
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7546900
25 May 2022
In-Service Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7457972
2 February 2022
Annual Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7363864
10 September 2021
Internal Structural Exam · Hull Examination · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7281754
27 March 2021
Damage Survey · In-Service Inspection · Administrative Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7163736
27 March 2021
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7169013
3 February 2021
Deficiency Check · Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7121558
13 June 2020
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6980079
29 January 2020
Annual Inspection · DAPI Audit
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6884874
12 September 2019
Internal Structural Exam · Drydock Exam · Examination of Repairs
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6782574
6 February 2019
Administrative Inspection · Deficiency Check · Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6610660
6 November 2017
DAPI Audit · COI Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6301408
10 October 2017
Deficiency Check · In-Service Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6286473
7 September 2017
Internal Structural Exam · Drydock Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6233285
13 February 2017
DAPI Audit · Administrative Inspection · Annual Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6087404
24 October 2016
Examination of Repairs
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6028284
23 October 2016
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6033440
16 February 2016
DAPI Audit · Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 5816087
14 September 2015
Internal Structural Exam · Examination of Repairs · Hull Examination
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 5719257
17 May 2012
Administrative Inspection
Administrative · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 4313700
13 February 2012
Deficiency Check · Annual Inspection · Administrative Inspection · DAPI Audit
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 4243205
8 September 2011
Internal Structural Exam · Administrative Inspection · Drydock Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 4138565
24 February 2011
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3952576
15 March 2010
Administrative Inspection · DAPI Audit · Annual Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3695788
9 March 2009
Deficiency Check · DAPI Audit · Annual Inspection · Administrative Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3430081
13 September 2007
Internal Structural Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3056765
24 March 2007
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2902143
28 February 2007
Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2880448
19 September 2006
Deficiency Check · Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2770311
15 November 2005
Deficiency Check · Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2534804
28 September 2005
Hull Examination
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 2498062
18 November 2004
Deficiency Check · Annual Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 2242986
20 April 2004
In-Service Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 2049397
16 December 2003
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1965285
28 October 2003
Deficiency Check · Annual Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1929739
14 October 2003
Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1924019
25 October 2002
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1696197
16 August 2002
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1661436
30 May 2002
Examination of Repairs
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1626456
21 December 2001
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1479151
26 November 2001
Re-Inspection · Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1460590
21 November 2001
Type not recorded
No type recorded · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 153932
19 November 2001
Damage Survey
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 772331
18 November 2001
Type not recorded
No type recorded · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 112443
23 October 2001
Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1399732
15 August 2001
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1069170
25 October 2000
Type not recorded
No type recorded · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 111784
16 October 2000
Re-Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1473104
2 November 1999
Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1465509
16 August 1999
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1384229
19 August 1998
Re-Inspection · Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1442732
29 January 1998
Type not recorded
No type recorded · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 670281
1 November 1997
Type not recorded
No type recorded · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 188785
10 October 1997
Deficiency Check · Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1424535
11 August 1997
Re-Inspection · Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1424534
19 August 1996
COI Inspection · Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1371523
12 December 1995
Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1385596
29 August 1995
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1192690
27 June 1995
Type not recorded
No type recorded · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 64939
21 October 1994
Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1174978
2 September 1994
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 862240
27 September 1993
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1153887
8 September 1993
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1142561
7 September 1993
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 829376
16 October 1992
Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1269222
9 September 1992
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1245544
24 October 1991
Type not recorded
No type recorded · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 665298
16 September 1991
Administrative
Administrative · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1248623
13 September 1991
Deficiency Check · COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1248220
30 October 1990
Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 927454
26 October 1990
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 919081
3 October 1990
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1242944
5 September 1990
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 900641
15 November 1989
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1212786
5 September 1989
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1351864
2 May 1989
Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1038493
10 April 1989
Drydock Extension
Administrative · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 890199
14 September 1988
COI Inspection
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1044350
10 March 1988
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1337857
3 December 1987
Administrative
Administrative · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1335024
30 November 1987
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1027574
24 September 1987
Deficiency Check
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1320151
18 September 1987
Initial Certification · Hull Examination
Physical examination · MSO TAMPA · USCG Southeast District (CGD-SE) · Activity 1320733
Deficiency record · 240
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 11 December 2025
Resolved
46 CFR 182.100
All machinery and equipment must be installed and maintained in such a manner as to afford adequate protection from causing fire, explosion, machinery failure, and personnel injury. MI observed hydraulic leaks on both steering rams. Enact permanent repairs to the satisfaction of USCG Marine Inspector.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 11 December 2025
Resolved
46 CFR 182.455 (b) (4)
The shutoff valve at the tank must be manually operable from outside the compartment in which the valve is located. MI observed that valves were not completely closing. Enact permanent repairs to the satisfaction of USCG Marine Inspector.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 11 December 2025
Resolved
46 CFR 181.405 (c)
Vessels described by 46 CFR 175.110(c) must have an interconnected fire detection system in compliance with § 181.450 installed in all enclosed areas where passengers and crew have routine access, including accommodation spaces and machinery spaces. MI observed
that detector in engine room was not operational, and
that a detector was not installed in the pilothouse.
Enact permanent repairs to the satisfaction of USCG
Marine Inspector.
11 - Life Saving Appliances › N/A - No Subsystem › Evaluation, testing and approval
Issued 11 December 2025
Resolved
46 CFR 180.210 (a)
A vessel of more than 19.8 meters (65 feet) in length must carry at least one rescue boat unless the cognizant OCMI determines that the vessel is sufficiently maneuverable, arranged, and equipped to allow the crew to recover a helpless person from the water. During a demonstration of helpless person recovery, the Marine Inspector observed that the recovery method was unsatisfactory. The vessel shall propose procedures and demonstrate a safe and effective method for recovering a helpless person from the water.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 11 December 2025
Resolved
46 CFR 176.810 (b) (ii)
Monthly inspections required by NFPA 10 may be conducted by the owner, operator, person-in-charge, or a designated member of the crew. Vessel logs indicated that fire extinguishers were not being inspected monthly
Corrected on the spot.
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance and inspections
Issued 11 December 2025
Resolved
46 CFR 185.728 (a)
Each EPIRB, other than an EPIRB in an inflatable life raft, must be tested monthly, using the integrated test circuit and output indicator, to determine that it is operative. Vessel logs indicated that EPIRB was not being tested monthly. Corrected on the spot.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 18 February 2025
Resolved
Exhaust gas must not leak from the piping or any
connections in the exhaust system.
Both port and stbd exhaust pipes were leaking cooling
water from the flexible coupling just before passing
through the aft bulkhead. Make repairs to the Coast
Guards satisfaction.
46 CFR 182.430
11 - Life Saving Appliances › N/A - No Subsystem › Distress flares
Issued 18 February 2025
Resolved
Vessel on a Oceans route must carry a total of 12
distress signals, 6 red, 6 smoke, or 12 red. All
distress signals were 1 month expired. New distress
signals were purchased and on board prior to completing
the inspection.
