Records from 1988 to 1994. Most recent: inspection, 22 February 1994.
Documentation record
Registered dimensions (L × B × D)145.8 ft × 27.3 ft × 9.0 ft
Registered tonnagegross 319 / net 179
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderNORTHSEA SHIPYARD LTD. · RINGKOEBING, DENMARK · built 1976
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portMIAMI, FL
Trade endorsementsRegistry
DocumentationNo Operation - PM · issued 26 June 1990
Service, as the file records itFreight Ship
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it319 - Regulatory (Subpart C or D), Gross Ton
179 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 12
22 February 1994
Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1163321
13 February 1994
Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 852952
8 August 1990
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 901686
26 July 1990
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1213846
18 July 1990
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 899557
15 December 1989
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 931334
29 November 1989
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 924521
29 August 1989
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1212399
4 January 1989
Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1348861
1 September 1988
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1043270
14 July 1988
Reflagging & Initial Certification · Hull Examination · Initial Certification
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1042266
14 July 1988
Initial Certification · Reflagging & Initial Certification · Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1348037
Electrical
Issued 26 July 1990
Resolved
PROVE PROPER OPERATION OF FORWARD EMERGENCY GENERATOR INCLUDING ALL SAFETIES REMOTES, ALARMS AND SHUTDOWNS. NEEDED REPAIRS ARE TO BE IN ACCORD-ANCE WITH 46 CFR SUB-CHAPTER "5".
Condition: Unknown
Due 26 July 1990
Resolved 26 July 1990
Fire Fighting
Issued 18 July 1990
Resolved
PROVE PROPER OPERATION OF ENGINEROOM SMOKE DETECTOR.
Condition: Unknown
Due 18 July 1990
Resolved 18 July 1990
Engineering
Issued 18 July 1990
Resolved
PROVE PROPER OPERATION OF MAIL DIESEL ENGINE OVERSPEED TRIP.
Condition: Unknown
Due 18 July 1990
Resolved 18 July 1990
Engineering
Issued 29 August 1989
Resolved
COMPLETE THE FOLLOWING ITEMS OF THE AUTOMATION TEST PROCEDURE #2 GENERATOR HIGH WATER TEMPERATURE ALARM/SHUTDOWN, STEERING ALARM, STARTING AIR ALARM AND RELIEF VALVE TEST, #1 & #2 & SHAFT GENERATOR LOW HZ/OVERLOAD ALARM.
Condition: Unknown
Due 29 August 1989
Resolved 29 August 1989
Electrical
Issued 29 August 1989
Resolved
PDROVE THE PROPER OPERATION OF THE SHAFT GENERATOR.
Condition: Unknown
Due 29 August 1989
Resolved 29 August 1989
Fire Fighting
Issued 29 August 1989
Resolved
PERMANENTLY DISPLAY "FOOLPROOF" INSTRUCTION ON OPERATION OF THE FIXED CO2 EXTINGUISHING SYSTEM.
Condition: Unknown
Due 29 August 1989
Resolved 29 August 1989
Fire Fighting
Issued 29 August 1989
Resolved
PROVE THE PROPER OPERAITON OF THE SMOKE DETECTION SYSTEM. UNTIL THIS IS COMPLETED A MANNED FIRE WATCH SHALL BE SET FOR THE CARGO HOLDS WHEN CARRY- ING HAZARDOUS CARGOES. APPROPRIATE ENTRIES SHALL BE MADE AND MAINTAINED IN THE VESSEL'S LOG AS PROOF OF COMPLIANCE WITH THE LATTER.
Condition: Unknown
Due 29 August 1989
Resolved 29 August 1989
Fire Fighting
Issued 29 August 1989
Resolved
PROVIDE ONE UL APPROVED FIRE HOSE WHERE MISSING. THIS REQUIREMENT TO COMPLETED ASAP.
Condition: Unknown
Due 29 August 1989
Resolved 29 August 1989
Electrical
Issued 29 August 1989
Resolved
PROVIDE FLOURESCENT LIGHT GUARDS THROUGHOUT THE VESSEL WHERE MISSING. (IE. AFT SHOWER, LAUNDRY ROOM, 1ST OFFICER ROOM).
