← All vessels
HOCKING
HOCKING is a 1968 research vessel. The Coast Guard has recorded 71 inspections since 1985, most recently in July 2025, along with 98 deficiencies.
Records from 1985 to 2025. Most recent: inspection, 10 July 2025.
- Built
- 1968
- Last inspected
- 10 July 2025
- Documentation
- Not in the documentation file of 10 September 2026
- Deficiencies
- 98 recorded · 0 without a recorded resolution
- Controls
- None recorded without a removal date
Identity
AEPB
41156
Flag
UNITED STATES
—
Maury page id
psix-41156
Inspections, by type
…with no type recorded5
Years with a record
37 calendar years (1985–2025)
The 71 inspections in the strip above, split by the kind of activity the US
Coast Guard recorded. Years with a record are calendar years in which a record exists, not
years in service. What Maury does not do.
Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Research Ship class in Maury's sources begin in 1980.
Documentation record
Tonnage as PSIX records it55 - Regulatory (Subpart C or D), Net Ton
74 - Regulatory (Subpart C or D), Gross Ton
74 - Regulatory (Subpart C or D), Gross Ton
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.
Radio station licence
No FCC ship-station licence is recorded against this Official Number in the file of
6 September 2026. That is a fact about the licence file, not about the radio.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 71
10 July 2025
Annual Inspection · In-Service Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 8160456
16 July 2024
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7959354
15 May 2024
Drydock Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7912716
6 December 2023
Drydock Exam · Deficiency Check · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7835836
19 July 2023
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7746457
13 July 2022
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7504899
6 December 2021
Internal Structural Exam · Drydock Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7362942
19 July 2021
COI Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7260680
10 August 2020
Damage Survey
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7028896
15 July 2020
Administrative Inspection · Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7007878
10 September 2019
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6808104
9 October 2018
Hull Examination · Internal Structural Exam · Examination of Repairs
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6553905
27 August 2018
Drydock Extension
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 6524413
16 August 2018
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6513688
9 November 2017
Administrative Inspection
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 6304010
28 August 2017
MTSA Verification · Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6253665
3 November 2016
Hull Examination · Deficiency Check · Examination of Repairs · Internal Structural Exam
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 6034389
28 July 2016
Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5956858
19 July 2016
COI Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5948142
27 June 2016
Drydock Extension
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 5921470
5 August 2015
Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5206743
22 July 2015
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 5192148
24 July 2012
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 4387888
20 July 2011
Deficiency Check · COI Inspection · Drydock Exam · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 4087951
7 August 2008
Annual Inspection · Hull Examination · Internal Structural Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3291449
24 September 2007
Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3064685
8 August 2006
COI Inspection · MARPOL Annex V Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 2740129
1 August 2006
Internal Structural Exam · Hull Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 2734051
15 August 2005
Annual Inspection
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 2463566
9 September 2004
MARPOL Annex V Examination · Annual Inspection · MARPOL Annex I Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 2190914
27 October 2003
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1936637
2 September 2003
Hull Examination · Internal Structural Exam
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1894290
19 August 2003
Annual Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1875755
17 September 2002
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1676493
5 August 2002
Annual Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1656688
27 November 2001
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1072092
6 August 2001
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1461422
10 August 2000
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1376289
8 February 2000
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1046508
13 December 1999
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1471398
10 November 1999
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1361206
20 July 1999
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1423232
25 September 1998
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 798845
12 August 1998
COI Inspection · Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1131661
18 May 1998
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 793376
16 December 1997
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 780526
20 November 1997
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1461002
25 September 1997
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1116078
14 August 1996
Re-Inspection · Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1089391
1 September 1995
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 876506
11 August 1995
COI Inspection · MARPOL Annex V Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 877767
13 September 1994
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1179849
31 August 1994
Deficiency Check · Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 869401
10 August 1994
MARPOL Annex V Examination · Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 869727
4 August 1993
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 845423
11 August 1992
Deficiency Check · Hull Examination · COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 951602
28 August 1991
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1249943
12 August 1991
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1249942
9 August 1990
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 913183
26 February 1990
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1233446
16 February 1990
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 930099
11 August 1989
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 890979
17 February 1989
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 892557
22 August 1988
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1198712
11 August 1988
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1038594
29 October 1987
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1326644
21 July 1987
Hull Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1328248
12 September 1986
Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1308004
11 August 1986
COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 985230
13 January 1986
Credit Drydock
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 992582
4 September 1985
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1295135
Deficiency record · 98
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 10 July 2025
Resolved
In the inspection of hulls, boilers, and machinery of vessels, the standards established by the American Bureau of Shipping, see part 90, subpart 90.35 of this chapter, respecting material and inspection of hulls, boilers, and machinery, and the certificate of classification referring thereto, except where otherwise provided for by the rules and regulations in this subchapter, subchapter E (Load Lines), subchapter F (Marine Engineering), subchapter J (Electrical Engineering).
