Inspection history · 18
20 November 1996
Type not recorded
No type recorded · MSO GUAM · USCG Oceania District (CGD-O) · Activity 398127
18 December 1995
Administrative
Administrative · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1192715
1 March 1995
COI Inspection
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1164352
19 July 1994
Deficiency Check
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 869934
19 July 1994
Deficiency Check
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 869935
10 June 1994
Deficiency Check
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1178437
15 March 1994
Re-Inspection
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1164818
4 January 1994
Type not recorded
No type recorded · MSO GUAM · USCG Oceania District (CGD-O) · Activity 177594
4 January 1994
Damage Survey
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1358280
11 March 1993
COI Inspection · Hull Examination
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1149303
2 January 1993
Administrative
Administrative · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1140905
18 November 1992
Type not recorded
No type recorded · MSO GUAM · USCG Oceania District (CGD-O) · Activity 139700
9 August 1992
Administrative
Administrative · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1262409
16 April 1992
Re-Inspection
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1257250
25 February 1991
COI Inspection
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1239918
27 September 1990
Type not recorded
No type recorded · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1226416
14 July 1990
Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1224817
19 January 1989
Hull Examination · COI Inspection
Physical examination · MSO GUAM · USCG Oceania District (CGD-O) · Activity 1209490
Construction/Loadline
Issued 1 March 1995
Resolved
CROP OUT AND RENEW ALL DECK FRAMES, SIDE PLATE AND BOTTOM LONGITUDINALS, AND STRUCTUAL FRAME AS REQUIRED BY THE ATTENDING USCG MARINE INSPECTOR OR ABS SURVEYOR DURING NEXT DRYDOCKING BUT NO LATER THAN 01SEP95
Condition: Unknown
Due 1 September 1995
Resolved 18 May 2002
Resolution: MISLE Maintenance - Resolved all open deficiencies issued prior to 6/1/1997 where activity was closed and deficiency due date was past
Construction/Loadline
Issued 4 January 1994
Resolved
MAKE PERMANENT REPAIRS TO THE STARBOARD STERN RAKE.
Condition: Unknown
Due 1 March 1996
Resolved 18 May 2002
Resolution: MISLE Maintenance - Resolved all open deficiencies issued prior to 6/1/1997 where activity was closed and deficiency due date was past
Electrical
Issued 25 February 1991
Resolved
PLACE BATTERIES IN LEAD LINED BOX OR IN PLASTIC CONTAINERS.
Condition: Unknown
Due 25 February 1991
Resolved 25 February 1991
Unknown
Issued 25 February 1991
Resolved
INSTALL DRIP PANS ON RACOR FUEL FILTERS.
Condition: Unknown
Due 25 February 1991
Resolved 25 February 1991
Unknown
Issued 25 February 1991
Resolved
REMOVE DIESEL FUEL FROM CONTANMENT IN ENGINE ROOM.
Condition: Unknown
Due 25 February 1991
Resolved 25 February 1991
Construction/Loadline
Issued 25 February 1991
Resolved
PAINT LOAD LINE ON SIDE OF VESSEL.
Condition: Unknown
Due 25 February 1991
Resolved 25 February 1991
Unknown
Issued 25 February 1991
Resolved
INSOLATE EXHUAST ON DIESEL ENGINES.
Condition: Unknown
Due 25 February 1991
Resolved 25 February 1991
Construction/Loadline
Issued 14 July 1990
Resolved
RENEW UPPER 4 LADDER RUNGS ON THE #4 PORT VOID OUTBOARD MANHOLE LADDER.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
FRESHEN HULL MARKINGS, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#2 PORT VOID - RENEW OUTBOARD SIDE SHELL LOGITUDINALS #1 AND #2 UP FROM THE UPPER CHINE FROM FWD WTB (FRAME #19) TO APPROX 1100 MM AFT, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 PORT VOID - RENEW OUTBOARD SIDE SHELL LOGITUDINALS #1 AND #2 UP FROM UPPER CHINE FROM AFT WTB (FRAME #19) TO APPROX 1800 MM FWD. PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
RENEW MANHOLE GASKETS AS REQUIRED PRIOR TO VESSEL MOVEMENT - DEPARTURE SHINKASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
RENEW THE UPPER LADDER FITTINGS FOR THE FOLLOWING OUTBOARD MANHOLES: STBD AFT RAKE, #4 STBD VOID, #3 STBD VOID AND #4 PORT VOID (3, 4 & 4 ALL OUTBOARD).