46 CFR 180.68
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 18 February 2025
Resolved
At each inspection each item of fire protection
equipment shall be ready for inspection. The 5th, extra,
fire extinguisher in the E/R had no charge. Service,
replace, or remove to the satisfaction of the Coast
Guard.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 18 February 2025
Resolved
A visual and audible alarm must be provided at the
operating station to indicate high water. The visual
light for compartment 1 was not working. Repair to the
satisfaction of the Coast Guard.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 9 January 2025
Resolved
Deck material wastage discovered beyond 25% within fuel tank room. Repair to the satisfaction of the CG.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 9 January 2025
Resolved
Excessive shaft movement discovered on port and starboard shafts. Remove and inspect. Provide objective evidence to the satisfaction of the CG shafts are not damaged or worn.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 6 January 2025
Resolved
46 CFR 182.100
Machinery and equipment installed on each vessel must be suitable for the vessel and its operation and for the purpose intended. Vessel reported port engine water pump failed. Vessel shall enact permanent repairs to the satisfaction of USCG Marine Inspector.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 6 December 2023
Resolved
All engine exhaust pipes must be water cooled.
MI found the starboard engine exhaust cooling water hose to be deteriorated needing replacement.
46 CFR 182.425
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 6 December 2023
Resolved
Each connection to a conductor or terminal part of a conductor must be made within an enclosure.
Junction box for the DC system located forward of the door on the port side to the accommodation space has no means of closure exposing the wire connections and breakers.
46 CFR 183.340(g)
09 - Working and Living Conditions › 092 - Working Conditions › Guards - fencing around dangerous machinery parts
Issued 6 December 2023
Resolved
An exposed hazard, such as gears or rotating machinery, must be properly protected by a cover, guard, or rail.
MI observed the guard for the belt on the vessel's generator to be missing.
46 CFR 183.340(g)
02 - Structural Conditions › N/A - No Subsystem › Steering gear
Issued 6 December 2023
Resolved
At each initial and subsequent inspection for certification the owner or managing operator shall be prepared to test the steering systems of the vessel and make them available for inspection to the extent necessary to determine that they are in suitable condition and fit for the service intended.
MI found the connection joint of the starboard side ram of the steering gear to be loose causing play in the system.
46 CFR 176.814
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 6 December 2023
Resolved
Each window, port hole, and its means of attachment to the hull or deck house, must be capable of withstanding the maximum load from wave and wind conditions expected due to its location of the vessel and the authorized route of the vessel.
MI observed two broken windows, one located in the wheel house and one on the galley door.
46 CFR 177.1020
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 6 December 2023
Resolved
A lighting fixture must be installed as follows: Each fixture must comply with 183.200.
MI observed the lighting fixture in front of the wheelhouse to be missing the bulb exposing the socket.
46 CFR 183.410(c)
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 14 September 2023
Resolved
Vessels described by 46 CFR 175.110(c) must have an interconnected fire detection system in compliance with § 181.450 installed in all enclosed areas where passengers and crew have routine access, including accommodation spaces and machinery spaces.
Vessel shall install system to the satisfaction of attending USCG Marine Inspector.
46CFR185.405(c)
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 14 September 2023
Resolved
Flammable items not otherwise covered by the regulations of this subchapter, such as rechargeable batteries, including lithium ion batteries utilized for commercial purposes, must be handled, stored, and operated in a way that mitigates the risk of hazardous conditions.
Vessel shall develop plan to the satisfaction of attending USCG Marine Inspector.
46CFR185.364
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 1 July 2023
Resolved
Propulsion machinery must be suitable in type and design for propulsion requirements and capable of operating at constant marine load under such requirements without exceeding its design limitations.
Vessel experienced power load failure and lost propulsion capabilities as a result.
Repair failed equipment and demonstrate proper operation of machinery to attending USCG Marine Inspector prior to carrying passengers.
46 CFR 182.200(a)
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 8 November 2022
Resolved
All vessels must have navigation lights that are in compliance with the applicable sections of the International and Inland Navigation Rules.
MI found the stern light extinguished.
The vessel is limited to daylight without reduced visibility operations.
46 CFR 183.420
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 8 November 2022
Resolved
At each initial inspection for certification of a vessel the owner or operator shall have the vessel ready for inspection all machinery essential to the routine operation of the vessel.
MI found the ships service diesel generator (SSDG) leaking fuel from the fuel manifold.
46 CFR 176.804(c)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 8 November 2022
Resolved
At each initial inspection for certification of a vessel the owner or operator shall have the vessel ready for inspection all machinery essential to the routine operation of the vessel.
MI found the ships service diesel generator leaking fuel from the fuel manifold.
46 CFR 176.804(c)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 8 November 2022
Resolved
At each initial inspection for certification of a vessel the owner or operator shall have the vessel ready for inspection all machinery essential to the routine operation of the vessel.
MI found the starboard MDE emergency fuel shut off valve not completely closing when activated.
46 CFR 176.804(c)
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 8 November 2022
Resolved
The enclosures of all equipment shall be permanently grounded to the metal hull of the vessel by the mounting bolts or other means.
MI found metallic enclosures ungrounded.
46 CFR 183.10-20(g)
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 8 November 2022
Resolved
A dual voltage generator installed on a vessel shall be of the grounded type, where the neutral of a dual voltage system must be solidly connected at the switchboard's neutral bus.
MI found no neutral to ground.
46 CFR 183.324(a)(1)
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 8 November 2022
Resolved
Ground detection must be provided for a dual voltage alternating current system.
The dual voltage AC electrical generator is missing ground detection at the switchboard.
46 CFR 183.324(c)(1)
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 8 November 2022
Resolved
On a metallic vessel, a grounded alternating current system must be grounded to the hull.
MI fund the 110 volt AC appliances ungrounded.
46 CFR 183.376(d)
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 8 November 2022
Resolved
During a fire in the engine room causality the vessel shall follow the emergency checklist including closing air supply by closing ventilators.
MI found in the engine room aft port overhead a ventilation duct without a dampener.
46 CFR 185.25-5(c)
04 - Emergency Systems › N/A - No Subsystem › Water level indicator
Issued 8 November 2022
Resolved
On a vessel of at least 26 feet) in length, a visual and audible alarm must be provided at the operating station to indicate a high water level.
MI found the bilge high level alarms OOC.
46 CFR 185.530(a)
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 8 November 2022
Resolved
The neutral of each grounded generation and distribution system must be grounded at the generator switchboard.
MI found the neutral ungrounded.
46 CFR 183.376(c)
07 - Fire Safety › N/A - No Subsystem › Fire pumps and its pipes
Issued 8 November 2022
Resolved
Each vessel shall be provided with safe, readily available and sufficient firefighting equipment necessary to extinguish a fire.
MI found leaking fire main pipes above the main fire pump in the engine room.
