Inspection history · 111
23 April 2026
Internal Structural Exam · Vessel Attendance · Periodic Inspection · Administrative Inspection · Hull Examination · Drydock Exam
Physical examination · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 8354417
11 December 2025
Type not recorded
No type recorded · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 8303033
1 November 2025
Administrative Inspection · Deficiency Check
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 8268817
12 August 2025
Administrative Inspection · Damage Survey
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 8207970
12 August 2025
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 8208847
31 January 2025
Annual Inspection
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 8072602
18 November 2024
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 8041748
8 October 2024
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 8015890
29 September 2024
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 8094689
23 September 2024
Deficiency Check
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 8007470
12 September 2024
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 8001096
5 September 2024
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 8040978
26 July 2024
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7967456
19 July 2024
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7961861
29 June 2024
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 7945147
18 June 2024
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7938049
17 June 2024
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 8042944
8 May 2024
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7908430
27 February 2024
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7886150
26 February 2024
Deficiency Check
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 7873003
9 February 2024
Administrative Inspection · Annual Inspection
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 7863070
29 November 2023
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7830974
21 November 2023
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7827936
15 September 2023
Administrative Inspection · ISM Oversight · Deficiency Check · In-Service Inspection · MARPOL Annex IV Survey
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 7791891
6 August 2023
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7768607
26 July 2023
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7752552
19 July 2023
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7746443
20 June 2023
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7718615
9 May 2023
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7791930
10 March 2023
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7653339
16 February 2023
Administrative Inspection · Drydock Exam · Internal Structural Exam · Examination of Repairs · Hull Examination
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 7637544
14 February 2023
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7636345
11 February 2023
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7664296
7 February 2023
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7633676
24 January 2023
COI Inspection
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 7619720
22 January 2023
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7627804
9 January 2023
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7618301
23 December 2022
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7612337
30 November 2022
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7600994
29 November 2022
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7618302
14 October 2022
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7577108
11 October 2022
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7574757
4 October 2022
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7571073
3 October 2022
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7606007
25 September 2022
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 7565653
12 September 2022
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7556717
7 September 2022
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7553260
1 September 2022
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7548432
1 September 2022
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 7554831
30 August 2022
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7604105
29 August 2022
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7566055
18 August 2022
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 7554826
12 August 2022
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 7591819
28 July 2022
Administrative Inspection · Damage Survey
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 7518316
29 April 2022
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7440453
16 January 2022
Administrative Inspection · Deficiency Check
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 7380999
29 November 2021
Annual Inspection
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 7358237
10 September 2021
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 7309226
2 August 2021
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7274801
9 February 2021
Annual Inspection · Internal Structural Exam · Drydock Exam
Physical examination · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 7137751
11 January 2021
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7122415
2 November 2020
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7088222
7 October 2020
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 7072991
14 August 2020
COI Inspection
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 7023048
18 June 2020
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6979836
31 May 2020
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6964897
19 May 2020
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6955693
4 April 2020
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6939295
21 February 2020
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6912844
17 January 2020
Type not recorded
No type recorded · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6934365
16 December 2019
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6874243
18 November 2019
Periodic Inspection · MTSA/ISPS Verification · Ballast Water Examination · Deficiency Check
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6857346
4 November 2019
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6848380
11 October 2019
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6832629
27 September 2019
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6822319
9 September 2019
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6807112
27 August 2019
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6795737
22 August 2019
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6791156
10 August 2019
Administrative Inspection · Deficiency Check
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6782820
13 July 2019
Administrative Inspection · Deficiency Check
Physical examination · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6747751
3 April 2019
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6654763
27 February 2019
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6635582
7 January 2019
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 6606230
30 October 2018
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6570863
18 October 2018
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6563514
24 July 2018
Administrative Inspection · Periodic Inspection
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6457408
6 May 2018
Damage Survey
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6408674
23 April 2018
Damage Survey
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6405405
23 April 2018
Administrative Inspection · Deficiency Check
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6441781
12 April 2018
Deficiency Check
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6405387
28 March 2018
Administrative Inspection · Deficiency Check · Damage Survey
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6381646
27 March 2018
Administrative Inspection · Deficiency Check
Physical examination · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6379193
3 January 2018
Type not recorded
No type recorded · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6339324
19 December 2017
Administrative Inspection · Hull Examination · Deficiency Check · Inclining Experiment
Physical examination · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 6326343
7 November 2017
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6303767
10 July 2017
Annual Inspection · Examination of Repairs
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6143535
9 June 2017
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6177325
20 April 2017
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 6133430
26 January 2017
Administrative Inspection · Deficiency Check
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 6073207
6 December 2016
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 6053700
6 December 2016
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 6055040
1 December 2016
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 6054343
7 October 2016
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 6024516
25 September 2016
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 6018093
30 August 2016
Examination of Repairs
Physical examination · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 5974929
28 August 2016
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 5988376
10 August 2016
Annual Inspection
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 5983472
21 March 2016
Deficiency Check · Administrative Inspection
Physical examination · Activities Far East · USCG Oceania District (CGD-O) · Activity 5837123
17 March 2016
Type not recorded
No type recorded · Activities Far East · USCG Oceania District (CGD-O) · Activity 5857241
7 March 2016
Administrative Inspection
Administrative · Activities Far East · USCG Oceania District (CGD-O) · Activity 5828076
10 February 2016
Administrative Inspection
Administrative · Marine Inspections Unit Singapore · USCG Oceania District (CGD-O) · Activity 5812488
10 - Safety of Navigation › N/A - No Subsystem › Radar
Issued 24 June 2026
Resolved
All mechanically propelled vessels of 1,600 gross tons and over in ocean or coastwise service must be fitted with a marine radar system for surface navigation. Vessel's X-band and S-band radars were inoperable at the time of inspection due to water intrusion into exterior control unit. 46 CFR 96.25-1
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Due 24 June 2026
Resolved 25 June 2026
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 24 June 2026
No resolution recorded
Test procedure documents must be in a step-by-step or checkoff list format. Each test instruction must specify equipment status, apparatus necessary to perform the tests, safety precautions, safety control and alarm setpoints, the procedure to be followed, and the expected test result. Periodic safety test procedure (PSTP) for Main Diesel Engine Jacket Water High Temp Alarm was unable to be performed as per written procedure due to prior modification to engines. 46 CFR 61.40-10
Extended to 24OCT2026.
