COQUI II is a 1994 passenger vessel (inspected). The Coast Guard has recorded 61 inspections since 1994, most recently in April 2026, along with 145 deficiencies and 3 operational controls.
Records from 1994 to 2026. Most recent: inspection, 7 April 2026.
- Built
- 1994
- Last inspected
- 7 April 2026
- Documentation
- Valid · documentation file of 10 September 2026
- Deficiencies
- 145 recorded · 0 without a recorded resolution
- Controls
- None recorded without a removal date
Identity
1021050
WDC7132
398541
Flag
UNITED STATES
367066670, 368369370
Maury page id
psix-398541
Inspections, by type
…with no type recorded5
Years with a record
25 calendar years (1994–2026)
The 61 inspections in the strip above, split by the kind of activity the US
Coast Guard recorded. Years with a record are calendar years in which a record exists, not
years in service. What Maury does not do.
Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 1977.
Documentation record
Registered dimensions (L × B × D)42.3 ft × 12.5 ft × 6.7 ft
Registered tonnagegross 23 / net 18
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderREX-MEYER YACHTS INC · SANFORD, FL, UNITED STATES · built 1994
Hull materialFRP (Fiberglass)
PropulsionJet Drive
Hull shapeShip
Hull configurationMonohull
Hailing portST THOMAS, VI
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 16 January 2026 · expires 31 December 2026
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it23 - Simplified, Gross Ton
18 - Simplified, Net Ton
18 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Radio station licence
WDC7132MMSI 367066670 · active · compulsorily equipped · granted 26 June 2025, expires 13 September 2035
WDP6091MMSI 368369370 · active · voluntarily equipped · granted 23 May 2024, expires 23 May 2034
WDA5461MMSI 366820350 · expired · voluntarily equipped · granted 24 July 2001, cancelled 24 September 2011
WCW9178MMSI not assigned · expired · compulsorily equipped · granted 25 October 1996, cancelled 30 December 2006 · licensed under a name not among this hull’s recorded names (not shown)
FCC Universal Licensing System ship-station file of 6 September 2026, matched to this hull on its
US Official Number. Status and dates are the file’s own. The licensee is not read from the file and is not shown.
A lapsed licence’s MMSI is still the number the vessel transmitted under while it was valid.
Inspection history · 61
7 April 2026
Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 8346843
21 April 2025
COI Inspection · DAPI Audit · Administrative Inspection
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 8116346
25 November 2024
Internal Structural Exam · Administrative Inspection · Drydock Exam
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 8047213
16 January 2024
DAPI Audit · Annual Inspection
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 7863445
12 January 2023
COI Inspection · Administrative Inspection · DAPI Audit
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 7604781
28 November 2022
Drydock Exam · Internal Structural Exam
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 7604180
5 November 2021
Annual Inspection
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 7344463
11 January 2021
Administrative Inspection · Annual Inspection · Drydock Exam · DAPI Audit
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 7132106
20 December 2019
Administrative Inspection · DAPI Audit · Annual Inspection
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 6880449
31 January 2019
In-Service Inspection
Physical examination · Marine Safety Unit Saint Thomas · USCG Southeast District (CGD-SE) · Activity 6616803
4 December 2018
Deficiency Check · Annual Inspection
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6592023
13 November 2018
Deficiency Check · Administrative Inspection · Drydock Exam
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6579366
14 November 2017
In-Service Inspection · COI Inspection
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6306935
16 October 2017
Damage Survey · Deficiency Check · Administrative Inspection
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6288687
27 March 2017
Deficiency Check · Annual Inspection
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6112380
10 March 2017
Administrative Inspection
Administrative · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6102523
7 February 2017
Deficiency Check
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6084036
23 November 2016
Deficiency Check · Hull Examination
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6046468
22 January 2016
Annual Inspection · Deficiency Check
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 5801872
14 July 2009
Deficiency Check · COI Inspection
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 3534018
14 July 2009
Type not recorded
No type recorded · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 3536127
29 September 2008
Annual Inspection · Deficiency Check
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 3330795
30 June 2008
Hull Examination · Internal Structural Exam
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 3253509
5 July 2006
Annual Inspection · Deficiency Check
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 2703444
18 January 2006
In-Service Inspection
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 2569216
21 November 2005
Plan Review "T" Boat · Construction Oversight
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 2538611
7 October 2005
Deficiency Check
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 2512107
7 September 2005