46 CFR 181.01-5
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 8 November 2022
Resolved
New installations of electrical equipment and material, and the repair or replacement of wire and cable, on an existing vessel, shall be completed to the satisfaction of the cognizant [name withheld] found multiple deficiencies in the electrical system to include: missing grounding conductors for all AC items onboard, missing ground bus bar in the distribution panel, missing neutral to ground at the switchboard, and missing ground detection at the switchboard.
The vessel shall submit electrical repair plans to MSC for approval.
46 CFR 183.115(c)
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 8 November 2022
Resolved
Each portable fire extinguisher on a vessel must be of an approved type.
MI found a 40-B:C fire extinguisher waisted from corrosion.
Rectify within 7 days.
46 CFR 181.500(a)
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 8 November 2022
Resolved
All cable and wire must be installed with metal supports spaced not more than 24 inches apart, and in such a manner as to avoid chafing and other damage.
MI found wiring in the AC compartment not properly affixed to metal brackets.
Rectify within 7 days.
46 CFR 183.340(b)(4)
02 - Structural Conditions › N/A - No Subsystem › Stability/strength/loading information and instruments
Issued 8 November 2022
Resolved
All vessels must have permanent draft marks at each end of the vessel or have permanent load markings placed on either side of the forward, amidships, and aft to indicate the maximum allowable draft and trim.
MI found the draft makings required by the vessels stability letter missing from the hull.
Repair during next drydock.
46 CFR 185.30(b)(1)
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 8 November 2022
Resolved
All vessels must have navigation lights that are in compliance with the applicable sections of the International and Inland Navigation Rules, except that a vessel of more than (65 feet) in length must also have navigation lights that meet UL 1104, Standards for Marine Navigation Lights.
MI found navigation lights including, port side light, starboard side light, and mast light lenses severely corroded.
Rectify within 14 days.
46 CRF 183.420
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 8 November 2022
Resolved
Each ring life buoy must be marked in clearly legible block capital letters with the vessel's name.
MI found ring life buoys markings faded and unreadable.
Rectify within 7 days.
46 CFR 185.604(b)
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 8 November 2022
Resolved
Each ring life buoy on a vessel must be approved in accordance with 46 CFR 160.050 in subchapter Q of this chapter.
MI found the starboard aft life ring buoy to be unserviceable due to a cracked water tight plug in the body of the buoy.
Rectify within 7 days.
46 CFR 180.70(b)(1)
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 8 November 2022
Resolved
The fire pump outlet shall be fitted with a pressure gauge.
The MI found the fire pump pressure gauge unserviceable.
46 CFR 181.10-1(c)
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 8 November 2022
Resolved
Each penetration of a watertight bulkhead shall be Accomplished by using an approved method.
MI found missing packing encompassing a cable run from the fuel space to the engine room.
46 CFR 182.40
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 8 November 2022
Resolved
Where flexibility is necessary, a section of flexible metallic hose may be used and is double clamped where practicable.
MI found 5 hose clamps missing from the wet exhaust system.
Rectify within 7 days.
46 CFR 182.430(e)
11 - Life Saving Appliances › N/A - No Subsystem › Buoyant apparatus
Issued 8 November 2022
Resolved
The platform must be arranged so that under normal stowed conditions, it can be retained in the center of the float and can be readily released from this position for use.
MI found the life float basket affixed using an unapproved nylon cord.
Rectify within 7 days.
46 CFR 160.027-3(e)
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 2 February 2022
Resolved
Each connection to a conductor or terminal part of a conductor must be made within an enclosure.
The PA speaker conductor connections on the main deck were not made within an enclosure and conductors are exposed to the elements.
46 CFR 183.340(g)
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 2 February 2022
Resolved
All cable and wire must be installed with metal supports spaced not more than 24 inches apart. The conductors on the main deck located behind where the life jackets are stored on port/stbd upper shelves are not supported.
The conductors are tangled with the life jackets and create a hazard to passengers/crew when removing life jackets.
46 CFR 183.340(a)(4)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 27 March 2021
Resolved
Propulsion machinery shall be suitable in type and design for propulsion requirements of the hull in which it is installed and capable of operating at constant marine load under such requirements without exceeding its designed limitations.
Vessels Starboard engine failed while the vessel was underway with passengers.
After troubleshooting and engine is operational, conduct Sea trials in the presence of Coast Guard marine Inspector.
05 - Radio Communications › N/A - No Subsystem › MF Radio installation
Issued 3 February 2021
Resolved
A vessel must comply with the applicable requirements for any radio and EPIRB installation as set forth in 47 CFR part 80. The vessel's MF-DSC single side band radio is inoperable. The vessel is restricted to voyages no further than 20 miles from shore. 46 CFR 184.502
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 3 February 2021
Resolved
Repairs or alterations to the hull, machinery, or equipment that affect the safety of the vessel must not be made without approval of OCMI. Identified heavy pitting corrosion on two transverse frames in the engine compartment. Engine room frames #1 and #2 (numbered from aft to fwd) were found pitted. Crop and renew frames at the next scheduled dry dock. 46 CFR 176.700
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 3 February 2021
Resolved
The exhaust piping shall be so arranged as to be gas tight throughout its length. Identified corroded exhaust piping in the lazarette for the ship's generator. The corrosion is located at the rubber hose connection for flexibility and permits the flow of exhaust vapor into the space. Make satisfactory repairs and contact MI for re-inspection when complete. 46 CFR 182.20-20
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 12 September 2019
Resolved
The OCMI may require an inspection and testing whenever a repair or alteration is undertaken.
Following main propulsion rebuild and steering gear servicing, conduct sea trials in the presence of a marine inspector. Prior to Credit Dry-dock. 46 CFR176.700(d)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 6 February 2019
Resolved
All vessels shall be provided with a satisfactory arrangement for draining any watertight compartment other than small buoyancy compartments, under all practical conditions.
MI observed unapproved nonmetallic flexible hose at discharge end of bilge system from auxiliary pump. Replace unapproved hoses with approved bilge piping, as listed below, and provide satisfactory operational test.
Approved Bilge piping materials:
1.) Metallic (Aluminum)
2.) Rigid Nonmetallic (PVC)
3.) SAE J-1942 Nonmetallic Flexible Hose w/ approved
1475 fittings.
4.) SAE J-1527 or J-2006 Nonmetallic Flexible Hoses,
meeting the following additional requirements:
- Length of hose must be less than 30 in.
- System pressure must be less than 5 psig.
- Where practicable, have 2 hose clamps at both
ends.
IAW: 46 CFR 182.25-1, 46 CFR 182.40-15, 46 CFR 182.720 (e)
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 6 February 2019
Resolved
In systems and applications where flexible hoses are permitted to be clamped, double hose clamping is required where practicable.
MI observed missing hose clamps on multiple generator hoses. Repair.
IAW: 46CFR182.410 (d) (1)
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 6 February 2019
Resolved
Where life preservers are stowed so that they are not readily visible to passengers, the containers in which they are stowed shall be marked "life preservers".
