Records from 2001 to 2022. Most recent: inspection, 22 July 2022.
Inspection history · 38
22 July 2022
PSC A
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7513639
15 June 2022
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7479144
14 June 2022
Special
Type not classified · Liquefied Gas Carrier National Center of Expertise · Activity 7499361
17 March 2022
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7413443
29 December 2021
Special
Type not classified · Liquefied Gas Carrier National Center of Expertise · Activity 7373847
23 December 2021
COC-GAS Renew · Administrative Inspection · PSC B
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7372056
14 December 2020
Special
Type not classified · Liquefied Gas Carrier National Center of Expertise · Activity 7112697
3 December 2020
Deficiency Check · COC-GAS Annual · Ballast Water Examination · PSC B
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7105718
31 August 2020
Deficiency Check · PSC B
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7046597
11 December 2019
Ballast Water Examination · COC-GAS Renew · ISPS II Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6870810
11 November 2018
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6578810
11 November 2018
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6581269
7 November 2018
Administrative Inspection · COC-GAS Annual · ISPS II Exam · Deficiency Check · Ballast Water Examination
Physical examination · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 6573122
5 October 2017
Ballast Water Examination · ISPS II Exam · COC-GAS Renew
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6281736
13 February 2016
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5814784
13 February 2016
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5814787
10 February 2016
COE-Administrative
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5812582
24 December 2015
COE-Administrative
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5786951
11 November 2015
COC-GAS Renew · ISPS II Exam · Ballast Water Examination
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 5755517
9 November 2015
Type not recorded
No type recorded · Station Port Aransas · USCG Heartland District (CGD-H) · Activity 5761053
9 November 2015
Type not recorded
No type recorded · Station Port Aransas · USCG Heartland District (CGD-H) · Activity 5808334
2 December 2011
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4200411
22 August 2011
ISPS II Exam · COC-GAS Annual · Ballast Water Examination
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 4123506
18 September 2010
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3849373
18 September 2010
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3852297
7 March 2010
Ballast Water Examination · COC-GAS Annual · ISPS II Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3691201
23 June 2008
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3245528
22 June 2008
ISPS II Exam · MARPOL Annex V Examination · COC-GAS Renew · MARPOL Annex I Examination · Ballast Water Examination
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3240473
22 June 2008
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3243946
21 June 2008
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3239792
6 August 2006
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2737160
25 May 2006
COC-GAS Renew · ISPS II Exam
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 2658578
7 August 2003
Certificate of Compliance
Administrative · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1870139
21 January 2003
Security Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1733174
16 January 2003
Security Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1732240
9 January 2003
Certificate of Compliance · Ballast Water Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1728804
30 July 2001
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 292417
30 July 2001
Letter of Compliance (Initial/Renewal)
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1069583
07 - Fire Safety › N/A - No Subsystem › Operation of Fire protection systems
Issued 3 December 2020
Resolved
GAs detection equipment should be so designed that it may readily be tested. PSCO observed the fix gas detection di not read the proper LEL for the sample gas used. The crew tried 3 times with unsatisfactory results.
73SOLAS(04) VII/13.1
IGC Code 13.6.6
Action required: 17 - Rectify deficiencies prior to departure
Resolved 15 December 2020
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 11 December 2019
Resolved
Electrical installations should be such as to minimize the risk of fire and explosion from flammable products [IGC 10.1.2]. Electrical equipment, cables, and wiring should not be installed in hazardous locations unless it conforms with the standards not inferior to those acceptable to the Organization [IGC 10.1.4, refers to IEC 60092:502]. Cables shall enter an explosion protected enclosure only by means of a gland or equivalent device cable of maintaining the integrity of the enclosure [IEC 7.5.1].
Multiple explosion proof electrical installations on deck were full of water and/our corroded from the inside of the fixture. Additionally, cable entrances into explosion proof fixtures missing necessary glands/packing thus exceeding the maximum experimental safe gap of the fixture. All of the identified fixtures are located in hazardous locations (gas-dangerous zones, as defined by IGC 93/1.3.17).
74SOLAS(2014) VII/13.1
93IGC 10.1.2 &10.1.4
IEC 60092:502
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 24 December 2019
Resolved 31 August 2020
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 11 December 2019
Resolved
On ships carrying flammable or toxic products or both, a water-spray system for cooling, fire prevention and crew protection should be installed to cover: exposed cargo tank domes and any exposed parts of cargo tanks, cargo liquid and vapour discharge and loading manifolds, and boundaries of superstructures and deckhouses normally manned, cargo compressor rooms, store rooms containing high risk fore items and cargo control rooms, all facing the cargo area.
Multiple clogged nozzle heads and missing end caps along the entirety of the DWS system causing an approximately 50% degradation of the system and lack of coverage for all locations listed above. Additionally, a hole was found in the DWS piping over the #2 cargo tank top.