Annual Inspection
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 2486406
28 September 2004
Deficiency Check
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 2206951
23 June 2004
Hull Examination · Deficiency Check · COI Inspection
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 2108917
16 July 2003
Hull Examination
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1860626
29 October 2002
COI Inspection
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1702259
12 December 2001
Re-Inspection
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1481375
7 September 2001
Deficiency Check
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1073470
23 July 2001
Hull Examination
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1406988
14 June 2001
Type not recorded
No type recorded · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1397666
14 June 2001
Type not recorded
No type recorded · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1399688
12 October 2000
Re-Inspection
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1466174
27 October 1999
COI Inspection
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1463519
29 September 1999
Plan Review "T" Boat
Administrative · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 794484
20 August 1999
Type not recorded
No type recorded · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 731988
12 August 1999
Hull Examination
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1442882
2 May 1999
Type not recorded
No type recorded · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 97026
1 April 1999
Administrative
Administrative · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1120016
17 November 1998
Administrative
Administrative · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 806840
27 May 1998
Administrative
Administrative · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 792058
20 April 1998
Re-Inspection
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 802899
13 November 1997
Hull Examination
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 782824
6 May 1997
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1098866
22 April 1997
COI Inspection · MARPOL Annex V Examination
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1099047
13 December 1996
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1091779
10 October 1996
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1151476
22 August 1996
Administrative
Administrative · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1087398
15 May 1996
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1082997
8 May 1996
Re-Inspection
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1083764
13 October 1995
Hull Examination
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 876737
22 August 1995
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 877556
5 June 1995
Deficiency Check
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 874969
18 May 1995
Re-Inspection
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1238975
22 April 1994
Initial Certification
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 857008
9 February 1994
Hull Examination · Initial Construction-Excluding Oversight
Physical examination · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 849359
Deficiency record · 145
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 4 December 2018
Resolved
A vessel must carry one floating waterlight. Vessel's waterlight is non-operational. Vessel is restricted to daylight operations until proper operation of the waterlight can be demonstrated.
07 - Fire Safety › N/A - No Subsystem › Fire-dampers
Issued 4 December 2018
Resolved
Provisions must be made for closing all supply duct cowls or scoops and exhaust duct discharge openings for a space protected by a fixed gas extinguishing system. The port side ventilation in the engine space does not properly close due to wires and packing foam blocking the closure.
09 - Working and Living Conditions › 092 - Working Conditions › Guards - fencing around dangerous machinery parts
Issued 4 December 2018
Resolved
An exposed hazard, such as gears or rotating machinery, must be properly protected by a cover, guard, or rail. The shaft in the steering compartment does not have a guard or cover and poses a hazardous condition in the space.
09 - Working and Living Conditions › 091 - Living Conditions › Medical Equipment
Issued 4 December 2018
Resolved
A vessel must carry either a first-aid kit approved under approval series 160.041 or a kit with equivalent contents and instructions. Vessel is missing the required ammonia inhalants.
11 - Life Saving Appliances › N/A - No Subsystem › On board training and instructions
Issued 4 December 2018
Resolved
Placards containing instructions for the donning and use of the life jackets aboard the vessel must be posted in conspicuous places that are regularly accessible and visible to the crew and passengers. The vessel did not have any life jacket placards posted.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 4 December 2018
Resolved
A vessel of at least 26 feet in length must be provided with individual bilge lines and bilge suctions for each watertight compartment. One of the vessel's manual bilge line is disconnected from itself. Properly secure line or remove system from on board.
11 - Life Saving Appliances › N/A - No Subsystem › Distress flares
Issued 4 December 2018
Resolved
A vessel on a limited coastwise route must carry six hand orange smoke distress signals. Vessel has four distress signals expiring at the end of the month.