Boiler inspection is overdue.
46CFR91.15
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 10 July 2025
Resolved
All electrical engineering details and installations shall be designed and installed in accordance with subchapter J (Electrical Engineering) of this chapter.
Engine Room emergency lighting is inadequate.
46 CFR 90.25-1
09 - Working and Living Conditions › 092 - Working Conditions › Anchoring devices
Issued 19 July 2021
Resolved
The keeper nut on the anchor swivel is at the end of the threads, tighten up the nut as discussed.
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 19 July 2021
Resolved
The pressure switch for the CO2 is not operating properly, demonstrate proper operation.
09 - Working and Living Conditions › 092 - Working Conditions › Warning notices
Issued 19 July 2021
Resolved
Provide the proper signage for operation (46 CFR 95.15-10(h) of the CO2 system and warnings
(46 CFR 97.37-11)
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 15 July 2020
Resolved
Refs: 46 CFR 91.25-20 / NFPA 10
CO2 bottles were not weighed by Sea Safety at annual servicing IAW 46 CFR and NFPA 10. Vessel must prove the bottles are in compliance with annual servicing requirements of all applicable regulations. Ambient temp and liquid level indicator accepted no longer accepted.
**BOTTLES MUST BE WEIGHED AT COI IN 2021**
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 15 July 2020
Resolved
46 CFR 95.05-1 / Sub H
Galley smoke detector expired. Independent device was installed in 2000; sensor life cycle 10 years. Detector expired 2010. Must replace.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 15 July 2020
Resolved
46 CFR 91.25-35 / Sub F
Port-side engine shift cable severely chaffed. Must replace.
Engineering › Sea-water System (primary cooling) › Piping
Issued 19 July 2016
Resolved
Rubber hose on the S/W OVBD for the STBD main needs to be replaced. Prior to going back in service after upcoming dry-dock.
Engineering › Sea-water System (primary cooling) › Piping
Issued 19 July 2016
Resolved
Replace the S/W hoses on both mains from the strainer to the pump inlet. Prior to going back in service after upcoming dry-dock.
Engineering › Diesel Engine (propulsion/auxiliary-electric) › Emergency shutdown
Issued 19 July 2016
Resolved
Prove proper operation of the low L/O alarm for the STBD main.
Engineering › Steam Boiler (auxiliary/waste heat) › Valve, Relief
Issued 19 July 2016
Resolved
The relief valve on the boiler did not relieve at the proper PSI. Need to prove proper operation of the relieving device. Prior to going back in service after upcoming dry-dock.
Engineering › Pressure Vessel › Pressure Gauge
Issued 19 July 2016
Resolved
Perform hydro test on the boiler. Prior to going back in service after upcoming dry-dock.
Engineering › Diesel Engine (auxiliary) › Overspeed Device
Issued 22 July 2015
Resolved
Crew were not able to prove operation of over speed trip for starboard generator. CG-835 issued to prove proper operation of starboard generators over speed trip to the satisfaction of attending Marine Inspector
Engineering › Steam Boiler (auxiliary/waste heat) › Automation Equipment
Issued 24 July 2012
Resolved
Prior tooperating heating boiler and or placing it service CG Marine Inspector must inspect the system. Additionally hydro test the system at 1.25 times MAWP.