Condition: Design Flaw
Action required: 50 - Rectify deficiencies w/in 30 days
Due 24 July 2026 — due date passed with no resolution recorded
11 - Life Saving Appliances › N/A - No Subsystem › Rescue boats
Issued 24 June 2026
Resolved
Each inflated rescue boat must be repaired and maintained in accordance with the manufacturer's instructions. Starboard side grab line attachments have started losing adhesion to inflated hull. 46 CFR 199.190(g)(4)
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 24 July 2026
Resolved 25 June 2026
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 24 June 2026
Resolved
The design and arrangement of electric apparatus must afford accessibility to each part as needed to facilitate proper inspection, adjustment, maintenance, or replacement. Stored goods were situated in front of HVAC Feeder Ckt 15-8 P401, preventing access to control unit. 46 CFR 111.01-7
Condition: Improper Installation
Action required: 10 - Deficiency Rectified
Resolved 24 June 2026
02 - Structural Conditions › N/A - No Subsystem › Closing devices/watertight doors
Issued 24 June 2026
Resolved
During and after any survey made by the assigning and issuing authority, those items, fittings, etc., which are found to be in an unsatisfactory condition by the surveyor shall be repaired or renewed in order to place the vessel in a satisfactory condition. Void below engineering office is being used for additional storage, but normal arrangement with temporary lighting and grated cover precluded the required closure of scuttle 2-31-2 to comply with load line requirements. 46 CFR 42.09-45
Condition: Damaged By Earlier Event
Action required: 10 - Deficiency Rectified
Resolved 24 June 2026
02 - Structural Conditions › N/A - No Subsystem › Decks - cracking
Issued 12 August 2025
Resolved
The condition of the ship shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all aspects will remain fit to proceed to sea without danger to the ship or persons on board.
Crack and hole identified in the 74 Tank sounding tube during pressure test. 74SOLAS(2024)I/11a
Action required: 17 - Rectify deficiencies prior to departure
Resolved 18 September 2025
Resolution: USCG and ABS witnessed satisfactory NDT and air tank testign following repairs.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 31 January 2025
Resolved
Non-conducting deck coverings, such as non-conducting mats or gratings, suitable for the specific switchboard voltage must be installed for personnel protection at the front and rear of the switchboard and must extend the entire length of, and be of sufficient width to suit, the operating space. Attending MI's noted that existing matting was not providing adequate protection from the switchboard, nor displayed the type approval for this application. Provide a replacement rated for the maximum voltage output of on board systems that is approved for such applications.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 25 March 2025
Resolved 10 April 2025
Resolution: Non conductive matting has been ordered the PR was provided. ABS Yokohama has issued a 30 day class finding number in order to track this to closure.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › UMS - Ship
Issued 31 January 2025
Resolved
Remote alarms. All ECC alarms required by this part must be extended to the engineer's accommodations. Other than fire or flooding this my be accomplished by summarized visual displays. In order to restore PUMS on board the vessel the following must occur.
1. Provide a watch call alarm station in the officers mess near the galley location. On board staterooms were verified on 24 March 2025, however it was noted that the relocation of the Officers mess where the licensed engineers eat is missing a alarm panel display.
2. Complete a trial period to verify the effectiveness
and the reliability of bilge arrangement trans alteration that was completed in October of 2024.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 25 March 2025
Resolved 10 April 2025
Resolution: Observation period has been completed and the watch call alarm has been relocated to the new Officers mess, ABS Nagata-san has conducted on site testing and was satisfied that it was working correctly.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 8 October 2024
Resolved
During servicing of the steering system it was noted that the port canard was 5 degress difference from the actual rudder position from the bridge rudder angle indicator. ABS Class has issued a finding number and giving the vessel 30 days to correct the issue. The vessel has devleoped a work around procedure and the system is still fully in tact with excpetion to one RAI. No CG 835 was issued as Class is acting on USCG's behalf.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 8 October 2024
Resolution: ABS class is tracking and closing this item. under findings number 1106.0
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 5 March 2024
Resolved
Means shall be provided to control leaks and restrict ignition of combustible materials. MIs noted substantial hydraulic oil leaks for port and starboard anchor windlass HPUs. Leaks shall be cleaned and contained prior to departure. Chief Engineer reported damaged internal O'rings and ship worklist request (SWFL) for the parts over 3 months ago after MIs noted the leaks. SWFL to be submitted to local OCMI and expedited order by company for HPUs to be serviced within 30 days.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 5 April 2024
Resolved 5 April 2024
01 - Certificates & Documentation › 012 - Crew Certificates › Certificates for master and officers
Issued 5 March 2024
Resolved
STCW engineering officer endorsements are required due to vessel's tonnage (>200GT) and route (Oceans Unlimited). 2AE did not have STCW Officer In Charge Engineering Watch (OICEW) endorsement on MMC. Mariner to submit STCW OICEW endorsement application to USCG NMC within 14 days. Vessel is a gov't vsl & exempt from PSC.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 10 March 2024
Resolution: Application submitted to NMC and marininer meets STCW OICEW requirements.