Engineering › Feedwater/Condensate Water System › Gauge
Issued 27 March 2017
Resolved
Gauges to indicate engine revolutions per minute (RPM), jacket water discharge temperature, and lubricating oil pressure must be provided for all propulsion engines installed in the vesselAlso noted high water cooling temperature displayed on cooling water temperature gauge, also at steering console. After Master diagnosed, faluty gauge was found to be the source of the high temperature reading.
Lifesaving › Lifebuoys › Buoyant Lifeline
Issued 27 March 2017
Resolved
At least one ring life buoy must be fitted with a lifeline. If more than one ring life buoy is carried, at least one must not have a lifeline attached. Each lifeline on a ring life buoy must:(1) Be buoyant;Vessel did not have 60ft of bouyant lifeline on board for lifebouy. Line that was attached to life bouy did not float.
Operations/Management › Bilge/Bilge System Management › Control of Excess Water
Issued 27 March 2017
Resolved
High bilge alarm visual not working
Engineering › Fuel Oil Service System › Hose
Issued 23 November 2016
Resolved
The flexible fuel hose from the service tank to the fuel filter passes unprotected through the bulkhead. Correct flexible fuel hose penetrating forward engine room bulkhead.
Engineering › Fuel Oil Service System › Gauge
Issued 23 November 2016
Resolved
The installed marine type fuel gauge had been removed and the vessel operator was using a wooden dowel with markings to get sounding through the top of the fuel tank. Provide adequate means to measure fuel level.
Engineering › Bilge Water Management System › Valve
Issued 23 November 2016
Resolved
A plastic through-hull fitting was discovered on the bilge discharge piping in the fuel compartment. Replace plastic through-hull fittings with metallic fittings.
Engineering › Bilge Water Management System › Valve
Issued 23 November 2016
Resolved
There is a ball valve used as the isolation valve installed on the bilge line outside the collision bulkhead. Replace valve on forward collision bulkhead bilge piping with gate valve (screw down valve).
Lifesaving › Rescue Boat › Boarding Ladder
Issued 23 November 2016
Resolved
Multiple cracks were noted on the swim deck ladder and on the underside of the support stanchions. Repair cracked welds on swim deck ladder and on underside of swim deck for welds on stanchion supports.
Stability › Watertight Integrity › General
Issued 23 November 2016
Resolved
The fiberglass deck had multiple cracks next to the engine room cover. Repair / dewater cracks on deck next to engine room cover.
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 23 November 2016
Resolved
There is an exposed belt on the engine with no machinery guard in place. Provide machinery guard.
Documentation › Certificates/Documents › FCC SSL
Issued 26 January 2016
Resolved
PROVIDE CURRENT FCC STATION LICENSE, RESTRUCTED TO 1,000 FT. FROM SHORE.
Construction/Loadline › Penetrations › Valve Flange
Issued 26 January 2016
Resolved
PROPERLY SECURE AFT COMPARTMENT THROUGH-HULL PENETRATION. THERE IS A FITTING CONNECTED WITH A LOOSE HOSE AND PVC VALVE.
Fire Fighting › Fixed Fire Detection System › Annual Inspection
Issued 26 January 2016
Resolved
PROVIDE PROPER OPERATION OF FIXED PRE-ENGINEERED FIRE FIGHTING SYSTEM.
Engineering › Steering Gear System › Linkage
Issued 26 January 2016
Resolved
PROPERLY REPAIR EMERGENCY STEERING TILLER LINKAGE.
Electrical › Electrical Distribution System (service) › Wiring
Issued 26 January 2016
Resolved
SECURE ALL LOOSE/HANGING WIRES ON FUEL-TANK COMPARTMENT.
Operations/Management › Drills/Instruction › Not Conducted
Issued 26 January 2016
Resolved
CONDUCT SATISFACTORY DRILLS AND SEA-TRIALS IN THE PRESENCE OF CG MARINE INSPECTOR.
