This record may be incomplete: the most recent inspection recorded for this vessel was 26 years ago. Maury shows what the Coast Guard recorded, not whether the vessel has been inspected since, is still in service, or what condition it is in. Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard.
Every line above is a count of records the US Coast Guard wrote, or a date it recorded.
A blank resolution means none was recorded in this data; it does not establish that a
deficiency is outstanding. Years with a record are calendar years in which a record
exists, not years in service. What Maury does
not do.
598 - Regulatory (Subpart C or D), Net Ton
598 - Regulatory (Subpart C or D), Gross Ton
Maury page id
psix-40563
Vessel history report
Every record for this hull, in one document — $299
Every recorded inspection, 1972 to
2026, in one chronology · every deficiency, with system, dates
and resolution · operational controls imposed and removed · every name this
hull has been recorded under · the vessels it was inspected alongside, and when
· how its record compares with hulls of similar age and size, as a fact about the
population and never a judgement about this vessel.
This report is in development and is not for sale yet. There is
no date, and nothing is charged. Leave an email and we will tell you when it exists, once.
Used only to tell you when the report exists.
Not shared, not sold, and not added to a mailing list.
INSTALL TANK LEVEL INDICATORS PRIOR TO LOADING CARGO BUT NO LATER THAN 07 AUG 95
Condition: Unknown
Due 7 August 1995
Resolved 20 July 1995
Deck/Cargo
Issued 2 April 1992Resolved
CONDUCT REPAIRS ON STEAM HEATING PIPING IN WAY OF #3 PORT CARGO TANK. IN INTERIM OF REPAIRS, PLACE ADEQUATE METALLIC PORTABLE CONTAINMENT UNDERNEATH#3 PORT STEAM VENT DISCHARGE TO CAPTURE ESCAPING CARGO.
Condition: Unknown
Due 2 April 1992
Resolved 2 April 1992
Construction/Loadline
Issued 26 September 1990Resolved
REPAIR OR REPLACE TORN STERN TIMBERHEAD PRIOR TO USE, BUT NOT LATER THAN THE COMPLIANCE DATE. MAKE TEMPORARY REPAIR TO MAINTAIN VOID INTEGRITY UNTILPERMANENT REPAIRS ARE EFFECTED.
Condition: Unknown
Due 26 September 1990
Resolved 26 September 1990
Deck/Cargo
Issued 26 September 1990Resolved
HYDROSTATICALLY TEST CARGO PIPING AS REQUIRED BY 33CFR 156.170, OR IN ACCORDANCE WITH CURRENT COMMANDANT POLICY NOT LATER THAN THE COMPLIANCE DATE.
Condition: Unknown
Due 26 September 1990
Resolved 26 September 1990
Deck/Cargo
Issued 28 January 1989Resolved
INSTALL A PRESSURE GAGE IN THE DISCHARGE HEADER PRIOR TO LOADING ADDITIONALCARGO BUT NOT LATER THAN 31AUG89.
Condition: Unknown
Due 28 January 1989
Resolved 28 January 1989
Deck/Cargo
Issued 28 January 1989Resolved
MAKE PERMANENT REPAIRS TO THE STEAM COIL LEAKS IN WAY OF THE #5 AND #7 CARGO TANKS PRIOR TO LOADING ADDITIONAL CARGO BUT NOT LATER THAN 31AUG89.
Condition: Unknown
Due 28 January 1989
Resolved 28 January 1989
Deck/Cargo
Issued 17 March 1988Resolved
INSTALL CORRECT SIZE CARGO CONTAINMENT DRIP PANS ONBOARD NOT LATER THAN 30 JUN 88.
Condition: Unknown
Due 17 March 1988
Resolved 17 March 1988
Deck/Cargo
Issued 18 September 1987Resolved
MAKE PERMANENT REPAIRS TO A 6" OPEN FRACTURE LOCATED JUST BELOW THE DECK KNUCKLE ON THE VESSEL'S PORT SIDE AT NO. 2 CAVEL. THIS ITEM IS TO BE COMPLETED PRIOR TO LOADING NEXT VESSEL CARGO BUT NOT LATER THAN 18SEP87.
Condition: Unknown
Due 18 September 1987
Resolved 18 September 1987
Deck/Cargo
Issued 18 September 1987Resolved
OPEN AND CLEAN ALL P/V VALVES AND FLAME SCREENS IN P/V VALVES AND ULLAGE OPENINGS. THIS ITEM IS TO BE COMPLETED PRIOR TO LOADING NEXT VESSEL CARGO BUT NOT LATER THAN 18SEP87.
Condition: Unknown
Due 18 September 1987
Resolved 18 September 1987
Deck/Cargo
Issued 18 September 1987Resolved
PROVIDE SATISFACTORY EVIDENCE OF HYDROSTATIC TEST OF THE VESSEL'S CARGO PIPING. THIS ITEM IS TO BE COMPLETED PRIOR TO LOADING NEXT VESSEL CARGO BUT NOT LATER THAN 18SEP87.
Condition: Unknown
Due 18 September 1987
Resolved 18 September 1987
Construction/Loadline
Issued 18 September 1987Resolved
REPLACE OR REPAIR BOTH OF THE TIMBERHEADS ON THE VESSEL'S STERN. REPAIRS REQUIRED PRIOR TO USING THE FITTINGS AND NOT LATER THAN 18SEP87.
Condition: Unknown
Due 18 September 1987
Resolved 18 September 1987