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 5 March 2024
Resolved
Penetrations of fire rated boundaries shall be kept in good order and maintained to meet appropriate structural fire protection rating. MIs noted improper cabling penetration in the following areas:
1. Improper multi cable transit (MCT) in way of MG Set #1 controls - mixed approval types in a single penetration
2. Improper MCT rocksblock installation in way of AMR forward bulkhead - blocks need to be rebuilt for satisfactory cable size
Satisfactory repairs and verification due w/in 30 days.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 5 April 2024
Resolved 8 March 2024
Resolution: Verified repairs w/ local ABS and submitted to OCMI for evidence.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 29 November 2023
Resolved
For vessel having internal combustions engine arranged for air starting, ther are to be two or more air compressors. Vessel Captain reported that start air compressors were not producing the vessels required air presurre. Further investigation and troubleshooting by ships force found thatthe low pressure piston and liner wer badly worn/scored.
46 CFR 62.35-35
ABS SVR 4-2-1
08DEC2023: Modified and extended to 29FEB2024 VRA, ABS verified partial repairs.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 29 February 2024
Resolved 10 March 2024
Resolution: New compressors installed and tested
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 15 September 2023
Resolved
Iaw 46 USC 8104(d) - 3 watch system required with max work time of 8 hours. Chief Engineer and 1AE are working 12+ hours a day and splitting a two watch rotation. 1AE openly stated that he was violating STCW work rest hours but was told by the Captain what to write in the reports to not exceed allowances (NMT 13 hours per day). Both engineers stated there is a huge safety concern with lack of rest and missing 2AE and 3AE for over 6 weeks and ongoing. During investigation, 1AE accidentally blacked out the ship by tripping on-line generator breaker - directly related to fatigue and lack of awareness.
46 CFR 15.1111 (e)
Action required: 30 - Ship detained
Resolved 26 October 2023
Resolution: Resolved via internal/external ISM audit
08 - Alarms › N/A - No Subsystem › Engineers' alarm
Issued 15 September 2023
Resolved
Automation systems must perform assigned tasks continuously for the detection of unsafe conditions and not be interrupted from monitoring. During inspection of bilge alarms by OEM for vital system automation, it was uncovered that the system had been rewired to bypass the alarms and trick the system to not alarm. This was across multiple bilge alarms and noted to be a deliberate modification (unauthorized by crew). Weekly bilge alarm testing required, questionable documentation as unsure of timeline for modifications.
46 CFR 62.25(b)
Action required: 30 - Ship detained
Resolved 24 October 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 15 September 2023
Resolved
Service pumps shall be fitted with remote controls and protected against tampering. Report from 1AE yielded that power controls from ASW motor controller had been modified to remove electrical safety trips (breaker installed backwards to fail closed and consistently energize controls) - deliberate modification to bypass safety. Satisfactory repairs and further investigation required for additional unauthorized system modifications.
46 CFR 58.01-25
Action required: 30 - Ship detained
Resolved 24 October 2023
08 - Alarms › N/A - No Subsystem › Engineers' alarm
Issued 15 September 2023
Resolved
Vital systems that are automatically or remotely controlled must be provided with an effective primary control, and safety control system to ensure adequate and effective operation of the systems. 140+ inhibited alarms, reduced to 40+ by system grooming and engineers but still an active issue (includes ballast system valve actuators and remote controls disabled, FO tank level indicators faulty (manual soundings required, ASW remote pump controls disabled, LO pumps remote controls disabled).
46 CFR 62.25 (a)
Action required: 30 - Ship detained
Resolved 24 October 2023
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 15 September 2023
Resolved
The following fire protection systems shall be kept in good order so as to ensure their required performance if a fire occurs fire detection and fire alarms systems. Attending IO/MI noted that the Fire Detection panned located in the ECC had numerous active inhibited alarms in addition to active faults preventing the system from operating correctly leaving the ship vulnerable to rapid fire growth.
74SOLAS(2014) II-2/14.2.1.1.2
Action required: 30 - Ship detained
Resolved 24 October 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 15 September 2023
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. Starboard ASW motor controller switch has been gutted and removed and is currently being turned on by the knife switch. This alteration was not authorized or approved. Restore to original configuration.
74 SOLAS (2020) I/11(a)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 26 October 2023
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Documentation-ISM
Issued 15 September 2023
Resolved
The company should establish and maintain procedures to control all documents and data which are relevant to the SMS. The onboard maintenance system “SAMMS” has been inoperable for task direction and tacking for the past 9 months. The company has provided a stand alone laptop, which intermittently works and is only available with signal at the pier.
74SOLAS(2020)IX/3.1
ISM Code (2018) 11.1
Action required: 17 - Rectify deficiencies prior to departure
Resolved 26 October 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 15 September 2023
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. Attending IO/MI noted that when entering the starboard ASW pump room there was evident smell of burning electrical components. Further investigation identified that the No.2 ASW pump has a wasted mechanical seal, and the pump is running 10-15 degrees hotter than the adjacent pump verified with a thermal gun. This imminent failure could be further confirmed had the Vibration analysis equipment required
to onboard been utilized to compare base readings to
compare base readings to current conditions.