Construction/Loadline › Hull › Collision Chock
Issued 26 January 2016
Resolved
PROPERLY SECURE/REPAIR ACCESS IN COLLISION BULKHEAD/FWD COMPARTMENT WHERE THERE IS WATER INGRESS.
Engineering › Fuel Oil Service System › Hose
Issued 26 January 2016
Resolved
PROVE FLEXIBLE FUEL HOSE AND ENGINE COMPARTMENT AND FUEL TANK MEETS ASTM D1692 OR REPLACE FELXIBLE FUEL HOSE WITH APPROVED TYPE.
Fire Fighting › Fixed CO2 Fire Extinguishing System › Servicing
Issued 14 July 2009
Resolved
Provide technician's report for properly installed and functioning fireboy system in engine room.
Construction/Loadline › Structures › Deck Plating
Issued 14 July 2009
Resolved
Submit repair proposal for cracked deck between engine compartment and fwd compartment.
Construction/Loadline › Structures › Deck Plating
Issued 14 July 2009
Resolved
Submit repair proposal for cracked deck stbd aft corner.
Construction/Loadline › Structures › Transverse Bulkhead
Issued 14 July 2009
Resolved
Submit repair proposal for ensuring a watertight bulkhead between the engine compartment and the fwd compartment.
Electrical › Electric Supply System (service) › Battery Installation
Issued 14 July 2009
Resolved
Provide top covers for the two battery boxes in the engine compartment.
Electrical › Electrical Distribution System (service) › Panelboard
Issued 14 July 2009
Resolved
Provide covering for electric panel in engine compartment to ensure panel does not get splashed with water.
Construction/Loadline › Structures › End Bulkhead
Issued 14 July 2009
Resolved
Make transom watertight.
Stability › Watertight Integrity › General
Issued 14 July 2009
Resolved
Install check valves for all thru hull fittings.
Lifesaving › Lifejacket/PFD (General) › Condition
Issued 14 July 2009
Resolved
Replace (15) fifteen adult lifejackets.
Lifesaving › Lifejacket/PFD (General) › Retroreflective Material
Issued 14 July 2009
Resolved
Replace retro-reflective tape on (04) four child-size lifejackets.
Lifesaving › Lifejacket/PFD (General) › Retroreflective Material
Issued 14 July 2009
Resolved
Provide adequate retro-reflective tape on all remaining adult lifejackets (07) seven total.
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 14 July 2009
Resolved
Provide properly working and approved self-igniting light for life buoy.
Operations/Management › Vessel Safety Management › Maintenance of Ship/Equipment
Issued 14 July 2009
Resolved
Repair mounting for water tank in fwd compartment.
Operations/Management › Vessel Safety Management › Maintenance of Ship/Equipment
Issued 14 July 2009
Resolved
Provide proper latch on stbd side engine room cover.
Engineering › Freshwater System (jacketwater cooling) › Containment
Issued 14 July 2009
Resolved
Make proposal to re-locate anti-freeze resevoir recovery.
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 14 July 2009
Resolved
Remove excess studs on overhead deck plates.
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 14 July 2009
Resolved
Remove all exposed excess studs on bracketry.
Engineering › Bilge Water Management System › Not Operational
Issued 14 July 2009
Resolved
remove or repaire bilge alarm system in fwd compartment by fuel tank.
Engineering › Steering Gear System › Ram
Issued 14 July 2009
Resolved
Repair hydraulic ram leak in aft compartment.
Operations/Management › Vessel Safety Management › Maintenance of Ship/Equipment
Issued 14 July 2009
Resolved
Repair cracked swim ladder at hinge plate.
Operations/Management › Drug and Alcohol Testing › Testing, Equipment
Issued 14 July 2009
Resolved
Ensure compliance with ability to conduct alcohol testing within two hours, an additional DOT approved sampling kit is required on board.
Fire Fighting › Miscellaneous Items › Insulation (Penetration of Oil/Oil Vapors)
Issued 14 July 2009
Resolved
Repair hanging and ripped insulation inside engine room cover.
Electrical › Electrical Distribution System (service) › Wiring
Issued 14 July 2009
Resolved
Provide metal brackets for hanging wiring in fwd compartment.