Engineering › Bilge Water Management System › Pump
Issued 20 July 2011
Resolved
Demonstrate proper operation of bilge pump system both electric and engine driven pump prior to conducting operations.
Fire Fighting › Fixed CO2 Fire Extinguishing System › Automatic Heat Detectors
Issued 20 July 2011
Resolved
Demonstrate proper operation of heat sensor for fixed CO2 System prior to conducting operations.
Communications › Alarms/Indicators › Engine RPM Gauge/Indicator
Issued 20 July 2011
Resolved
Starboard generator alarm panel in the pilothouse not operating properly.
Construction/Loadline › Structures › Door
Issued 7 August 2008
Resolved
Replace cracked window IWO port side pilot house door.
Fire Fighting › Ventilation Systems › Fans
Issued 15 August 2005
Resolved
Make repairs to automatic shut down for E/R exhaust blowers. Blowers do not shut down when CO2 system is actuated.
Engineering › Sea-water System (primary cooling)
Issued 2 September 2003
Resolved
Make available for CG inspection all sea valves (6) and sea chests. LEGACY COMPONENT DESC: Valve
Engineering › Sea-water System (primary cooling)
Issued 2 September 2003
Resolved
Replace port and starboard MDE sea suction valves. LEGACY COMPONENT DESC: Valve
Construction/Loadline › Hull
Issued 2 September 2003
Resolved
Make available for CG inspection all interior hull plating. LEGACY COMPONENT DESC: Hull Plating
Engineering › Shafting/Propeller Arrangements
Issued 2 September 2003
Resolved
Replace port aft cutlass bearing. LEGACY COMPONENT DESC: Bearing
Engineering › Shafting/Propeller Arrangements
Issued 2 September 2003
Resolved
Repair/replace port propeller due to fracture. LEGACY COMPONENT DESC: Propeller (fixed pitch)
Engineering › Shafting/Propeller Arrangements
Issued 2 September 2003
Resolved
Draw both shafts and make available for CG inspection. LEGACY COMPONENT DESC: Propeller Shaft
Engineering › Steering Gear System
Issued 2 September 2003
Resolved
Make permanent repairs to P/S rudder stops. LEGACY COMPONENT DESC: Rudder
Engineering › Bilge Water Management System
Issued 2 September 2003
Resolved
Hard pipe all connections for bilge eductor system. LEGACY COMPONENT DESC: Piping
Fire Fighting › Means of Escape
Issued 2 September 2003
Resolved
Make permanent repairs to hairline crack in both emergency escape hatches and properly adjust handles.
Construction/Loadline › Structures
Issued 2 September 2003
Resolved
Install watertight packing to cables (2) on forward E/R bulkhead. LEGACY COMPONENT DESC: Transverse Bulkhead
Construction/Loadline › Structures
Issued 2 September 2003
Resolved
Replace gaskets to WTD's for E/R and FWD berthing. LEGACY COMPONENT DESC: Door
Fire Fighting › Fixed CO2 Fire Extinguishing System
Issued 19 August 2003
Resolved
CO2 25 sec time delay tested and discharged at 20 sec. Replace or prove proper operation of time delay prior to operating. Vessel to provide ACTNY inspection certificate from servicing tech attesting to proper operation. LEGACY COMPONENT DESC: Operating Controls
Navigation › Collision/Grounding Avoidance
Issued 19 August 2003
Resolved
Sternlight top cap broke during operations. Issued requirement to replace. Witnessed sat operation of light and requisition of new light. LEGACY COMPONENT DESC: Navigation Lights
Communications › Radio Communications
Issued 19 August 2003
Resolved
EPIRB sent in to manufacturer for battery replacement and repair of strobe light. Issued requirement to install prior to operating in Oceans or Coastwise trade route. LEGACY COMPONENT DESC: EPIRB
Lifesaving › Rocket Parachute Flares
Issued 5 August 2002
Resolved
Provide 12 Rocket Parachut flares IAW 46 CFR sub W
Communications › Radio Communications
Issued 5 August 2002
Resolved
Provide current hydrostatic release LEGACY COMPONENT DESC: EPIRB
Lifesaving › Immersion Suits
Issued 5 August 2002
Resolved
Provide #30 immersion suits
Lifesaving › Lifejacket/PFD (General)
Issued 5 August 2002
Resolved
Repair/replace retroreflective material and lights for identified lifejackets LEGACY COMPONENT DESC: Retroreflective Material
Deck/Cargo › Mooring/Anchoring
Issued 5 August 2002
Resolved
Secure anchor LEGACY COMPONENT DESC: Anchor
Lifesaving
Issued 6 August 2001
Resolved
VESSEL IS REQUIRED TO HAVE (15) MAN L/R ONBOARD, CURRENTLY A (10) MAN LOANER IS INSTALLED. VESSEL IS LIMITED TO 22 PERSONS UNTIL REPLACED.