74SOLAS(2014) VII/13.1
93IGC 11.3.1
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 24 December 2019
Resolved 31 August 2020
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 11 December 2019
Resolved
Ships in which the carriage of flammable products is intended should be fitted with fixed dry chemical powder type extinguishing systems for the purpose of fighting fire on deck in the cargo area and bow and stern cargo handling areas of applicable [11.4.1]. The system should be capable of delivering powder from at least two hand hose lines or combination monitor/hand hose lines to any part of the above-deck exposed cargo area including above-deck product piping [11.4.2].
PSCOs observed that half of the DCP hose station’s are cracked as the result of dry-rotting.
74SOLAS(2014) VII/13.1
93IGC 11.4
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 24 December 2019
Resolved 31 August 2020
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 11 December 2019
Resolved
Fire doors in main vertical zone bulkheads, galley boundaries and stairway enclosures, other than power-operated watertight doors and those which are normally locked, shall satisfy the following requirements: the doors shall be self-closing; hold back hooks not subject to central control station release are prohibited.
Nearly all self-closing fire doors within the superstructure had inoperable handles and/or faulty self-closing mechanisms. Additionally, four hold-backs were identified.
74SOLAS(2001) II-2/30.4
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 16 December 2019
Resolved 16 December 2019
Resolution: Attending PSCO verified the rectification of this deficiency. All fire door self-closing mechanisims and handles were repaired/replaced.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 11 December 2019
Resolved
An airlock should only be permitted between a gas-dangerous zone on the open weather deck and a gas-safe space [3.6.1]. The doors should be self-closing and without any holding back arrangements [3.6.2].
Stbd side PSA room airlock door not self-closing.
74SOLAS(2014) VII/13.1
93IGC 3.6.1, 3.6.2
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 16 December 2019
Resolved 16 December 2019
Resolution: Slefclosing mechnism was replced. Attending PSCO verified the door is now self-closing.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 7 November 2018
Resolved
Electrical installations should be such as to minimize the risk of fire and explosion from flammable products. Cable wiring for high level and overfill alarms on multiple tanks are fraying and have electrical tape wrapped around the ends. 74 SOLAS (2014 Cons Ed) Ch VII Reg 13.1
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 8 November 2018
Resolution: Received report from DNV-GL attesting that 14 cable connections were replaced with new cable and all others were found in good condition.
from the high level/overfill sensor
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 7 November 2018
Resolved
Pressure relief valves should be set and sealed by a competant authority. Numerous setset of seal tags are painted over. 74 SOLAS (14 Cons Ed) Ch VII Reg 13.1
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 7 December 2018
Resolved 8 November 2018
Resolution: Received report from DNV-GL attesting that overpainted seal tags have been cleaned by crew. Surveyor verified tags with certificate of functional test and found in order.
Deck/Cargo › Cargo Stowage › General
Issued 22 August 2011
Resolved
1099 - Other (alarm-signals) - Gas detection equipment shall be designed so that it can be readily tested. Following operational test of gas detection system, system received several flow failure alarms before system could be properly reset approx 30-40 minutes later. SOLAS(2009Cons)Ch.VII/Reg.13; IGC 13.6.6
Action required: 705 - Other - as specified
Due 21 September 2011
Resolved 2 October 2011
Resolution: Recieved class report attesting the proper operation and calibration of the fixed gas detection system.
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 22 August 2011
Resolved
1720 - Control of discharge of oil - Oil filtering equipment shall be provided with arrangements to ensure that any discharge of oily mixtures is automatically stopped when the effluent content exceeds 15ppm. The pneumatic shut-off valve was inoperable. C/E tried multiple times to repair the valve with no success. OWS shall not be operated. MARPOL Annex I/Reg 14.7
Action required: 705 - Other - as specified
Due 21 September 2011
Resolved 2 October 2011
Resolution: Received class report attesting to the proper operation of the OWS.
Documentation › Manuals/Policy Documentation › Procedures and Arrangements Manual (NLS)
Issued 22 August 2011
Resolved
1911 - P&A Manual - Every ship certified to carry Noxious Liquid Substances shall have on board a manual approved by the administration. Vessel's crew could not provide an approved procedures and arrangements manual. MARPOL Annex II / Reg 14.1
Action required: 705 - Other - as specified
Due 21 September 2011
Resolved 2 October 2011
Resolution: Received class report attesting to the P & A manual physically onboard the vessel.
Navigation › Collision/Grounding Avoidance › Radar
Issued 23 June 2008
Resolved
Vessel's radar was reported as inoperative.
Action required: 17 - Rectify deficiencies prior to departure
Due 25 June 2008
Resolved 23 June 2008
Resolution: Received proper documentation rectifying the deficiency.