Condition: Unknown
Due 29 August 1989
Resolved 29 August 1989
Documentation
Issued 29 August 1989
Resolved
VSL PTP W/1 "ORD SEAMAN"(IN REPLACEMENT OF FIRED A/B SEAMAN)TO NEXT PORT OFCALL,AT WHICH AN AMERICAN A/B SHALL BE PROVIDED TO BRING SHIP'S CREW LEVEL TO FULL REQ. COMPLIMENT.THIS ALLOWANCE TERMINATED AT NEXT PORT OF CALL OR BY 2SEP89.DOC. & APPRO. LOG ENTRIES PROVIDED TO COG [name withheld] OF COMPLI
Condition: Unknown
Due 29 August 1989
Resolved 29 August 1989
Fire Fighting
Issued 29 August 1989
Resolved
PROVIDE ONE ADDITIONAL B-III SEMI-PORTABLE FIRE EXTINGUISHER FOR THE ENGINEROOM AS REQUIRED BY 46 CFR TABLE 95.50-10(A) "MACHINERY SPACES". TOTAL EQUIPMENT REQUIRED IN ENGINE ROOM: (2) B-II; (1) B-III.
Condition: Unknown
Due 29 August 1989
Resolved 29 August 1989
Fire Fighting
Issued 1 September 1988
Resolved
REPLACE THE THREE (3) STAINLESS STEEL A-II PORTABLE FIRE EXTINGUISHERS WITHTHE PROPER USCG APPROVED MARINE TYPE UNITS.
Condition: Unknown
Due 1 September 1988
Resolved 1 September 1988
Engineering
Issued 1 September 1988
Resolved
PROVIDE TO [name withheld] REPORT INDICATING THE WATER CONTENT OF THE TAILSHAFT SEAL LUBE OIL. THIS SAMPLE SHOULD BE TAKEN APPROX. 30 DAYS AFTER THE VSL IS REFLOATED.
Condition: Unknown
Due 1 September 1988
Resolved 1 September 1988
Fire Fighting
Issued 1 September 1988
Resolved
PROVIDE AND MOUNT PERMANENT OPERATING INSTRUCTIONS FOR THE INSTALLED SMOKE/CO2 FIRE DETECTION SYSTEM.
Condition: Unknown
Due 1 September 1988
Resolved 1 September 1988
Fire Fighting
Issued 1 September 1988
Resolved
PROVIDE PRESSURE GAUGE ON DISCHARGE SIDE OF EMERGENCY FIRE PUMP.
Condition: Unknown
Due 1 September 1988
Resolved 1 September 1988
Fire Fighting
Issued 14 July 1988
Resolved
UPON INSTALLATION OF SMOKE DETECTION SYSTEM IN THE CARGO HOLD AND FORWARD STORAGE COMPARTMENT PROVE PROPER OPERATION OF SAME TO THE SATISFACTION OF ATTENDING COAST GUARD MARINE INSPECTOR.
Condition: Unknown
Due 14 July 1988
Resolved 14 July 1988
Fire Fighting
Issued 14 July 1988
Resolved
REPLACE ALL FIRE FIGHTING EQUIPMENT WITH COAST GUARD APPROVED EQUIPMENT.
Condition: Unknown
Due 14 July 1988
Resolved 14 July 1988
Fire Fighting
Issued 14 July 1988
Resolved
REPLACE ALL FIRE FIGHTING EQUIPMENT WITH COAST GUARD APPROVED EQUIPMENT.
Condition: Unknown
Due 14 July 1988
Resolved 14 July 1988
Fire Fighting
Issued 14 July 1988
Resolved
UPON INSTALLATION OF SMOKE DETECTION SYSTEM IN THE CARGO HOLD AND FOREWARD STOWAGE COMPARTMENT PROVE PROPER OPERATION OF SAME TO THE SATISFACTION OF AATTENDING COAST GUARD MARINE INSPECTOR.;L
Condition: Unknown
Due 14 July 1988
Resolved 14 July 1988