Replace pump with suitable “In Kind” selection prior to
fire or failure.
74SOLAS(2020)I/11(a)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 15 September 2023
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. ASW system pressure is substandard preventing operation of the full engineering plant. MI’s noted that one of the ASW check valves that had been removed had the stopping flap removed from it. All system valves shall be restored to originally designed components.
74 SOLAS (2020) I/11(a)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 15 September 2023
Resolved
The main steering gear and rudder stock shall be capable of putting the rudder over from 35 degrees on one side to 30 degrees on the other side with the ship at its deepest seagoing draft and running ahead at maximum ahead service speed in not more than 28 seconds. It was disclosed to attending MI that the Steering canards have a delayed response when in FU and NFU modes.
74SOLAS(2020)II-1/29.3.2
Action required: 17 - Rectify deficiencies prior to departure
Resolved 23 September 2023
Resolution: Steering test conducted and sat w/ USCG witness
08 - Alarms › N/A - No Subsystem › UMS - alarms
Issued 15 September 2023
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. Fuel oil tank level indicators are inoperable and manual soundings are being conducted daily. Restore all required TLI’s to fully operational.
74SOLAS(2020)I/11(a)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2023
08 - Alarms › N/A - No Subsystem › UMS - alarms
Issued 15 September 2023
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. Bilge alarms are inoperable or have been modified from original configuration, attending IO/MI’s noted that the bilge alarm located in the MSD compartment was sitting on the deck grate and disconnected and improperly mounted.
74SOLAS(2020)I/11(a)
Action required: 30 - Ship detained
Resolved 24 October 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 15 September 2023
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. Port ASW pump has faulty remote controls impacting vital system automation and local function only. Additional loads on ASW pumps have impacted system availability and increased demands for maintenance.
74SOLAS(2020)I/11(a)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 15 September 2023
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. Motor controlled valves for both the fuel transfer manifold and ballast systems are working intermittently or not at all. Restore all remote operated valves for these system to full operations.
74SOLAS(2020)I/11(a)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 15 September 2023
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. Two of the three onboard chiller units for the air condition system are currently inoperable.
74SOLAS(2020)I/11(a)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 23 September 2023
Resolution: received AC tech report and verified operation
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 15 September 2023
Resolved
The following fire protection systems shall be kept in good order so as to ensure their required performance if a fire occurs structural fire protection including fire resisting divisions, and protection of openings and penetrations in these divisions Self closing fire door leaving the engine room was broken.
74SOLAS(2020)I/11(a)
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2023
Resolution: Extended final repair to 28FEB2024
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 15 September 2023
Resolved
Piping systems shall be examined under working conditions as required by the marine inspector. Bilge system - issues with system piping and suction - crew has been using portable pumps in voids/confined spaces. Conduct satisfactory suction tests w/ MI witness of deep well spaces & bilge collection pockets.
46 CFR 61.15-15
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 October 2023
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Maintenance of the ship and equipment
Issued 15 September 2023
Resolved
The safety management system should provide for specific measures aimed at promoting the reliability of such equipment or systems. The onboard testing for fuel oil dilution and vibration analysis have been inhibited by broken or inoperable testing equipment. Attending MI/IO noted that visage or falling ball lube oil viscosity tests for fuel oil dilution were unable to be complete due to broken test units and additionally the vibration analysis testing tool was also inoperable.
74SOLAS(2020)IX/3.1
ISM CODE 10.3
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 24 October 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 15 September 2023
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. Attending [name withheld] a leaky relief valve on the ships service air receivers.
74SOLAS(2020)I/11(a)
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 23 September 2023
Resolution: verified adjustment of relief valve
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 15 September 2023
Resolved
A nonmetallic expansion joint must be replaced 10 years after it has been placed into service if it is located in a system which penetrates the side of the vessel and both the penetration and the nonmetallic expansion joint are located below the deepest load waterline. Vessel needs to establish a tracking and replacement program for all expansion joints located below the water line.
Attending MI noted numerous nonmetallic piping installations located in the ASW pump rooms in addition to additional machinery spaces.
46 CFR61.15-12 (b)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 3 October 2023
Resolved 24 October 2023
Resolution: Matrix submitted with tracking and install dates
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Company responsibility and authority
Issued 15 September 2023
Resolved
ISM Code requirements were not met onboard and multiple violations observed:
6.2.1 - The company shall ensure that each ship is manned with qualified seafarers iaw national and international requirements. The ship has been without a 2AE and 3AE for over 6 weeks and not in compliance with STCW work rest hours for licensed engineering officers.
7 - Company shall establish procedures, plans and instructions for key shipboard operations concerning the safety of the personnel, ship and protection of the environment. No record book entries or concise instructions from engineering department with logging sewage discarges/transfers to retention barges. No instructions available for transfer procedures or
pollution prevention instructions.
9.1 - The safety management system should include procedures ensuring that non-conformities, accidents, and hazardous situations are reported to the company, investigated, and analyzed with the objective of improving safety and pollution preventions. Ship received reports from the chief engineer o/a 16JUN2023 concerning the potential discharge of raw sewage while at the pier due to failures within the MSD system for treatment. No further report was made to the local OCMI or MSC until 12SEP2023 via whistleblower. Reports were submitted to company DPA but little action were taken for prompt and thorough investigation by operator.