Lifesaving
Issued 6 August 2001
Resolved
VESSEL IS LIMITED TO 22 PERSONS UNTIL ADULT LIFEJACKETS ARE REPLACED OR REPAIRED.
Lifesaving
Issued 6 August 2001
Resolved
REPLACE BROKEN PADDLES FOR LIFE FLOAT.
Lifesaving
Issued 6 August 2001
Resolved
PROVIDE ONBOARD LIFESAVING REQUIREMENTS OF 46CFR 199.180.
Electrical
Issued 6 August 2001
Resolved
REPAIR LIGHTING FIXTURE IN ENGINEROOM.
Navigation
Issued 6 August 2001
Resolved
STEERING GEAR IS RESISTANT FROM SIDE TO SIDE WITH A HUNTING MOTION WITH MOTOR, MAKE REPAIRS TO SYSTEM.
Accommodation/Occupational Safety
Issued 10 November 1999
Resolved
SUBMIT PLAN FOR FOR FORWARD RAILS TO COAST GUARD PLAN REVIEW AND EXTEND RAIL HEIGHT ON FORWARD RAILS TO 39.5 INCHES AS DISCUSSED.
Electrical
Issued 10 November 1999
Resolved
Provide marine type/grade alternator on port generator.
Lifesaving
Issued 10 November 1999
Resolved
Replace expired hydrostatic release mechanism on EPIRB.
Electrical
Issued 10 November 1999
Resolved
Extend rubber matting in front of gererator switchboard to a reasonable length.
Documentation
Issued 10 November 1999
Resolved
Provide Waste Management Plan iaw 33 CFR 151.57.
Navigation
Issued 10 November 1999
Resolved
Replace port running light canister.
Lifesaving
Issued 10 November 1999
Resolved
Provide new retroreflective tape (Type II) and line (dark in color or UV resistant: 46 CFR 180.175) for the lifefloats.
Lifesaving
Issued 12 August 1998
Resolved
Install 30x30 mesh screen for port fuel tank.
Engineering
Issued 12 August 1998
Resolved
Weld cracks in port engine muffler.
Electrical
Issued 12 August 1998
Resolved
Provide method to verify generator overspeed trip and overspeed trip setting.
Navigation
Issued 12 August 1998
Resolved
Verfy proper steering hydraulic operation and lubricate pivit point._x001C_ (No Sail)
Construction/Loadline
Issued 12 August 1998
Resolved
Renew gasket port side engine room escape.
Construction/Loadline
Issued 12 August 1998
Resolved
Repair or replace sea chest guards.
Fire Fighting
Issued 25 September 1997
Resolved
DOUBLE CLAMP ALL HOSES FOR THE FIRE MAIN SYSTEM PIPING IN THE ENGINEROOM.
Engineering
Issued 25 September 1997
Resolved
DOUBLE CLAMP THE RAW WATER HOSE OVBD DISCHARGE FOR THE STBD MDE.
Lifesaving
Issued 25 September 1997
Resolved
PROVIDE A RESCUE PLATFORM FOR RETRIEVING A PERSON THAT HAS FALLEN OVBD.