Operations/Management › Drills/Instruction › Man Overboard Recovery
Issued 14 July 2009
Resolved
Vessel must conduct MOB drills prior to carrying passengers.
Fire Fighting › Fixed Halon Fire Extinguishing System › Operating Controls
Issued 3 October 2008
Resolved
Repair fixed fire fighting system indicator and main engine reset device at the pilot station. At time of this def check, it was determined that the incorrect indicator was installled. At time of inspection, the visual indicator worked, but the audible was still patched to the engine room bilge pump alarm buzzer. The reset work one time, then failed the second time.
Fire Fighting › Portable CO2 Fire Extinguisher › Number
Issued 29 September 2008
Resolved
Provide a B-II portable fire extinguisher. At time of inspection, a B-I was in place of the required B-II. The B-I needed to be serviced due to frozen discharge handle.
Fire Fighting › Fixed Gas Fire Extinguishing System › Operating Controls
Issued 29 September 2008
Resolved
Repair electric wire that connects to the fixed fire fighting system cylinder head in engine room.
Fire Fighting › Fixed Gas Fire Extinguishing System › Operating Controls
Issued 29 September 2008
Resolved
Repair the fixed fire fighting system indicator at the pilot station. The green light at the indicator was not working at time of the inspection indicating that the system is operational.
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 29 September 2008
Resolved
Repair navigation lights. At time of inspection, the stern white light worked, but the port and starboard lights did not work. Vessel restricted to daytime ops only and not during restricted visibility.
Lifesaving › Buoyant Apparatus › Floating Electric Waterlight
Issued 29 September 2008
Resolved
Repair or replace waterlight to ringbuoy. At time of inspection, the waterlight was working intermitently. Vessel restricted to daytime ops only and not during restricted visibility.
Lifesaving › Lifejacket/PFD (Type I) › Storage
Issued 29 September 2008
Resolved
Provide lifejacket donning placard.
Engineering › Lubricating Oil Service System › Gauge
Issued 29 September 2008
Resolved
Repair oil pressure gauge at the pilot station. At time of inspection, gauge was showing incorrect reading. As soon the power was energized to MDE, the gauge needle jumped all the way to max reading.
Engineering › Diesel Engine (propulsion-direct drive) › Governor
Issued 29 September 2008
Resolved
Repair MDE rpm gauge at the pilot station. Ensure gauge is permanent installed at the console. At time of inspection, the gauge was reading 000 with MDE operating and not fixed to console.
Communications › Radio Communications › VHF Radiotelephone
Issued 29 September 2008
Resolved
Provide FCC marine Radio Operator permit for master.
Accommodation/Occupational Safety › Occupational Safety › Tripping/Falling Hazard
Issued 29 September 2008
Resolved
Make repairs to fly bridge deck. Deck plates are loose presenting a falling hazard to crew members.
Operations/Management › Passenger Operations › Safety Orientation
Issued 5 July 2006
Resolved
Post Emergency Instructions.
Documentation › Logs/Records › Logbook (official)
Issued 5 July 2006
Resolved
Provide a log for drills and lifesaving equipment.
Fire Fighting › Fire Bucket › Quantity
Issued 5 July 2006
Resolved
Provide 2 stenciled fire buckets with lines attached.
Navigation › Piloting/Steering › Marine Charts
Issued 5 July 2006
Resolved
Provide correct chart for Puerto Rico.
Navigation › Collision/Grounding Avoidance › Danger Messages
Issued 5 July 2006
Resolved
Provide operational horn.
Lifesaving › Hand Flares › Quantity
Issued 5 July 2006
Resolved
Provide three (3) missing orange smokes.
Communications › Radio Communications › EPIRB
Issued 5 July 2006
Resolved
Provide EPIRB with new antenna.
Engineering › Steering Gear System › Follow-up Assembly
Issued 5 July 2006
Resolved
Provide emergency steering tiller.
