Records from 2016 to 2026. Most recent: inspection, 8 July 2026.
Documentation record
Registered dimensions (L × B × D)63.6 ft × 17.5 ft × 8.3 ft
Registered tonnagegross 70 / net 48
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderBLOUNT MARINE CORPORATION · WARREN, RI, UNITED STATES · built 1979
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeUNSPECIFIED
Hull configurationUNSPECIFIED
Hailing portLEWES, DE
Trade endorsementsCoastwise, oil-spill response
DocumentationValid · issued 12 January 2026 · expires 28 February 2027
Service, as the file records itOil Recovery
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it70 - Regulatory (Subpart C or D), Gross Ton
48 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 20
8 July 2026
Internal Structural Exam · Drydock Exam
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 8410577
15 April 2026
Administrative Inspection · COI Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 8325080
16 April 2025
Annual Inspection
Physical examination · Marine Safety Unit Lewes · USCG East District (CGD-E) · Activity 8112780
28 February 2025
Type not recorded
No type recorded · Marine Safety Unit Lewes · USCG East District (CGD-E) · Activity 8092619
14 January 2025
Administrative Inspection
Administrative · Sector Delaware Bay · USCG East District (CGD-E) · Activity 8063385
15 October 2024
Internal Structural Exam · Drydock Exam · In-Service Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 8019358
17 April 2024
Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7896992
6 June 2023
In-Service Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7704683
27 April 2023
Deficiency Check · Administrative Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7676604
12 April 2023
Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7667389
5 July 2022
Administrative Inspection
Administrative · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7524249
6 April 2022
Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7424091
6 April 2021
COI Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7169376
29 June 2020
Annual Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6990800
2 March 2020
Drydock Exam · Internal Structural Exam
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6919048
12 July 2019
Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Lewes · USCG East District (CGD-E) · Activity 6747240
24 July 2018
Examination of Repairs · Administrative Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6490672
14 May 2018
Internal Structural Exam · Annual Inspection · Administrative Inspection · Examination of Repairs · Hull Examination · DAPI Audit
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6407864
19 April 2017
Administrative Inspection · Annual Inspection · DAPI Audit
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6124362
19 April 2016
COI Inspection · DAPI Audit
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 5857300
01 - Certificates & Documentation › 012 - Crew Certificates › Certificates for master and officers
Issued 15 April 2026
Resolved
Each officer employed on any vessel subject to this subchapter must have his or her license or merchant mariner credential onboard and available for examination at all times when the vessel is operating. MI observed that master was unable to produce official MMC during inspection. Provide inspector original MMC to satisfy requirements.
46 CFR 185.402
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 April 2026
Resolved 17 April 2026
Resolution: MI verified original MMC.
11 - Life Saving Appliances › N/A - No Subsystem › Operation of Life Saving Appliances
Issued 15 April 2026
Resolved
Each survival craft must be stowed so that when the vessel sinks the survival craft floats free and, if inflatable, inflates automatically. MI found painter line permanently attached to the vessel restricting the ability of the survival craft to float free. Corrected on the spot.
46 CFR 180.130(a)(2)
Condition: Improper Installation
Action required: 10 - Deficiency Rectified
Due 15 April 2026
Resolved 15 April 2026
Resolution: Crew corrected on the spot to satisfaction of MI.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Covers (hatchway-, portable-, tarpaulins, etc.)
Issued 15 April 2026
Resolved
A hatch cover must be attached to the hatch frame or coaming by hinges, captive chains, or other devices of substantial strength to prevent its loss. MI found line connecting hatch to the vessel disconnected. Corrected on the spot.
46 CFR 179.360(b)(2)
Condition: Improper Installation
Action required: 10 - Deficiency Rectified
Due 15 April 2026
Resolved 15 April 2026
Resolution: Crew corrected on the spot to satisfaction of MI.
04 - Emergency Systems › N/A - No Subsystem › Public address system
Issued 12 April 2023
Resolved
Public address system must be a fixed installation and be audible during normal operating conditions throughout the accommodation spaces and all other spaces normally manned by crew members.
Public address system was inoperable at time of inspection.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 13 May 2023
Resolved 27 April 2023
Resolution: SECTOR DEL BAY RECEIVED DOCUMENTATION OF INSTALLATION AND OPERATIONAL TEST OF NEW PUBLIC ADDRESS SYSTEM ON VESSEL DEL BAY.
04 - Emergency Systems › N/A - No Subsystem › Fire drills
Issued 12 April 2023
Resolved
Crew training shall be logged or otherwise documented for review by the Coast Guard upon request. The training entry shall include date and general description of the training.
Vessel's training log was found to be inadequate and previous training evolutions were not logged.
Condition: Invalid
Action required: 10 - Deficiency Rectified
Due 12 April 2023
Resolved 12 April 2023
Resolution: Conducted drills and training and verified properly logged
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 8 April 2021
Resolved
Pressure vessel safety relief valve must be tested twice in a 5 year period in order to verify correct operation. Provide servicing report of a properly bench tested relief valve or have current installation tested in the presence of an attending Marine Inspector.46 CFR 54.15-10(g).