10.1 - The company should establish procedures to ensure that the ship is maintained in conformity with the relevant rules and regulations. Ship had several unauthorized modifications to safety systems and engineering equipment (MSD, Bilge alarms, salt water cooling pumps) that were uncovered by OEMs during technical support and servicing. Technicians were unable to determine length of time that systems were modified and safeties disabled.
10.3 - The company should identify equipment and technical systems the sudden operational failure of which may result in hazardous situations. These measures should include the regular testing of equipment. Several items were noted in direct contrast to this requirement:
1. During inspection of bilge alarms by OEM for vital system automation, it was uncovered that the system had been rewired to bypass the alarms and trick the system to not alarm. This was across multiple bilge alarms and noted to be a deliberate modification (unauthorized by crew). Weekly bilge alarm testing required, questionable documentation as unsure of timeline for modifications.
2. Attending IO/MI noted that the Fire Detection panned located in the ECC had numerous active inhibited alarms in addition to active faults preventing the system from operating correctly leaving the ship vulnerable to rapid fire growth. None of the crew could state how long the alarm had been active or sounding.
12.3 - The company should periodically evaluate the effectiveness of the SMS. Multitude of SMS failures observed onboard w/ little to no internal documentation.
Action required: 30 - Ship detained
Resolved 26 October 2023
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Company responsibility and authority
Issued 15 September 2023
Resolved
Deficiency #21 Continued:
ABS intermediate audit conducted 12/13JUL2023 in Yokohama, JP.
External audit required for further oversight into the following areas:
1. ISM Code (2018) 6 - Manning
2. ISM Code (2018) 7 - Shipboard operations directly related to engineering inspections and SMS required testing for safety systems.
3. ISM Code (2018) 9 - NC, incident investigation, corrective & preventative actions.
4. ISM Code (2018) 10 - Engineering maintenance, monitoring & measurement.
74SOLAS(2020)IX/3.1
ISM Code (2018) 6.2.1
ISM Code (2018) 7
ISM Code (2018) 9.1
ISM Code (2018) 10.1
ISM Code (2018) 10.3
ISM Code (2018) 12.3
Action required: 30 - Ship detained
Resolved 26 October 2023
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 9 January 2023
Resolved
It shall be the duty of the owner, master, or person in charge to see that the vessel's firefighting equipment is at all times ready for use and that all such equipment required is maintained. Vessel Master reported an intermittent fire alarm fault.
46 CFR 95.05-1 (a)
46 CFR 76.27-5 (b)
Action required: 15 - Rectify deficiencies by next port
Resolved 23 January 2023
Resolution: Cleared via servicing report and testing.
10 - Safety of Navigation › N/A - No Subsystem › Speed and distance indicator
Issued 9 January 2023
Resolved
All ships of 300 gross tonnage and upwards... be fitted with speed and distance measuring device, or other means, to indicate speed and distance through water.
Vessel Master reported intermittent failure of the doppler speed log.
1974 SOLAS (2014) Reg. V/2.3.4
Action required: 15 - Rectify deficiencies by next port
Resolved 23 January 2023
Resolution: Cleared via servicing report and system upgrades.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 14 August 2020
Resolved
Exhaust system piping and components shall be independently supported to minimize failure from vibration, shock, expansion and contraction. Found #4 MDG exhaust support broken. 46CFR 58.03-1
ABYC P-1-1.5.6 50c
Action required: 50 - Rectify deficiencies w/in 30 days
Due 14 September 2020
Resolved 9 September 2020
Resolution: Resolved to the satifaction of marine inspector.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 14 August 2020
Resolved
Fire detecting systems must be installed in the locations indicated by Table 76.05-1(a). Found INOP smoke detector in STBD Motor room. 46CFR95.05, 76.05-1
Action required: 50 - Rectify deficiencies w/in 30 days
Due 14 September 2020
Resolved 4 September 2020
Resolution: Received signed statement and picture from CE [name withheld]. Repaired damaged end of line capacitor and detector base wire contact point. All Sat.
11 - Life Saving Appliances › N/A - No Subsystem › Stowage and provision of liferafts
Issued 14 August 2020
Resolved
Liferafts must be arranged for float-free launching. Port/STBD liferaft station strap setup for center raft is dependent of outboard raft hydrostatic release for float-free launching. 46CFR199.130 10c
Action required: 10 - Deficiency Rectified
Resolved 14 August 2020
Resolution: Sat repair.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 14 August 2020
Resolved
The exhaust system shall be gas-tight to the hull interior. Found #4 MDG exhaust piping joint separated and leaking into the space. 46CFR 58.03-1, ABYC P-1-1.5.1 10c
Action required: 10 - Deficiency Rectified
Resolved 14 August 2020
Resolution: Sat repair
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 14 August 2020
Resolved
Bolts and studs must extend completely through the nuts. Loose bolts were found on Port Steering ram attachment. Torque bolts to OEM specifications. 46 CFR 56.25-20
10c
Action required: 10 - Deficiency Rectified
Resolved 14 August 2020
Resolution: Sat repair
11 - Life Saving Appliances › N/A - No Subsystem › Fast Rescue Boats
Issued 14 August 2020
Resolved
Lifesaving appliance must be in working order and ready for immediate use. Found FRB unable to start. Corroded connection lead to fuse failure. 46CFR199.70 10c
Action required: 10 - Deficiency Rectified
Resolved 14 August 2020
Resolution: Sat repair
14 - Pollution Prevention › 141 - MARPOL Annex I › Oil and oily mixtures from machinery spaces
Issued 4 December 2019
Resolved
During operational test of oily water separator (OWS), unit could not produce effluent under 15 ppm. Prove proper operation of OWS prior to use.