MI observed faded/illegible life preserve stowage markings in accommodation space. Repair.
IAW: 46 CFR 185.30-15
11 - Life Saving Appliances › N/A - No Subsystem › Buoyant apparatus
Issued 6 February 2019
Resolved
Each item of lifesaving equipment determined by the marine inspector to not be in serviceable condition must be repaired or replaced.
MI observed tear/hole on inside grab line of life-float. Repair.
IAW: 46 CFR 176.808 (b)
09 - Working and Living Conditions › 092 - Working Conditions › Safe means of access
Issued 6 February 2019
Resolved
All escape hatches and other emergency exits shall be marked on both sides using 1-inch letters: "Emergency Exit, Keep Clear".
Escape hatch in engine room was not properly labeled. Label escape hatch with proper wording in no less than 1-inch letters.
IAW: 46 CFR 185.30-15
03 - Water/Weathertight Conditions › N/A - No Subsystem › Covers (hatchway-, portable-, tarpaulins, etc.)
Issued 6 February 2019
Resolved
A vessel is inspected for compliance with the standards required by this subchapter. Machinery, equipment, materials, and arrangements not covered by standards in this subchapter may be inspected in accordance with standards acceptable to the cognizant OCMI as good marine practice.
MI observed forward rope deck pipe missing cover. Replace.
IAW: 46 CFR 16.800 (a)
Lifesaving › Lifefloat › Serviceable
Issued 10 October 2017
Resolved
Install 2 life floats in kind and reduce manning to 40 pax and 4 crew iaw 46CFR180.10-5
Communications › Radio Communications › VHF Radiotelephone
Issued 1 March 2017
Resolved
Provide GPS input to VHF radio containing MMSI number for DSC. 46 CFR 184.502
Stability › Watertight Integrity › General
Issued 1 March 2017
Resolved
Replace missing gasket on aft watertight hatch; prove watertight. 46 CFR 179.360
Stability › Watertight Integrity › General
Issued 1 March 2017
Resolved
Replace missing lanyard on forepeak hatch. 46 CFR 176.360(b)(2)
Electrical › Lighting (service) › Lighting Fixture
Issued 1 March 2017
Resolved
Replace three inoperable lighting fixtures in accommodation space. 46 CFR 183.410
Engineering › Diesel Engine (propulsion-direct drive) › Gear/Clutch Starter (electric)
Issued 24 October 2016
Resolved
Port Engine was reported inoperable. Make proper repairs and prove satisfactory operation of engine. Deficiency is in effect once vessel is dockside. 46CFR 182.200
Engineering › Bilge Water Management System › Piping
Issued 14 September 2015
Resolved
Properly install metallic fittings and shut off valves on all nonmetallic piping that penetrates all water tight bulkheads IAW 46 CFR 182.40
Stability › Weathertight Integrity › General
Issued 14 September 2015
Resolved
Replace cracked bridge window IAW 46 CFR 177.1010
Electrical › Electrical Distribution System (service) › Conductor
Issued 14 September 2015
Resolved
Properly terminate all dead end wires IAW 46 CFR 183.340
Construction/Loadline › Structures › Manhole
Issued 14 September 2015
Resolved
Properly install chain/captive device to forepeak water tight hatch IAW 46 CFR 171.124
Fire Fighting › Fire Pumps › Capacity
Issued 19 March 2012
Resolved
Demonstrate fire pump capacity (gpm) and pressure as per 46 CFR 181.300(b). Submit proposal for pump/system within 07 days of this date. Demonstrate to attending marine inspector within 14 days of this date.
Engineering › Fuel Oil Storage/Transfer System › Piping
Issued 13 February 2012
Resolved
Fuel tank suction lines terminate higher that 1.5 inches above tank bottom as referenced on vessel drawings leaving 150 gallons of fuel in tank unusable. Continue sounding and logging fuel level prior to getting underway. Owner shall provide plans for alteration, or return equipment to original design no later than 08SEP2013 (next dry dock exam) as per 46 CFR 176.700.
Fire Fighting › Emergency Fire Pumps › Pressure
Issued 13 February 2012
Resolved
The power fire pump shall have a minimum capacity of 50 gallons per minute at a pressure of not less than 60 psi, and be fitted with a pressure gauge at the pump outlet. Install pressure gauge and prove proper capacity of fire pump IAW ("Old T") 46 CFR 181.10-1(b) and (c).
Communications › Radio Communications › EPIRB
Issued 15 March 2010
Resolved
Replace hyrdostatic release on EPIRB.
Lifesaving › Lifejacket/PFD (Type I) › Retroreflective Material
Issued 15 March 2010
Resolved
Replace retro-reflective tape on 02 lifejackets.
Engineering › Steering Gear System › Hydraulic Hose
Issued 15 March 2010
Resolved
Replace hydraulic hoses on steering gear with approved JSAE-1942 type hoses.
Construction/Loadline › Hull › Side Shell
Issued 9 March 2009
Resolved
REPAIR/RENEW THE FOLLOWING 4 WASTED SIDE SHELL OVERBOARD FITTINGS.
1. STBD ENGINE ROOM DECK DRAIN
2. PORT ENGINE ROOM DECK DRAIN
3. FISH BOX DRAIN IWO STBD STEERING COMPARTMENT
4. ICE BOX DRAIN IWO STBD STEERING COMPARTMENT
Engineering › Sea-water System (primary cooling) › Piping
Issued 9 March 2009
Resolved
RENEW ROTTEN SEA SUCTION HOSE ON INLET SIDE OF SEA STRAINER FOR BAIT WELL PUMP.
Lifesaving › Lifefloat › Paddle
Issued 9 March 2009
Resolved
RESTENCILE ALL LIFEFLOAT PADDLES AS NEEDED AND REPLACE 2 PADDLES.
Lifesaving › Lifejacket/PFD (Type I) › Retroreflective Material
Issued 9 March 2009
Resolved
REPLACE RETROFLECTIVE TAPE OF LIFEJACKET IDENTIFIED BY CG MARINE INSPECTOR.
Lifesaving › Lifejacket/PFD (Type I) › Quantity
Issued 9 March 2009
Resolved
PASSENGER COUNT IS REDUCED TO 76 UNTIL 9 ADULT LIFEJACKETS ARE PROVIDED.
Lifesaving › Lifefloat › Serviceable
Issued 19 September 2006
Resolved
Prior to the carriage of passengers, relocate life floats so they are not pinned under mast. POC lowered mast so the vessel can run under John's Pass bridge with out the bridge having to open. Doing so, they have pinned the FWD two life floats so to prevent float free if needed.
Lifesaving › Lifejacket/PFD (General) › Retroreflective Material
Issued 19 September 2006
Resolved
Prior to the carriage of passengers, replace retro-reflective tape on jackets as needed. Several jackets the tape had fallen off or was torn from age.
Documentation › Certificates/Documents › FCC SSL
Issued 19 September 2006
Resolved
Provide a corrected FCC Station License. The issued date is the same as the expiration date.