Engineering › Non-conventional Propulsion/Steering › Impeller Seat Ring (jet)
Issued 5 July 2006
Resolved
Correct aft water leak on jet drive in steering room// 06Jul06- System tested underway. Noted leak only when going in reverse and in neutral, but not going forward. No leak noted with vsl moored and system off. Master instructed to monitor space and to test high level alarm and bilge pump prior to carry passengers. New bushing already ordered by owner.
Operations/Management › Drills/Instruction › Fire
Issued 5 July 2006
Resolved
Conduct fire and man overboard drills with CG inspector.
Electrical › Lighting (emergency) › Battery Operated Lantern
Issued 5 July 2006
Resolved
Provide 2 emergency portable lights.
Fire Fighting › Portable Dry Chemical Fire Extinguisher › Service
Issued 7 September 2005
Resolved
Service portable fire extinguisher located at the pilot station.
Accommodation/Occupational Safety › Occupational Safety › Deck Rail
Issued 7 September 2005
Resolved
Repair the starboard side top safety rail.
Documentation › Certificates/Documents › FCC SSL
Issued 7 September 2005
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Documentation › Certificates/Documents › Proof of Consortium Enrollment (DAPI)
Issued 8 July 2004
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Fire Fighting › Fixed Halon Fire Extinguishing System › Quantity of Halon
Issued 8 July 2004
Resolved
Provide 3rd party report for annual servicing of the fixed fire fighting system. Both bottles have proper servicing tags.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 8 July 2004
Resolved
Provide a Cost Guard or equivalent first aid kit.
Accommodation/Occupational Safety › Other Accommodation Spaces › Open Deck Space
Issued 8 July 2004
Resolved
Provide additional safety chains so that no more than 12 inches exist from the main deck to the top rail, aft by dive platform. Rail courses not to exceed 12 inches apart.
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 8 July 2004
Resolved
Provide a 3-foot lanyard with a corrosion resistant clip to water light for the lifebuoy.
Lifesaving › Lifebuoys › Markings (ship name/port)
Issued 8 July 2004
Resolved
Mark lifebuoy with vessel name.
Lifesaving › Lifejacket/PFD (Type I) › Storage
Issued 8 July 2004
Resolved
Separate adult from child lifejackets.
Engineering › Steering Gear System › Valve, Control
Issued 8 July 2004
Resolved
Replace the current "leverage pipe" with a smaller diameter pipe for the emergency steering system handle.
Fire Fighting › Remote Fuel Shutoff › General
Issued 8 July 2004
Resolved
Label the remote fuel shut-off valve with direction of operation.
Fire Fighting › Portable Dry Chemical Fire Extinguisher › Mounting Bracket
Issued 8 July 2004
Resolved
Permanently install the portable fire extinguishers.
Lifesaving › Lifejacket/PFD (General) › Storage
Issued 23 June 2004
Resolved
Storage bags for the adult PFDs are too tight for PFD storage, which makes it very difficult to extract the PFDs. Provide storage bags that allow suitable/quicker extraction, or provide an alternative PFD stowage arrangement as per 46 CFR 180.78.
Construction/Loadline › Hull › Bottom Plating
Issued 16 July 2003
Resolved
Prior to carrying passengers, renew as original the aluminum bottom plate for the jet drive intake foundation. LEGACY COMPONENT DESC: Hull Plating
Construction/Loadline › Hull › Bottom Plating
Issued 16 July 2003
Resolved
Prior to carrying passengers, renew as original the aluminum jet drive mount to the stern. LEGACY COMPONENT DESC: Bracket
Construction/Loadline › Hull › Hull Plating
Issued 16 July 2003
Resolved
Prior to carrying passengers, renew as original all missing and pitted directional / stabilizer fins and properly reseal to hull.
Engineering › Steering Gear System › Fastener
Issued 16 July 2003
Resolved
Prior to carrying passengers, install adequate washer or device for the new steering cable terminus. LEGACY COMPONENT DESC: Linkage
Construction/Loadline › Structures › Deck Plating
Issued 16 July 2003
Resolved
Prior to carrying passengers, reweld all fractures to dive platform base and the dive ladder.
Construction/Loadline › Structures › Superstructure
Issued 16 July 2003
Resolved
Install missing securing bolts to flying bridge supports (six total).