Action required: 705 - Other - as specified
Resolved 5 December 2019
Resolution: Corrected.
02 - Structural Conditions › N/A - No Subsystem › Bulkheads - cracking
Issued 4 December 2019
Resolved
Make temporary repairs IAW RO standards, submit repair proposal and effect repairs for cracked bulkhead IWO door frame in space above stbd pump room.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 13 December 2019
Resolution: Cleared by ABS.
10 - Safety of Navigation › N/A - No Subsystem › Rudder angle indicator
Issued 4 December 2019
Resolved
Correct rudder angle helm/actual differential for both steering gear units to alarm within 5 degrees difference.
Action required: 705 - Other - as specified
Due 15 March 2020
Resolved 31 March 2020
Resolution: Corrected.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 4 December 2019
Resolved
Investigate and remove jumpers inside "Emergency shutdown relay panel" inside ECR.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 5 December 2019
Resolution: Cleared.
04 - Emergency Systems › N/A - No Subsystem › Emergency source of power - Emergency generator
Issued 27 August 2019
Resolved
here the emergency source of electrical power is an accumulator battery, it shall be capable of carrying the emergency electrical load without recharging while maintaining the voltage of the battery throughout the discharge period within 12% above or below the nominal voltage. Primary source of EDG starting, accumulator batteries are inoperable and EDG cannot start. Replace/repair primary source of EDG starting source prior to departure of current port.
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 30 August 2019
Resolution: Received proof that EDG batteries were properly replaced and tested. Cleared 835
11 - Life Saving Appliances › N/A - No Subsystem › Fast Rescue Boats
Issued 18 October 2018
Resolved
Make permanant repairs to the fast respinse boat ignition swith.
Due 18 November 2018
Resolved 20 November 2018
Resolution: Received satisfactory report from ABS stating that the fast rescue boat ignition switch was replaced and functionin properly.
11 - Life Saving Appliances › N/A - No Subsystem › Fast Rescue Boats
Issued 23 April 2018
Resolved
Fast rescue boat (FRB) propulsion shaft bearing failed, limiting the top speed of the FRB. Repair or replace thrust bearing.
Action required: 705 - Other - as specified
Due 8 August 2018
Resolved 31 July 2018
Resolution: Cleared by ABS.
Construction/Loadline › Structures › Transverse Bulkhead
Issued 28 March 2018
Resolved
Crack was discovered on a longitudinal weld seam on bulkhead 166, lower inboard longitudinal, forward of the port steering gear room. Make permanent repairs IAW ABS steel repair procedures to the satisfaction of the attending USCG Marine Inspector or ABS Marine Surveyor.
Action required: 705 - Other - as specified
Due 11 April 2018
Resolved 6 April 2018
Resolution: Corrected by ABS.
Lifesaving › Rescue Boat › Embarkation/Disembarkation Capabilities
Issued 7 November 2017
Resolved
Rescue boat davit hydraulic ram leaks excessively. Replace or make permanent repairs IAW manufacturers recommended repair procedures to the satisfaction of the attending USCG Marine Inspector.
Action required: 705 - Other - as specified
Due 31 December 2017
Resolved 12 February 2018
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 11 July 2017
Resolved
Replace running lights showing faults on the navigation panel.
Action required: 705 - Other - as specified
Due 11 July 2017
Resolved 11 July 2017
Resolution: Corrected.
Navigation › Piloting/Steering › Steering Magnetic Compass
Issued 11 July 2017
Resolved
Stbd rudder angle indicator on stbd bridge wing is inop and needs replacement.
Action required: 705 - Other - as specified
Due 31 December 2017
Resolved 12 February 2018
Lifesaving › Inflatable Liferafts › Markings
Issued 11 July 2017
Resolved
Post placards for both new davit launching life raft systems showing launching procedures.
Action required: 705 - Other - as specified
Due 11 August 2017
Resolved 10 August 2017
Resolution: Corrected.
Deck/Cargo › Holds/Tanks › Scuttle
Issued 11 July 2017
Resolved
All weather deck scuttles should open and close freely.
Action required: 705 - Other - as specified
Due 11 August 2017
Resolved 10 August 2017
Resolution: Corrected.
Deck/Cargo › Mooring/Anchoring › Anchor Chain (general)
Issued 11 July 2017
Resolved
Replace wasted pilot ladder shackle.
Action required: 705 - Other - as specified
Due 11 July 2017
Resolved 11 July 2017
Resolution: Corrected.
Electrical › Electric Generation Source (service) › Switch
Issued 11 July 2017
Resolved
Paint locker exterior light switch need to be replaced.
Action required: 705 - Other - as specified
Due 11 August 2017
Resolved 10 August 2017
Resolution: Corrected.
Navigation › Piloting/Steering › Gryo Compass Repeater
Issued 11 July 2017
Resolved
Port bridge repeater reads different from main heading inside pilothouse.
Action required: 705 - Other - as specified
Due 30 December 2017
Resolved 12 February 2018
Fire Fighting › Fixed CO2 Fire Extinguishing System › Operating Instructions
Issued 11 July 2017
Resolved
Stencil new Halon/CO2 release pull station for HPU/Array room located on fantail.
Action required: 705 - Other - as specified
Due 11 July 2017
Resolved 11 July 2017
Resolution: Corrected.
Construction/Loadline › Structures › Ventilators
Issued 11 July 2017
Resolved
Replace missing wingnuts on weatherdeck for several ventilation closures.