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 STBD VOID AND #2 STBD VOID, COMMON BULKHEAD (TRANSVERSE FRAME #19) - INSERT 400 MM FROM SIDE SHELL TO INBOARD FROM BETWEEN THE UPPER CHINE AND FIRST LONGITUDINAL TO BETWEEN THE 3RD AND 4TH LOGITUDINAL UP FROM UPPER CHINE, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 STBD VOID AND #2 VOID - RENEW 1ST, 2ND AND 3RD LOGITUDINAL UP FROM UPPERCHINE 1 METER FWD AND 1 METER AFT OF BULKHEAD (FRAME #19), PRIOR TO DEPARTURE OF KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 PORT VOID AND #2 PORT VOID; COMMON BULKHEAD (TRANSVERSE FRAME #19) - INSERT 300 MM FROM SIDE SHELL INBOARD FROM BETWEEN 2ND AND 3RD LOGITUDINALSUP FROM UPPER CHINE TO BETWEEN 2ND AND 3RD LONGITUDINALS UP FROM UPPER CHINE TO BETWEEN UPPER AND LOWER CHINE, PRIOR TO DEPARTURE FROM KASADO YARD
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#2 PORT VOID - RENEW FRAME #17 AND #18 OUTBOARD FROM BILGE (CHINE) BRACKET TO BETWEEN THE 2ND AND 3RD LONGITUDINAL UP FROM THE UPPER CHINE, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 PORT VOID - RENEW FRAME #20 OUTBOARD (INCLUDING THE BILGE (CHINE) BRACKET) TO BETWEEN THE 3RD AND 4TH LONGITUDINAL UP FROM THE UPPER CHINE, PRIOR TO DEPARTURE KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 PORT VOID - RENEW FRAME #21 AND #22 OUTBOARD SIDE SHELL FROM THE UNDER- DECK TRANSVERSE FRAME TO BETWEEN THE 1ST AND 2ND LOGITUDINAL DOWN FROM DECKAND THE TRANSVERSE UNDERDECK FROM SIDE SHELL TO BETWEEN THE 1ST AND 2ND INBOARD UNDERDECK LOGITUDINAL PRIOR TO DEPARTURE KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 PORT VOID - RENEW FRAME #23 AND #24 FROM APPROX 75 MM BELOW 2ND LONGITUDINAL DOWN FROM DECK TO APPROX 75 MM ABOVE THE 1ST LOGITUDINAL ABOVETHE UPPER CHINE, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 PORT VOID AND #2 PORT VOID - RENEW HULL PLATE FROM UPPER CHINE ROLL TO BETWEEN THE 2ND AND 3RD LOGITUDINAL UP FROM THE UPPER CHINE AND 1000 MM AFTOF WT BULKHEAD (FRAME #19) AND 1700 MM FWD OF WTB (FRAME #19, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
RENEW THE FOLLOWING BOLLANDS IN ACCORDANCE WITH ABS APPROVED PLANS: PORT AFT BOLLARD AND CENTER STBD, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
REPAIR THE FOLLOWING BOLLARDS IN ACCORDANCE WITH ABS APPROVED PLANS: STBD AFT, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Electrical
Issued 14 July 1990
Resolved
MAKE OPERABLE IN ACCORDANCE WITH 46 CFR SUB "J", DIESEL GENERATOR IN FORECASTLE OR REMOVE. PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
RENEW MANHOLE COMBING LIP AND COVER FOR STBD AFT RAKE AND #1 PORT VOID OUT-BOARD, PRIOR TO DEPARTURE FROM KASAKO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
CROP AND INSERT 12" X 12" AREA ON MAIN DECK IN WAY OF #2 PORT VOID, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Documentation
Issued 14 July 1990
Resolved