Accommodation/Occupational Safety › Other Accommodation Spaces › Recreation Space
Issued 16 July 2003
Resolved
Prior to carrying passengers, install missing vertical rail to bow sprit. LEGACY COMPONENT DESC: Open Deck Space
Electrical › Electrical Distribution System (service) › Conductor
Issued 16 July 2003
Resolved
Make port and starboard side elecrical cable runs weather tight where wires are currently exposed at flying bridge.
Electrical › Lighting (service) › Lighting Fixture
Issued 16 July 2003
Resolved
Drain water in aft deck light fixture and reseal.
Engineering › Diesel Engine (propulsion/auxiliary-electric) › Injector (fuel injection)
Issued 16 July 2003
Resolved
Install adequate fuel filter and gauge. Provide a steel strainer bowl for fuel filter.
Fire Fighting › Fixed Halon Fire Extinguishing System › Control Valve
Issued 16 July 2003
Resolved
Prior to carrying passengers, properly secure the fixed fire fighting pull cable where cable ends at the cylinder's nozzle. LEGACY COMPONENT DESC: Operating Controls
Engineering › Diesel Engine (propulsion/auxiliary-electric) › Silencer (exhaust)
Issued 16 July 2003
Resolved
Renew the exhaust seal where water leaks are present.
Electrical › Electrical Distribution System (service) › Conductor
Issued 16 July 2003
Resolved
Remove all dead end wires in engine and forward compartments.
Construction/Loadline › Penetrations › Pipe Flange
Issued 16 July 2003
Resolved
Prior to carrying passengers, properly plug unused through-hull fiting for the obsolete sewage line.
Engineering › Diesel Engine (propulsion/auxiliary-electric) › Governor
Issued 16 July 2003
Resolved
Prior to carrying passengers, renew throttle linkage terminus with a metal fiting or clip to replace current plastic tie. LEGACY COMPONENT DESC: Governor
Engineering › Freshwater System (jacketwater cooling) › Valve
Issued 16 July 2003
Resolved
Prior to carrying passengers, free and clean intake valve for the engine cooling water. LEGACY COMPONENT DESC: Valve
Construction/Loadline › Hull › Hull Plating
Issued 16 July 2003
Resolved
Renew extensive cracks in fiber glass knife edges to the engine compartment hatch.
Fire Fighting › Fixed Halon Fire Extinguishing System › Quantity of Halon
Issued 29 October 2002
Resolved
Provide proper fire extinguisher cylinder for fixed fire extinguishing system. replace cylinder from 9.5lbs to a 16lbs as per COI.
Documentation › Certificates/Documents
Issued 29 October 2002
Resolved
Provide evidence that new crew member is enrolled in a drug testing consortium.
Engineering › Steering Gear System › Rudder
Issued 29 October 2002
Resolved
Repair Auxiliary steering system (tiller) and prove proper operation to a Coast Guard Marine Inspector.
Fire Fighting › Portable Dry Chemical Fire Extinguisher › Condition
Issued 29 October 2002
Resolved
Provide service report for fixed fire extinguisher and portable fire extinguishers.
Fire Fighting › Portable Dry Chemical Fire Extinguisher
Issued 12 December 2001
Resolved
Install & provide missing and required portable fire extinguisher ( type B-II).
Fire Fighting › Portable Dry Chemical Fire Extinguisher
Issued 12 December 2001
Resolved
Service all portable fire extinguishers on board. LEGACY COMPONENT DESC: Service
Fire Fighting › Fixed Gas Fire Extinguishing System
Issued 12 December 2001
Resolved
Proof proper operation of vessel fixed fire extinguishing syatem onboard.