Action required: 705 - Other - as specified
Due 30 December 2017
Resolved 12 February 2018
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 11 July 2017
Resolved
Conduct operational test of OWS in port pump room (tank was empty).
Action required: 705 - Other - as specified
Due 30 November 2017
Resolved 12 February 2018
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 11 July 2017
Resolved
Conduct operational test of OWS in stbd pump room (solenoid valve on order).
Action required: 705 - Other - as specified
Due 30 November 2017
Resolved 12 February 2018
Lifesaving › Inflatable Liferafts › Painter
Issued 11 July 2017
Resolved
Ensure all life raft painter lines are secured to the weak links.
Action required: 17 - Rectify deficiencies prior to departure
Due 11 July 2017
Resolved 11 July 2017
Resolution: Corrected.
Electrical › Electric Generation Source (service) › Metallic Enclosure/Frame
Issued 11 July 2017
Resolved
Ensure stuffing tubes are replaced for steering oumps in both steering rooms.
Action required: 705 - Other - as specified
Due 11 July 2017
Resolved 11 July 2017
Resolution: Corrected.
Lifesaving › Launching Appliances › Davit
Issued 26 January 2017
Resolved
New installation of davit-launch liferafts requires an inspection of lifesaving arrangements for certification that includes proper condition and operation of survival craft launching appliances. Complete 10 percent overload test in the presence of ABS or USCG.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 6 February 2017
Resolution: Witnessed by ABS.
Lifesaving › Launching Appliances › Release Mechanism
Issued 26 January 2017
Resolved
New installation of davit-launch liferafts requires an on-load release hook test. Complete required tests in the presence of ABS or USCG. Towing strain test required by LSA Part 2, Regulation 6.2.7 can be delayed until a test liferaft is made available.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 21 February 2017
Resolution: Completed and attested by ABS
Operations/Management › Drills/Instruction › Launching/Recovery of Survival Craft
Issued 26 January 2017
Resolved
New installation of davit-launch liferafts requires an inspection of lifesaving arrangements for certification that includes proper condition and operation of survival craft launching appliances. Complete abandonship drill, launching a davit-launch raft of comparable size and capacity in the presence of USCG.
Action required: 705 - Other - as specified
Due 15 September 2017
Resolved 12 February 2018
Construction/Loadline › Structures › Superstructure
Issued 26 January 2017
Resolved
While onboard, discovered four locations on upper deck, aft of the engineroom casing stack space that showed signs of buckling, temporary repairs, and doublers installed to cover cracks in the superstructure. Make proper permanent repairs to the satisfaction of the attending USCG inspector.
Action required: 705 - Other - as specified
Due 31 December 2017
Resolved 12 February 2018
Lifesaving › Launching Appliances › Davit
Issued 26 January 2017
Resolved
New installation of davit-launch liferafts installation and steel structure modification requires approved plans be submitted to ABS and USCG. Provide approved plans to the attending marine inspector.
Action required: 705 - Other - as specified
Due 26 March 2017
Resolved 12 February 2018
Lifesaving › Launching Appliances › Davit
Issued 26 January 2017
Resolved
New installation davit-launch launching appliances must be Coast Guard approved. Provide Coast Guard Approval Certificate for the launching appliances to the attending marine inspector.
Action required: 705 - Other - as specified
Due 26 February 2017
Resolved 6 February 2017
Resolution: Corrected.
Lifesaving › Launching Appliances › Davit
Issued 26 January 2017
Resolved
Towing strain test required by LSA Part 2, Regulation 6.2.7 can be delayed until a test liferaft is made available.
Action required: 705 - Other - as specified
Due 12 April 2018
Resolved 12 April 2018
Resolution: Corrected by ABS.
Electrical › Electric Generation Source (service) › Switch
Issued 6 December 2016
Resolved
EDG tripped off-line during a 2-hour load test. Must be repaired to the satisfaction of Class and USCG prior to departure. SOLAS 2004 Cons. II-I/44.2
Action required: 17 - Rectify deficiencies prior to departure
Resolved 10 December 2016
Resolution: Cleared to the satisfaction of Class and USCG.
Construction/Loadline › Structures › Longitudinal Bulkhead
Issued 12 September 2016
Resolved
Provide repair proposal for existing cracks located at Frame 90, starboard side entrance to Pump Room.
Action required: 705 - Other - as specified
Resolved 16 September 2016
Resolution: Reviewed and Corrected.
Construction/Loadline › Structures › Deck Plating
Issued 12 September 2016
Resolved
Provide repair proposal for existing crack located on the deck on the 01 level, Frame 74.
Action required: 705 - Other - as specified
Resolved 16 September 2016
Resolution: ABS reviewed and approved repair.
Communications › Audible Communications › Horn/Whistle
Issued 12 September 2016
Resolved
Make proper repairs to the ships horn. Ensure temporary horn is readily accessible at all times.
Action required: 705 - Other - as specified
Due 12 October 2016
Resolved 20 September 2016
Resolution: ABS verified corrected.
Engineering › Compressed Air System (control) › Fitting
Issued 12 September 2016
Resolved
Make repairs to leaking ship service air reducer to control air system IWO cracked housing.
Action required: 705 - Other - as specified
Due 12 September 2016
Resolved 12 September 2016
Resolution: Air reducer was replaced and leak stopped.
Documentation › Markings/Placards › Lifejacket Placard
Issued 12 September 2016
Resolved
Update requirements for all personnel identified on the abandon ship muster checklist.
Action required: 705 - Other - as specified
Due 12 September 2016
Resolved 12 September 2016
Resolution: Updates were made for the checklist.