Engineering › Fuel Oil Service System › Hose
Issued 19 September 2006
Resolved
Provide double hose clamps on fuel lines as needed around and on engines. Mechanic changes several F/O lines and replaced them with only one hose clamp.
Accommodation/Occupational Safety › Washroom/Toilet › Toilet
Issued 19 September 2006
Resolved
Repair female head drain pipe in engine room OVHD. Drain pipe is leaking on the deck plates in the engine room just AFT of the PORT engine.
Electrical › Electric Supply System (service) › Cable
Issued 19 September 2006
Resolved
Remove all electrical extension cords throughout vessel. Refrigerator was hooked to an extension cord because it kept tripping the outlet close by.
Electrical › Electric Supply System (service) › Cable
Issued 19 September 2006
Resolved
Properly wire electrical outlet box to system IWO blue shelves in galley. Crew has added a 4 junction outlet box to the power panel with the wrong wire and installation methods.
Engineering › Steering Gear System › Piping
Issued 19 September 2006
Resolved
Repair hydraulic leak for peck cock on PORT steering ram. Oil is leaking around the air peck cock due to vibration. POC will change out with a new valve.
Electrical › Lighting (service) › Conductor
Issued 19 September 2006
Resolved
Properly secure wires IWO after steering OVHD. Brackets supporting wires have fallen off, allowing wires to hang.
Lifesaving › Lifefloat › Float-free Link
Issued 15 November 2005
Resolved
Replace life float weak links (4), or prove strength of existing links. Links were made of very thin fishing wire.
Engineering › Bilge Water Management System › Strainer
Issued 15 November 2005
Resolved
Provide a strainer for your FWD bilge piping pick-up tube. They had replaced the pipe during the yard, but never replaced the strainer.
Lifesaving › Lifejacket/PFD (General) › Storage
Issued 15 November 2005
Resolved
Label all life jacket stowage areas as discussed. Vessel just came from the yard and was missing the labels for the amount and size stowed.
Engineering › Diesel Engine (propulsion-reduction gear) › Crankcase
Issued 15 November 2005
Resolved
Provide a pipe plug on all engine oil drains as needed. STBD red-gear has an oil drain with a ball valve installed, but no cap or plug incase it was accidentally opened.
Construction/Loadline › Structures › Deck Plating
Issued 15 November 2005
Resolved
Seal deck over STBD engine red-gear so to prevent water from dripping on wire runs. The old installed fiberglassed cooler above the STBD engine is leaking down through the deck and onto the engine. POC has to remove the cooler and patch.
Lifesaving › Lifebuoys › Markings (ship name/port)
Issued 15 November 2005
Resolved
Remove letters from retro reflective tape on ring buoy. They placed the name of the vessel on ring which is over the retro tape.
Electrical › Electric Generation Source (service) › Panelboard
Issued 15 November 2005
Resolved
Close up holes on GEN-SET panel IWO galley. They left the old generator control box up and only utilized two of the existing six holes.
Operations/Management › Drills/Instruction › Man Overboard Recovery
Issued 15 November 2005
Resolved
Provide a rescue ladder with a 30 inch x 30 inch platform. Vessel has no platform to rescue a victim in the water besides climbing down an installed ladder off the stern. They will utilize a role-up body recovery ladder while one is being constructed.
Operations/Management › Drug and Alcohol Testing › Employee Coverage
Issued 18 November 2004
Resolved
PROVIDE CURRENT CONSORTIUM CONTRACT AND CREW LIST.
Fire Fighting › Fire Pumps › Pressure
Issued 18 November 2004
Resolved
PROVIDE PRESSURE GAUGE FITTED ON FIRE PUMP OUTLET.
Engineering › Bilge Water Management System › Valve
Issued 18 November 2004
Resolved
RE-LOCATE REACH ROD FOR FWD BILGE SUCTION VALVE IN MANNER TO ALLOW VALVE TO OPEN 100% PRIOR TO COMPLETION OF NEXT DRYDOCK.
Engineering › Freshwater System (jacketwater cooling) › Piping
Issued 18 November 2004
Resolved
REPAIR ALL LEAKS ON STARBOARD MAIN DIESEL ENGINE WET EXHAUST SYSTEM.
Stability › Watertight Integrity › General
Issued 18 November 2004
Resolved
REPLACE STARBOARD BRIDGE WINDOW.
Engineering › Lubricating Oil Service System › Flange
Issued 18 November 2004
Resolved
PROVIDE 3RD PARTY REPORT ATTESTING TO CONDITION OF GENERATOR REAR OIL SEAL LEAK.
Fire Fighting › Remote Fuel Shutoff › General
Issued 18 November 2004
Resolved
PROVIDE MEANS TO PULL EMERGENCY FUEL STOP WITHOUT OPENING ENGIN ROOM DOOR.
Documentation › Markings/Placards › Warning Signs
Issued 18 November 2004
Resolved
LABEL EMERGENCY FUEL STOP.
Engineering › Fuel Oil Storage/Transfer System › Valve
Issued 18 November 2004
Resolved
PROVIDE FUEL OIL SHUT OFF VALVE AT ENGINES.
Communications › Audible Communications › Horn/Whistle
Issued 18 November 2004
Resolved
INSTALL PERMANENT SOUND SIGNAL AUDIBLE FOR ONE NAUTICAL MILE.
Lifesaving › Buoyant Apparatus › Floating Electric Waterlight
Issued 18 November 2004
Resolved
REPLACE STARBOARD OUTBOARD WATERLIGHT BRACKET.
Engineering › Freshwater System (jacketwater cooling) › Piping
Issued 18 November 2004
Resolved
REPAIR PORT SIDE EXHAUST FLANGE AT LAZARETTE BULKHEAD PENETRATION.
Electrical › Electrical Distribution System (service) › Wiring
Issued 18 November 2004
Resolved
REMOVE DEAD END WIRES AND PROPERLY SECURE WIRING AS NEDDED IN ENGINE ROOM
Operations/Management › Drills/Instruction › Man Overboard Recovery
Issued 18 November 2004
Resolved
UPDATE EMERGENCY PROCEDURES TO REFLECT ACTUAL PROCEDURE FOR EACH EMERGENCY SITUATION.
Electrical › Electrical Distribution System (service) › Wiring
Issued 18 November 2004
Resolved
PROPERLY INSTALL ELECTRICAL WIRE TO OLD A/C CIRCULATION PUMP.
Electrical › Electrical Distribution System (service) › Metallic Enclosure/Frame
Issued 18 November 2004
Resolved
INSTALL STUFFING TUBES AS NEEDED IN BULKHEAD PENETRATIONS PRIOR TO COMPLETION OF NEXT DRYDOCK.
Navigation › Collision/Grounding Avoidance › Echo-sounding Device
Issued 18 November 2004
Resolved
PROPERLY INSTALL TRANSDUCER IAW MANUFACTURER INSTRUCTIONS PRIOR TO COMPLETION OF NEXT DRYDOCK.
