Records from 2016 to 2025. Most recent: inspection, 25 September 2025.
Documentation record
Registered dimensions (L × B × D)71.5 ft × 20.0 ft × 9.1 ft
Registered tonnagegross 87 / net 69
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderDAKOTA CREEK INDUSTRIES · ANACORTES WA, UNITED STATES · built 1990
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeShip
Hull configurationMonohull
Hailing portSEATTLE, WA
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 19 November 2025 · expires 30 November 2026
Service, as the file records itOil Recovery
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it87 - Simplified, Gross Ton
69 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 15
25 September 2025
Appeal · COI Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 8215914
16 September 2025
Internal Structural Exam · Cargo Tank Internal · Drydock Exam
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 8228778
3 October 2024
Annual Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 8014130
17 August 2023
Cargo Tank Internal · Internal Structural Exam · Drydock Exam
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 7771574
26 July 2023
Annual Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 7757041
12 October 2022
Annual Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 7579761
5 October 2021
Annual Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 7317372
5 October 2020
Administrative Inspection · COI Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 7064312
22 September 2020
Cargo Tank Internal · Underwater Inspection in lieu of Drydock · Internal Structural Exam
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 7062308
1 October 2019
Annual Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 6825916
8 September 2018
Administrative Inspection · Annual Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 6535775
8 August 2018
Plan Review "T" Boat · Internal Structural Exam · Ballast Water Examination · Drydock Exam · Administrative Inspection · Cargo Tank Internal
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 6495900
11 October 2017
Periodic Inspection · Administrative Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 6281977
30 September 2016
Annual Inspection
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 6021221
5 May 2016
Administrative Inspection
Administrative · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 5870086
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 25 September 2025
Resolved
All controls, safety devices, and other control system equipment must be tested and inspected to verify their proper design, construction, installation, and operation. Auxiliary boiler requires periodic safety test procedures. Submit test procedures IAW 46 CFR 61.35-3 for OCMI approval.
Condition: Invalid
Action required: 50 - Rectify deficiencies w/in 30 days
Due 31 October 2025
Resolved 10 December 2025
Resolution: PSTP for boiler received. All Sat
01 - Certificates & Documentation › 013 - Documents › Shipboard working arrangements
Issued 17 October 2018
Resolved
Vessel is required to submit drawings, sketches, or written specifications describing the details of any proposed alterations to the cognizant OCMI. Vessel does not have approved drawings for new sewage holding tank and electric water heater installations. Vessel must submit plans to MSC by the end of the calendar year.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 December 2018
Resolved 15 February 2019
Resolution: MSC Plan Review Letters E1-1900257 and E2-1904881