Condition: Placed in Improper Service
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 May 2021
Resolved 7 May 2021
11 - Life Saving Appliances › N/A - No Subsystem › Inflatable liferafts
Issued 8 April 2021
Resolved
Disposable hydrostatic release unit was not marked with its expiration date. Provide proof that the HRU attached to the inflatable life raft is still valid.46 CFR 185.740(2)(b).
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 May 2021
Resolved 27 April 2021
Resolution: Provided paperwork showing HRU was purchased in March 2021
11 - Life Saving Appliances › N/A - No Subsystem › Distress flares
Issued 8 April 2021
Resolved
Vessels with a limited coast wise endorsement must have 6 red hand flares and 6 orange hand smoke distress signals. Vessel currently has 8 red hand flares. Purchase either 6 hand orange smoke signals or as a substitution, the vessel can purchase 4 more red hand flares.46 CFR 180.68.
Condition: Invalid
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 May 2021
Resolved 7 May 2021
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 8 April 2021
Resolved
Shore tie cable was damaged at the head connection and the threads were worn. Replace connector or entire cable. 46 CFR 183.01-15.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 May 2021
Resolved 7 May 2021
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 8 April 2021
Resolved
Piping penetration from the E/R into the ballast pump room is not gas tight. Fill surrounding area with fire stop in order to maintain gas tight integrity to contain CO2 in the event of a release. 46 CFR 176.810.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 May 2021
Resolved 7 May 2021
05 - Radio Communications › N/A - No Subsystem › VHF radio installation
Issued 29 June 2020
Resolved
VHF on board did not have DSC capability. Ensure vessel VHF installation has MMSI and GPS integrated. 47CFR80.905(a)(1) - 50c
Action required: 50 - Rectify deficiencies w/in 30 days
Due 29 July 2020
Resolved 23 July 2020
Resolution: Vessel submitted proof of VHS being installed with vessel's MMSI number and is receiving GPS information.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 29 June 2020
Resolved
Provide chemical testing crew list with all members enrolled in the program. 46CFR16.203 - 50c
Action required: 50 - Rectify deficiencies w/in 30 days
Due 29 July 2020
Resolved 23 July 2020
Resolution: O/O submited roster of crewmembers enrolled in chemical testing program.
10 - Safety of Navigation › N/A - No Subsystem › Other (navigation)
Issued 29 June 2020
Resolved
Keep record of abandon ship and man overboard drills and training. 46CFR185.520(f) - 10c
Action required: 10 - Deficiency Rectified
Due 29 June 2020
Resolved 29 June 2020
Resolution: Vessel conducted man overboard drill during inspection and logged it in record book.
02 - Structural Conditions › N/A - No Subsystem › Hull - corrosion
Issued 2 March 2020
Resolved
UT pitting identified IWO collection area shaft door tube.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 3 April 2020
Resolved 4 April 2020
Resolution: Received documentation that showed good metal in area identified.
02 - Structural Conditions › N/A - No Subsystem › Hull - corrosion
Issued 2 March 2020
Resolved
Clean up aft collection door shaft tube area where metal scaling was identified
Action required: 50 - Rectify deficiencies w/in 30 days
Due 3 April 2020
Resolved 4 April 2020
Resolution: Area was cleaned and verified good metal.
02 - Structural Conditions › N/A - No Subsystem › Hull damage impairing seaworthiness
Issued 24 July 2018
Resolved
Submit repair proposal for vessel damage incurred on 24 July 2018 to be approved by the OCMI prior to making repairs.
Action required: 60 - Rectify deficiencies prior to movement
Resolved 14 September 2018
Resolution: All repairs identified on the repair proposal are complete.
Fire Fighting › Fixed CO2 Fire Extinguishing System › Operating Controls
Issued 14 May 2018
Resolved
CO2 System time delay bottles are not equipped with manual over ride valves.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 14 June 2018
Resolved 13 July 2018
Resolution: Verified installation of manual over ride valves at the time delay bottles.
Fire Fighting › Fixed CO2 Fire Extinguishing System › Piping
Issued 14 May 2018
Resolved
Repair identified union leaks on CO2 system piping.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 14 June 2018
Resolved 14 June 2018
Resolution: Areas where leaks were identified were tightened by crew.
Documentation › Logs/Records › Logbook/Record (unofficial)
Issued 14 May 2018
Resolved
Man overboard and abandon ship drills to be conducted and logged.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 14 June 2018
Resolved 14 June 2018
Resolution: Crew conducted and logged MOB and abandon ship drills while transiting to their drydock location.
Engineering › Fuel Oil Service System › Piping
Issued 14 May 2018
Resolved
Repair fuel and hydraulic piping leaks in engine room.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 14 June 2018
Resolved 14 June 2018
Resolution: Areas where leaks were identified were tightened by crew.