PROVIDE PHOTOCOPY OF VESSEL ABS ISSUED ANNUAL LOADLINE ENDORSEMENT.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Documentation
Issued 14 July 1990
Resolved
PROVIDE PHOTOCOPY OF ABS DRYDOCK REPORT - CURRENT-.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Navigation
Issued 14 July 1990
Resolved
PROVIDE AND MOUNT, WITH 36" FLAT BLACK SCREEN, CG APPROVED PORT AND STBD NAVIGATION LIGHTS FOR VESSEL 188 FT, PRIOR TO THE CARRIAGE OF CARGO.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Navigation
Issued 14 July 1990
Resolved
PROVIDE AND MOUNT, STERN LIGHT AND ANCHOR LIGHT WHICH ARE APPROVED BY THE CG FOR A VESSEL 188 FT LONG, PRIOR TO THE CARRIAGE OF CARGO.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Fire Fighting
Issued 14 July 1990
Resolved
PROVIDE FIRE EXTINGUISHER, B.C. TYPE, B-II WITH CURRENT INSPECTION PRIOR TO THE CARRIAGE OF CARGO.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
PROVIDE MEANS OF SOUNDING ALL VOIDS INDEPENDENTLY (10 COMPARTMENTS).
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
PORT AFT RAKE - RENEW UNDERDECK TRANSVERSE FRAME #3 FROM PORT SIDE SHELL TOAPPROX. 6" OUTBOARD OF FIRST VERTICLE STANCHION, PRIOR TO DEPARTURE OF KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
STBD AFT RAKE - RENEW UNDERDECK TRANSVERSE FRAME #3 FROM STBD SIDE SHELL TOAPPROX. 6" OUTBOARD OF FIRST VERTICLE STANCHION, PRIOR TO DEPARTURE OF KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#3 PORT VOID - FWD BULDHEAD (FR #14) OUTBOARD BETWEEN 1ST AND 2ND LONGITUDINAL UP FROM THE UPPER CHINE - LOCATE END OF JACK IN HULL SIDE SHELL TO BULDHEAD WELD, TERMINATE, GOUGE AND REWELD, PRIOR TO DEPARTURE OF KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 STBD VOID - FRAME #21, 22 AND 24 - RENEW FRAME FROM BILGE (CHINE) BRACKET TO BETWEEN THE 2ND AND 3RD LOGITUDINAL UP FROM THE UPPER CHINE, PRIOR TO DEPARTURE OF KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
#1 STBD VOID - FRAME #23 - RENEW SIDE SHELL FRAME FROM 1ST LOGITUDINAL DOWNFROM DECK TO TRANSVERSE UNDERDECK FRAME FROM HULL TO BETWEEN THE 2ND AND 3RD UNDERDECK LOGITUDINAL, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Unknown
Issued 14 July 1990
Resolved
HOSE TEST HULL PLATE INSERT #1 AND #2 PORT VOIDS, DECK PLATE INSERT #2 PORTVOID, #1 AND #2 PORT AND STBD VOID WTB (FRAME #19) OUTBOARD INSERTS AND RENEWED MANHOLES, PRIOR TO DEPARTURE KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
RENEW MANHOLE COVERS FORM #2 PORT VOID AND #1 SUBD VOID, PRIOR TO DEPARTUREFROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
REPAIR COMBING LIP MANHOLE PORT AFT RAKE, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990
Construction/Loadline
Issued 14 July 1990
Resolved
BLANK FLANGE (WITH METALIC PLATE) 3 SEA CHEST VALVES AT FIRST FLANGE OFF SEA CHEST, PRIOR TO DEPARTURE FROM KASADO DOCKYARD.
Condition: Unknown
Due 14 July 1990
Resolved 14 July 1990