Navigation › Piloting/Steering › Steering Magnetic Compass
Issued 18 November 2004
Resolved
REPAIR COMPASS LIGHT.
Lifesaving
Issued 28 October 2003
Resolved
Initiate lifesaving equipment records for all lifesaving equipment with expiration dates IAW manufacturer instructions. (46CFR185.702)
Navigation
Issued 28 October 2003
Resolved
Prior to the carriage of passengers, update charts of area of operation.
Lifesaving
Issued 28 October 2003
Resolved
Prior to the carriage of passengers, provide new or prove expiration date of EPIRB hydrostatic release.
Lifesaving
Issued 28 October 2003
Resolved
Re-new drop nets in bottom lifeboat.
Lifesaving
Issued 28 October 2003
Resolved
Prior to the carriage of passengers, replace 01 waterlight and bracket on life float.
Lifesaving
Issued 28 October 2003
Resolved
Re-new retro-reflective tape on life jackets as needed.
Lifesaving
Issued 28 October 2003
Resolved
Repair strapping material on AFT, upper, lifefloat. If float is removed for repair, maximum total persons allowed will be 66 until float is placed back onboard.
Fire Fighting
Issued 28 October 2003
Resolved
Prior to the carriage of passengers, relocate 2-BII fire extinguishers from engine room, to outside the engine room entrance.
Fire Fighting
Issued 28 October 2003
Resolved
Prior to the carriage of passengers, conduct annual service and 5 year hydrostatic test of CO2 cylinders dedicated for engine room, or remove from service.
Navigation
Issued 28 October 2003
Resolved
Prior to the carriage of passengers, repair stern and masthead light.
Engineering
Issued 28 October 2003
Resolved
Prep, prime and preserve, or replace fittings from hydraulic steering hoses to both steering rams.
Engineering
Issued 28 October 2003
Resolved
Repair PORT ram hydrau;ic leak on steering system.
Engineering
Issued 28 October 2003
Resolved
Double hose clamp rubber hose connection on fixed bilge system in AFT steering.
Engineering
Issued 28 October 2003
Resolved
Double hose clamp, FWD port MDE exhaust pipe, in AFT steering.
Electrical
Issued 28 October 2003
Resolved
Provide a proper stuffing tube for cabel IWO FWD BLKHD, port side in AFT steering.
Engineering
Issued 28 October 2003
Resolved
Provide a line diagram/instruction to line up and use the fixed bilge system.
Engineering
Issued 28 October 2003
Resolved
Provide a 2nd self priming bilge pump.
Fire Fighting
Issued 28 October 2003
Resolved
Remove check valve on fire main piping in #3 void.
Engineering
Issued 28 October 2003
Resolved
Double hose clamp all vital systems in engine room.(ex. bilge, raw water cooling, fuel)
Engineering
Issued 28 October 2003
Resolved
Provide plug for S/W system on live bait well sea chest.
Engineering
Issued 28 October 2003
Resolved
Provide a third party report, and repair if needed, cracked chalk-fast for both PORT & STBD engine mounts.
Engineering
Issued 28 October 2003
Resolved
Repair F/O leak on PORT MDE racor filter.
Engineering
Issued 28 October 2003
Resolved
Replace plastic plug to a metal plug on GENSET racor bowl.
Engineering
Issued 28 October 2003
Resolved
Double hose clamp F/O flex piping on GENSET.
Engineering
Issued 28 October 2003
Resolved
Provide a safety shield for STBD engine PTO.
Electrical
Issued 28 October 2003
Resolved
Provide a proper cover for battery charger control box, IWO AFT BLKHD in engine room. (Behind genset)
Electrical
Issued 28 October 2003
Resolved
Provide the proper switch cover for the electrical switch that energizes the bilge pump in engine room. Mounted on the inboard frame, FWD of the STBD engine.
Engineering
Issued 28 October 2003
Resolved
Double hose clamp bilge piping in #3 void.
Engineering
Issued 28 October 2003
Resolved
Double hose clamp flex piping on sea chest piping in #3 void.
Stability
Issued 28 October 2003
Resolved
Tighten deck drain, AFT over-head, STBD side in #3 void.
Engineering
Issued 28 October 2003
Resolved
Cap un-used line from air-conditioning circ pump.
Engineering
Issued 28 October 2003
Resolved
Double hose clamp bilge system in # 2 void.
Electrical
Issued 28 October 2003
Resolved
Provide a cover for battery terminals on battery in #2 void.
Engineering
Issued 28 October 2003
Resolved
Repair reach rod for collision BLKHD bilge piping valve, IWO #1 void.
Engineering
Issued 28 October 2003
Resolved
Provide a third party report on the oil leak for GENSET. Could be a rear oil seal, and repair if needed.
Engineering
Issued 28 October 2003
Resolved
Provide plugs for all engine oil changing lines coming from oil sumps on each engine.
Electrical › Electrical Distribution System (service)
Issued 14 October 2003
Resolved
Plug all loose wires stuffing tubes. LEGACY COMPONENT DESC: Cable
Engineering › Diesel Engine (propulsion-direct drive)
Issued 14 October 2003
Resolved
Repair/clean oil leaks on BMDE's and GENSET.
Accommodation/Occupational Safety › Occupational Safety
Issued 16 August 2002
Resolved
REPLACE STBD BRIDGE WINDOW. LEGACY COMPONENT DESC: Windows
Lifesaving › Buoyant Apparatus
Issued 16 August 2002
Resolved
REPLACE DROP NETS IN UPPER 2 LIFEFLOATS.
Lifesaving › Buoyant Apparatus
Issued 16 August 2002
Resolved
REPLACE PADDLE IN LOWER LIFEFLOAT PRIOR TO CARRIAGE OF PASSENGERS.
Fire Fighting › Miscellaneous Items
Issued 16 August 2002
Resolved
REPLACE FLAME SCREEN FOR FUEL VENT ON STBD SIDE CABIN TOP PRIOR TO CARRIAGE OF PASSENGERS. LEGACY COMPONENT DESC: Flame screen
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 16 August 2002
Resolved
REPLACE WATERLIGHT IN LIFERING PRIOR TO CARRIAGE OF PASSENGERS.
Engineering › Bilge Water Management System › Valve
Issued 16 August 2002
Resolved
REPAIR FWD BILGE SUCTION REACH ROD PRIOR TO CARRIAGE OF PASSENGERS.
Electrical › Lighting (service)
Issued 16 August 2002
Resolved
INSTALL DIFFUSERS ON OVERHEAD LIGHTING IN AFT HEADS AND OVERHEAD ENGINE ROOM STAIRWELL.. LEGACY COMPONENT DESC: Lighting Fixture
Lifesaving › Hand Flares
Issued 16 August 2002
Resolved
PROVIDE 3 ADDITIONAL HAND HELD FLARES PRIOR TO CARIAGE OF PASSENGERS.