Personnel › Certificates/Documents/Licenses
Issued 12 December 2001
Resolved
Vessel to have a Coast Guard licensed Master when carrying seven or more passengers for hire. LEGACY COMPONENT DESC: License, Master
Documentation › Logs/Records
Issued 12 December 2001
Resolved
Vessel to have a Training Log Book on board to log drills conducted by crew. LEGACY COMPONENT DESC: Logbook (official)
Documentation › Certificates/Documents
Issued 12 December 2001
Resolved
Provide Stability Letter for exposed water operation (operations of more than three miles from shore). Vessel has a Limited Coastwise route in its present COI. LEGACY COMPONENT DESC: Stability Letter
Operations/Management › Drills/Instruction
Issued 12 December 2001
Resolved
Crew to demonstrate man overboard drill. LEGACY COMPONENT DESC: Man Overboard Recovery
Construction/Loadline
Issued 23 July 2001
Resolved
Properly cancel existing non-utilized sea valves previously used for MSD unit.
Engineering
Issued 23 July 2001
Resolved
Install missing bracket (hose clamp), on wet exhaust hose.
Documentation
Issued 14 June 2001
Resolved
VESSEL TO PROVIDE CURRENT FCC(COMMUNICATION ACT SAFETY RDIO CERTIFICATE).
Documentation
Issued 14 June 2001
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Navigation
Issued 14 June 2001
Resolved
VESSEL TO REGISTER WITH NOAA, 406 SATELITE EPIRB REGISTRATION
Documentation
Issued 14 June 2001
Resolved
Vessel to provide current FCC Communication Safety Act Radiotelephony Certificate. Vessel not allowed to carry more than six(6) passengers until requirement is met.
Lifesaving
Issued 14 June 2001
Resolved
Vessel to register it's required 406 MHZ EPIRB.
Documentation
Issued 14 June 2001
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Navigation
Issued 12 October 2000
Resolved
Make emergency steering system available for full operation and testing no later than 28 OCT 00.
Fire Fighting
Issued 22 April 1997
Resolved
Perform annual servicing on fixed halon system and portable extinguishers._x001C__x001C_ _x001C_ _x001C_
Electrical
Issued 22 April 1997
Resolved
Provide 2 emergency flashlights.
Lifesaving
Issued 22 April 1997
Resolved
Permanently mount EPIRB to allow float free deployment.
Lifesaving
Issued 22 April 1997
Resolved
Stencil name of vessel on lifefloat and ringbuoy. Affix retro-reflective tape on lifefloat.
Documentation
Issued 22 April 1997
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Lifesaving
Issued 22 April 1997
Resolved
Provide one additional adult PFD. Limited to 21 total persons until completed.
Lifesaving
Issued 22 April 1997
Resolved
Renew retro-reflective tape on 2 adult PFD's.
Documentation
Issued 22 April 1997
Resolved
Renew garbage placard.
Lifesaving
Issued 22 April 1997
Resolved
Permanently mount bracket for waterlight on ringbuoy.
Fire Fighting
Issued 22 April 1997
Resolved
Install lanyards on fire buckets.
Documentation
Issued 8 May 1996
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Lifesaving
Issued 8 May 1996
Resolved
Post emergency check-off list.
Lifesaving
Issued 8 May 1996
Resolved
Stencil lifefloat with vessel's name and capacity.
Lifesaving
Issued 8 May 1996
Resolved
Restencil ringbuoy with vessel's name.
Lifesaving
Issued 8 May 1996
Resolved
Provide 2 additional orange flares.
Lifesaving
Issued 8 May 1996
Resolved
Renew battery in waterlight for ringbuoy.
Lifesaving
Issued 8 May 1996
Resolved
Provide watertight container for flares.
Engineering
Issued 8 May 1996
Resolved
Repair emer. fuel shutoff and stencil.
Documentation
Issued 8 May 1996
Resolved
Renew Certificate of Documentation.
Fire Fighting
Issued 18 May 1995
Resolved
Perform annual servicing on fixed halon system.
Lifesaving
Issued 18 May 1995
Resolved
Renew battery in waterlight for ringbuoy.
Lifesaving
Issued 18 May 1995
Resolved
Provide one additional red flare.
Lifesaving
Issued 18 May 1995
Resolved
Provide approved type waterlight for L/F.
Ownership record
The Coast Guard's documentation record for this hull -- the Abstract of Title,
with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National
Vessel Documentation Center, files it here with its date, and every reader of this page gets it.