Documentation › Markings/Placards › Lifejacket Placard
Issued 12 September 2016
Resolved
Post life-raft launching instructions in the immediate vicinity of the abandon ship muster area.
Action required: 705 - Other - as specified
Due 12 September 2016
Resolved 12 September 2016
Resolution: Placard was posted.
Lifesaving › Launching Appliances › Winch
Issued 12 September 2016
Resolved
Make permanent repairs to the rescue boat winch control system at the operating station.
Action required: 705 - Other - as specified
Due 12 October 2016
Resolved 23 September 2016
Resolution: Corrected by ABS
Pollution Prevention/Response › Prevention Equipment › Marine Sanitation Device, Type II
Issued 12 September 2016
Resolved
Make permanent repairs to the Marine Santitation Device (MSD).
Action required: 705 - Other - as specified
Due 12 September 2016
Resolved 8 December 2016
Resolution: Cleared by ABS
Accommodation/Occupational Safety › Potable Water System › General
Issued 12 September 2016
Resolved
Make permanent repairs to the potable water pipe located in void space 4-124-1. Damaged from earlier event due to a marine casualty.
Action required: 705 - Other - as specified
Due 12 October 2016
Resolved 23 September 2016
Resolution: Corrected by ABS
Pollution Prevention/Response › Prevention Equipment › Oily Residue (sludge/slop) Tank
Issued 12 September 2016
Resolved
Found two oily water holding tanks on the IOPP SOVC that may not be identified in the proper section. ABS to determine if tanks are either required equioment for controlling oil discharge from machinery spaces or are a means of retention and disposal of oil residues.
Action required: 705 - Other - as specified
Due 12 October 2016
Resolved 23 September 2016
Resolution: Corrected by ABS
Documentation › Markings/Placards › Warning Signs
Issued 12 September 2016
Resolved
Properly label "General Alarm - go to your station" at General Alarm located on the fantail.
Action required: 705 - Other - as specified
Due 12 October 2016
Resolved 23 September 2016
Resolution: Corrected by ABS
Engineering › Diesel Engine (auxiliary) › Injector (fuel injection)
Issued 12 September 2016
Resolved
Make permanent repairs to the fuel leak located on #4 SSDG at the fuel-oil return valve.
Action required: 705 - Other - as specified
Due 12 September 2016
Resolved 12 September 2016
Resolution: Corrected.
Lifesaving › Launching Appliances › Release Mechanism
Issued 12 September 2016
Resolved
Make proper repairs to the lifebuoy quick release arrangement located on the port side bridge wing.
Action required: 705 - Other - as specified
Due 12 September 2016
Resolved 12 September 2016
Resolution: Corrected.
Electrical › Electric Generation Source (emergency) › Generator
Issued 30 August 2016
Resolved
EDG failed to start due to faulty start batteries.
Action required: 17 - Rectify deficiencies prior to departure
Due 30 August 2016
Resolved 6 September 2016
Resolution: Recieved notification from ABS surveyor that batteries have been replaced and EDG tested satisfactory.
Communications › Audible Communications › Horn/Whistle
Issued 21 March 2016
Resolved
Vessel reports ships whistle is inoperable. Vessel shall repair or replace ships whistle and provide report to FEACT prior to departure from next port of call. To the Satisfaction of Coast Guard Activities Far East.
Action required: 17 - Rectify deficiencies prior to departure
Due 28 March 2016
Resolved 28 March 2016
Resolution: Spare parts received and installed by Ship's Force. System tested SAT in all modes.
Navigation › Collision/Grounding Avoidance › Radar
Issued 21 March 2016
Resolved
Vessels S-band (3GHz) is inoperable. Vessel shall repair or replace vessels S-band radar prior to departure from next port. To the satisfaction of Coast Guard Activities Far East.
Action required: 17 - Rectify deficiencies prior to departure
Due 28 March 2016
Resolved 28 March 2016
Resolution: FOR RADAR: Satisfactory MacKay technician service report was provided and is attached in documents tab.
Construction/Loadline › Structures › Transverse Bulkhead
Issued 7 March 2016
Resolved
1. Several inspection and multiple engineering analyses have identified high stress areas susceptible to structural failure throughout the T-AGOS Class.
Crowley and Military Sealift Command shall consolidate engineering studies and develop systematic approach to permanently repair areas of structural concern. All repair plans shall be submitted for approval to the satisfaction of the OCMI.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 1 June 2016
Resolved 1 June 2016
Resolution: Crowley and Military Sealift Command have consolidated engineering studies and imputed into vessels maintenance tracking system (SAMMS).
Repair plans have been submitted for known cracks. Any additional cracking discovered shall require a repair pla
Construction/Loadline › Structures › Transverse Bulkhead
Issued 7 March 2016
Resolved
2. Develop a structural monitoring plan for all identified areas of high stress/concern. All high stress areas shall be made available for inspection at each CG annual and Class Survey.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 1 June 2016
Resolved 1 June 2016
Resolution: 2. Structural monitoring plan for all identified areas of high stress/concern has been developed. Annual requirement for inspection has been imputed into SAMSS.
All high stress areas shall be made available for inspection at each CG annual and Class
Construction/Loadline › Structures › Transverse Bulkhead
Issued 7 March 2016
Resolved
Temporary repairs shall be made to the satisfaction of ABS and [name withheld] analysis and permanent repairs shall be completed by the next for-credit dry.
Action required: 705 - Other - as specified
Resolved 12 February 2018