Engineering › Sea-water System (primary cooling) › Piping
Issued 16 August 2002
Resolved
REPAIR GENSET WET EXHAUST LEAK IN LAZARETTE PRIOR TO CARRIAGE OF PASSENGERS.
Operations/Management › Prevention Equipment
Issued 16 August 2002
Resolved
POST WASTE MANAGEMENT PLAN IN VIEW OF PASSENGERS.
Communications › Radio Communications
Issued 16 August 2002
Resolved
POST EMERGENCY BROADCAST PLACARD ON BRIDGE.
Fire Fighting
Issued 26 November 2001
Resolved
REPLACE GAUGE ON DISCHARGE SIDE OF FIRE MAIN.
Navigation
Issued 26 November 2001
Resolved
PROVIDE UPDATED COPIES (EXCERPTS) OF COAST PILOT, LIGHT LIST, AND NAVIGATIONAL CHARTS.
Lifesaving
Issued 26 November 2001
Resolved
REPLACE ONE FLOATING WATERLIGHT ON LIFEFLOAT PRIOR TO CARRIAGE OF PASSENGERS.
Documentation
Issued 26 November 2001
Resolved
INITIATE LIFESAVING EQUIPMENT RECORDS.
Lifesaving
Issued 26 November 2001
Resolved
REPLACE RETRO MATERIAL ON 08 ADULT LIFEJACKETS. TOTAL PASSENGERS REDUCED TO 76 UNTIL CORRECTED.
Documentation
Issued 26 November 2001
Resolved
PROVIDE LATEST MIS REPORT FROM CONSORTIUM.
Lifesaving
Issued 26 November 2001
Resolved
REPLACE 4 PADDLES IN 2 LIFEFLOATS PRIOR TO CARRIAGE OF PASSENGERS.
Lifesaving
Issued 26 November 2001
Resolved
REPAINT LIFEFLOATS ORANGE. ENSURE VSL NAME AND CAPACITY ARE STENCILED ON EACH.
Lifesaving
Issued 26 November 2001
Resolved
PROPERLY REGISTER 406MHZ EPIRB.
Engineering
Issued 26 November 2001
Resolved
INSTALL FLAME IMPENGEMENT BOWL ON GENSET FUEL STRAINER.
Electrical
Issued 23 October 2001
Resolved
INSTALL STUFFING TUBES IN BULKHEADS WHERE BARE WIRES ARE RUNNING THROUGH.
Engineering
Issued 23 October 2001
Resolved
INSTALL REMOTE FUEL STOP FOR GENERATOR.
Electrical
Issued 23 October 2001
Resolved
REMOVE DEAD END WIRING FROM ENGINE ROOM.
Fire Fighting
Issued 16 October 2000
Resolved
REPLACE PVC PIPING ON FIRE MAIN WITH METALLIC AS ORIGINAL.
Construction/Loadline
Issued 16 October 2000
Resolved
INSTALL VENT CLOSURE FOR ENGINE ROOM VENTILLATION.
Lifesaving
Issued 16 October 2000
Resolved
DEMONSTRATE RETRIEVAL OF HELPLESS PERSON FROM THE WATER.
Documentation
Issued 16 October 2000
Resolved
INITIATE LIFESAVING EQUIPMENT/EPIRB MAINTENANCE LOGS.
Lifesaving
Issued 16 October 2000
Resolved
PROCURE NEW HYDROSTATIC RELEASE FOR 406 MHZ EPIRB.
Fire Fighting
Issued 16 August 1999
Resolved
REPAIR FIRE MAIN PIPING AND PRESSURE GUAGE ON FIRE MAIN PRIOR TO SAILING.
Lifesaving
Issued 19 August 1998
Resolved
REPLACE/SERVICE EPRIB AND HYDROSTATIC RELEASE MECHANISM.
Electrical
Issued 19 August 1998
Resolved
REPAIR CABLES AND WIRE/WIRINGTHROUGHOUT THE VESSEL. PROPERLY TERMINATE ALLDEAD END CABLES/WIRES; REPAIR SPLICES ON CABLES/WIRES THROUGHOUT.
Accommodation/Occupational Safety
Issued 19 August 1998
Resolved
INSTALL VALVE HANDLE ON MSD SEWAGE DISCHARGE PIPING BETWEEN TANK AND THROUGH HULL PENETRATION.
Lifesaving
Issued 11 August 1997
Resolved
INSTALL RETRO-REFLECTIVE MATERIAL ON ALL LIFERINGS.
Lifesaving
Issued 11 August 1997
Resolved
REPLACE BATTERIES IN ALL WATERLIGHTS.
Fire Fighting
Issued 11 August 1997
Resolved
INSTALL OPERATIONAL PRESSURE GUAGE ON DISCHARGE SIDE OF FIRE PUMP.
Engineering
Issued 11 August 1997
Resolved
DOUBLE CLAMP ALL HOSES ON COOLING WATER SYSTEM FOR MDE'S AND GEN.
Electrical
Issued 11 August 1997
Resolved
REPAIR SWITCH MOUNT ON GEN. BATTERY BOX.
Engineering
Issued 11 August 1997
Resolved
REPLACE BANDING CLAMPS ON MDE EXHAUST BOOTS IN AFT LAZARETTE.
Documentation
Issued 11 August 1997
Resolved
PROVIDE COPY OF MISR.
Electrical
Issued 19 August 1996
Resolved
INSTALL GLOBE COVERS ON LIGHT FIXTURES IN BOTH TOILETS.
Lifesaving
Issued 19 August 1996
Resolved
RESTENCIL VESSEL NAME ON ALL LIFE FLOATS, MINIMUM 3" LETTERS.
Engineering
Issued 19 August 1996
Resolved
RESTENCIL EMERGENCY FUEL SHUT OFF VALVES.
Electrical
Issued 29 August 1995
Resolved
Stencil all emergency lights with 1" red 'E'.
Accommodation/Occupational Safety
Issued 29 August 1995
Resolved
Replace missing overhead insulation in the engine room.
Electrical
Issued 21 October 1994
Resolved
Install electrical junction box at wire splice above port main engine.
Electrical
Issued 21 October 1994
Resolved
Seal wire penetrations in aft port bulkhead fuel tank compartment.
Electrical
Issued 21 October 1994
Resolved
Make water pump wire connection near switch by insulated connection.
Construction/Loadline
Issued 21 October 1994
Resolved
Gauge out leaking weld seams on keel and reweld.
Electrical
Issued 21 October 1994
Resolved
Install wire stuffing tube in forward starboard engineroom bulkhead near access ladder.
Construction/Loadline
Issued 2 September 1994
Resolved
Repair reach rod to bilge valve forward of collision bulkhead.
Documentation
Issued 2 September 1994
Resolved
Provide Radio Telephony Certificate.
Navigation
Issued 2 September 1994
Resolved
Double nut, pin or air-craft nut rudder arm at port & starboard rams.
