This record may be incomplete: the most recent inspection recorded for this vessel was 29 years ago. Maury shows what the Coast Guard recorded, not whether the vessel has been inspected since, is still in service, or what condition it is in. Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard.
Every line above is a count of records the US Coast Guard wrote, or a date it recorded.
A blank resolution means none was recorded in this data; it does not establish that a
deficiency is outstanding. Years with a record are calendar years in which a record
exists, not years in service. What Maury does
not do.
1028 - Regulatory (Subpart C or D), Net Ton
1028 - Regulatory (Subpart C or D), Gross Ton
Maury page id
psix-40572
Vessel history report
Every record for this hull, in one document — $299
Every recorded inspection, 1972 to
2026, in one chronology · every deficiency, with system, dates
and resolution · operational controls imposed and removed · every name this
hull has been recorded under · the vessels it was inspected alongside, and when
· how its record compares with hulls of similar age and size, as a fact about the
population and never a judgement about this vessel.
This report is in development and is not for sale yet. There is
no date, and nothing is charged. Leave an email and we will tell you when it exists, once.
Used only to tell you when the report exists.
Not shared, not sold, and not added to a mailing list.
PRIOR TO PLACING VESSEL BACK IN SERVICE, PRESENT VESSEL FOR COMPLETE DRYDOCK EXAMINATION.
Condition: Unknown
Due 24 January 1996
Resolved 18 May 2002
Resolution: MISLE Maintenance - Resolved all open deficiencies issued prior to 6/1/1997 where activity was closed and deficiency due date was past
Construction/Loadline
Issued 15 September 1992Resolved
PRIOR TO PLACING VESSEL BACK IN SERVICE, PRESENT VESSEL FOR COMPLETE INTERNAL STRUCTURAL EXAMINATION.
Condition: Unknown
Due 24 January 1996
Resolved 18 May 2002
Resolution: MISLE Maintenance - Resolved all open deficiencies issued prior to 6/1/1997 where activity was closed and deficiency due date was past
Deck/Cargo
Issued 15 September 1992Resolved
PRIOR TO PLACING VESSEL BACK IN SERVICE, PRESENT VESSEL FOR CARGO TANK INTERNAL EXAMINATION.
Condition: Unknown
Due 24 January 1996
Resolved 18 May 2002
Resolution: MISLE Maintenance - Resolved all open deficiencies issued prior to 6/1/1997 where activity was closed and deficiency due date was past
Construction/Loadline
Issued 22 April 1991Resolved
EFFECT TEMPORARY REPAIRS TO DAMAGED AREA LOCATED BETWEEN #2 & #3 STBD CARGOTANKS APPROX. 2FT FROM WATERLINE. REPAIRS TO BE COMPLETED PRIOR TO DEPARTING UPPER ST. ROSE FLEETING.
Condition: Unknown
Due 22 April 1991
Resolved 22 April 1991
Construction/Loadline
Issued 22 April 1991Resolved
CLEAN & GAS FREE #2 & #3 STBD CARGO TANKS AND MAKE AVAILABLE TO A COAST GUARD MARINE INSPECTOR TO DETERMINE PERMANENT REPAIRS NECESSARY TO PLACE BARGE BACK IN SERVICEC. VESSEL TO REMAIN IN UNLOADED CARGO CONDITION UNTIL SATISFACTORY REPAIRS.
Condition: Unknown
Due 22 April 1991
Resolved 22 April 1991
Construction/Loadline
Issued 18 January 1991Resolved
PRIOR TO LOADING CARGO, STRIP WATER FROM PORT BOW AND STBD STERN CORNER VOIDS, DETERMINE SOURCE OF LEAKAGE AND MAKE PERMANENT REPAIRS.
Condition: Unknown
Due 18 January 1991
Resolved 18 January 1991
Deck/Cargo
Issued 10 August 1990Resolved
THE STEAM PIPING FOR CARGO HEATING IS NOT TO BE USED UNTIL TESTED TO THE SATISFACTION OF A CG MARINE INSPECTOR DUE TO POSSIBLE LEAKAGE OF PRODUCT INTO THE STEAM PIPING SYSTEM.
Condition: Unknown
Due 10 August 1990
Resolved 10 August 1990
Construction/Loadline
Issued 3 December 1986Resolved
PERMANENTLY REPAIR FRACTURED HANDRAIL AT FORWARD, STBD. CORNER OF DECK TANKAT NEXT GAS-FREE AVAILABILITY, BUT NOT LATER THAN 28FEB87.
Condition: Unknown
Due 3 December 1986
Resolved 3 December 1986
Construction/Loadline
Issued 8 April 1986Resolved
MAKE PERMANENT REPAIRS TO THE 5' VERTICAL CORNER FRACTURE AT THE PORT BOW.
Condition: Unknown
Due 8 April 1986
Resolved 8 April 1986
Construction/Loadline
Issued 8 April 1986Resolved
MAKE PERMANENT REPAIRS TO THE 18" VERTICAL FRACTURE ON THE PORT BOW SIDE SHELL AT THE FORMED CORNER.
Condition: Unknown
Due 8 April 1986
Resolved 8 April 1986