Lifesaving
Issued 2 September 1994
Resolved
Replace 5 pfd lights (spare pfd's).
Engineering
Issued 7 September 1993
Resolved
INSTALL FUEL SHUTOFF VALVES PRIOR TO THE FLEX HOSES AT PORT, STARBOARD MAINENGINES AND GENERATOR.
Construction/Loadline
Issued 7 September 1993
Resolved
MAKE ENGINE ROOM EMERGENCY ESCAPE HATCH OPERABLE FROM BELOW, AND STENCIL ABOVE AND BELOW WITH "EMERGENCY ESCAPE KEEP CLEAR"
Construction/Loadline
Issued 7 September 1993
Resolved
RESTENCIL VESSEL NAME AND HAILING PORT ON STERN.
Engineering
Issued 7 September 1993
Resolved
REINSTALL FLAME SHIELD ON PORT MAIN ENGINE FUEL FILTER.
Engineering
Issued 7 September 1993
Resolved
RECONNECT BOTH EMERGENCY FUEL SHUTOFF PULL CABLES TO FUEL VALVES.
Accommodation/Occupational Safety
Issued 7 September 1993
Resolved
REINSTALL SCREEN IN RANGE HOOD.
Lifesaving
Issued 9 September 1992
Resolved
Stencil vessel name on L/F paddles.
Navigation
Issued 9 September 1992
Resolved
Double nut both steering ram ends.
Engineering
Issued 9 September 1992
Resolved
Prove reliable operation of emergency fuel shutoff vaves.
Fire Fighting
Issued 9 September 1992
Resolved
Renew or repair fire hose connection.
Fire Fighting
Issued 9 September 1992
Resolved
Provide adequate length of suction hose for hand fire pump.
Lifesaving
Issued 9 September 1992
Resolved
Renew painters on 2 life floats.
Construction/Loadline
Issued 9 September 1992
Resolved
Free up reach rod for fore peak bilge suction.
Construction/Loadline
Issued 30 October 1990
Resolved
CREDIT DRYDOCK DUE 30APR92. CONTACT USCG PRIOR TO THIS DATE TO SCHEDULE THIS INSPECTION.
Construction/Loadline
Issued 30 October 1990
Resolved
NOTIFY [name withheld] WHENEVER VESSEL IS TO BE HAULED OUTOF THE WATER FOR ANY REASON.
Lifesaving
Issued 5 September 1990
Resolved
INSTALL WOOD SPACES BETWEEN STACKED LIFEFLOATS.
Construction/Loadline
Issued 5 September 1990
Resolved
REPAIR CAPTIVE CHAIN AFT HATCH.
Navigation
Issued 5 September 1990
Resolved
REPAIR EPIRB AND RENEW BATTERY PRIOR TO EXCEEDING 20 MILES FROM A HARBOR OFSAFE REFUGE.
Lifesaving
Issued 5 September 1990
Resolved
REPAIR 1 LIFEFLOAT LIGHT IMMEDIATELY, PRIOR TO CARRYING PASSENGERS.
Lifesaving
Issued 5 September 1990
Resolved
ATTACH ALL LIFEFLOAT LIGHTS WITH 18' LINE IMMEDIATELY, PRIOR TO CARRYING PASSENGERS.
Accommodation/Occupational Safety
Issued 5 September 1990
Resolved
SEWAGE O/B VALVE TO BE CLOSED AT ALL TIMES WITHIN 3 MILE LIMIT IMMEDIATELY,PRIOR TO CARRYING PASSENGERS.
Documentation
Issued 5 September 1990
Resolved
POST 3 GARBAGE WARNING STICKERS P&S EXTERIOR, GALLEY.
Documentation
Issued 5 September 1990
Resolved
PROVIDE GARBAGE MANAGEMENT PLAN.
Fire Fighting
Issued 5 September 1990
Resolved
REPAIR FIREPUMP GAGE IMMEDIATELY, PRIOR TO CARRYING PASSENGERS.
Engineering
Issued 5 September 1990
Resolved
DOUBLE CLAMP GEN. EXH. HOSE AFT COMPT.
Fire Fighting
Issued 5 September 1989
Resolved
REPLACE THE 2 FIRE HOSES WITH APPROVED TYPE (BRONZE FITTINGS).
Lifesaving
Issued 5 September 1989
Resolved
MOVE MOUNTING BRACKET FOR PORT RING BOUY AWAY FROM DECK LIGHT FIXTURE SO ITCAN BE EASILY REMOVED.
Engineering
Issued 5 September 1989
Resolved
ADD ADDITIONAL BRACKETS TO THE FUEL OIL SHUTOFF VALVE REACH ROD SO IT CAN BE OPERATED WITHOUT HANGING UP.
Documentation
Issued 2 May 1989
Resolved
DRYDOCK DUE 02NOV90. CONTACT USCG PRIOR TO THIS DATE TO SCHEDULE THIS INSPECTION.
Lifesaving
Issued 18 September 1987
Resolved
PROVIDE ONE ADDITIONAL 22 PERSON LIFEFLOAT.
Electrical
Issued 18 September 1987
Resolved
PROVIDE BATTERIES FOR WATER LIGHTS FOR LIFE FLOATS AND RING BOUY.
Accommodation/Occupational Safety
Issued 18 September 1987
Resolved
INSTALL BLACKOUT CURTAINS ON WINDOWS BETWEEN PILOT HOUSE AND LOUNGE.
Documentation
Issued 18 September 1987
Resolved
PROVIDE STABILITY LETTER FROM U. S. COAST GUARD MARINE SAFETY CENTER.
Documentation
Issued 18 September 1987
Resolved
PROVIDE DOCUMENTATION FOR GENERATOR RECERTIFICATION TO 50 DEG. C AMB. TEMP.
Casualty record · 9
28 February 2007Routine · role: Involved in a Marine Casualty · activity 2880448
24 March 2007Routine · role: Involved in a Marine Casualty · activity 2902143
23 May 2010Routine · role: Involved in a Marine Casualty · at JOHNS PASS BRIDGE · activity 3748265
24 February 2011Routine · role: Involved in a Marine Casualty · activity 3952576
23 October 2016Routine · role: Involved in a Marine Casualty · activity 6033440
13 June 2020Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 6980079
27 March 2021Routine · role: Involved in a Marine Casualty · activity 7169013
1 July 2023Routine · role: Involved in a Marine Casualty · activity 7744913
5 January 2025Routine · role: Involved in a Marine Casualty · activity 8076216
Each line is an incident investigation the Coast Guard recorded with this hull among the vessels involved, with the date and the classification the Coast Guard gave it, and the bridge, lock or dam the investigation names where it names one. Involvement is not fault. The investigation narrative is not published. Source: IIR, through 2026.
Ownership record
The Coast Guard's documentation record for this hull -- the Abstract of Title,
with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National
Vessel Documentation Center, files it here with its date, and every reader of this page gets it.