Unknown
Issued 25 September 1997
Resolved
PROVIDE PROOF THAT VESSEL AND CREW BELONG TO A DRUG CONSORTIUM.
Unknown
Issued 25 September 1997
Resolved
PROVIDE COPIES OF 46 SUBCHAPTER T PART 166-199 AND 47 CFR PART 80 TO END.
Lifesaving
Issued 25 September 1997
Resolved
PROVIDE SIX ADULT LIFE JACKETS WITH LIGHTS.
Fire Fighting
Issued 25 September 1997
Resolved
WIRE THE ENGINEROOM EXHAUST FAN SO THAT IT SECURES WHEN THE CO2 SYSTEM IS ACTIVATED.
Lifesaving
Issued 25 September 1997
Resolved
REPAIR THE VESSEL'S EPRIB, THE LIGHT DID NOT ACTIVATE WHEN PLACED IN THE TEST POSITION.
Lifesaving
Issued 25 September 1997
Resolved
PROVIDE AND INSTALL A COAST GUARD APPROVED WEAK LINK FOR THE VESSEL'S LIFERAFT.
Lifesaving
Issued 25 September 1997
Resolved
PROVIDE ONE PADDLE AND PLACE IN THE VESSEL'S BA.
Documentation
Issued 25 September 1997
Resolved
PROVIDE AND POST A LETTER OF STABILITY FOR THE VESSEL.
Unknown
Issued 25 September 1997
Resolved
PROVIDE A PLUG OR CAP OFF HOLE THROUGH FWD BLKHD IN E/R AT CENTERLINE TO MAKE WATERTIGHT.
Unknown
Issued 25 September 1997
Resolved
MOUNT MICROWAVE OVEN SECURELY TO COUNTERTOP, OR REMOVE IT FROM VESSEL.
Navigation
Issued 25 September 1997
Resolved
PROVIDE AND POST NEAR RADIO, EMERGENCY OPERATING INSTRUCTION.
Lifesaving
Issued 25 September 1997
Resolved
PROVIDE AND POST INSTRUCTIONS FOR DONNING LIFE JACKETS.
Electrical
Issued 25 September 1997
Resolved
INSTALL GLOBES OVER LIGHT FIXTURES IN THE ENGINEROOM.
Electrical
Issued 25 September 1997
Resolved
LABEL BATTERY CHARGER DISCONNECT SWITCHES IN ENGINEROOM.
Electrical
Issued 25 September 1997
Resolved
REMOVE DEAD ENDED WIRES NEAR BOTH THE PORT AND STBD GENERATORS.
Electrical
Issued 25 September 1997
Resolved
PROVIDE A SWITCH HANDLE AND INSTALL ON SHORE POWER DISCONNECT SWITCH ON SWITCHBOARD IN ENGINEROOM.
Engineering
Issued 25 September 1997
Resolved
DOUBLE NUT OR COTTER PIN THE CLUTCH AND THROTTLE CONTROLS FOR BOTH MDE'S.
Electrical
Issued 25 September 1997
Resolved
MAKE EMERGENCY LIGHTING THROUGHOUT THE VESSEL ACTIVATE AUTOMATICALLY UPON LOSS OF NORMAL ELECTRICAL POWER.
Electrical
Issued 25 September 1997
Resolved
PROVIDE ELECTRICAL GRADE SAFETY MATTING AND PLACE NEAR SWITCHBOARD IN ENGINEROOM.
Electrical
Issued 11 August 1995
Resolved
PROVE PROPER OPERATION OF THE EMERGENCY LIGHTING TO THE SATISFACTION OF THEATTENDING MARINE INSPECTOR.
Lifesaving
Issued 11 August 1995
Resolved
REPLACE HYDROSTATIC RELEASE UNIT ATTACHED TO THE EPIRB.
Engineering
Issued 13 September 1994
Resolved
REPAIR LEAKING PORT GENERATOR EXHAUST SYSTEM IN LAZARETTE.
Construction/Loadline
Issued 31 August 1994
Resolved
REPLACE BILGE ALARMS IN THE FWD PEAK, FUEL COMPT, & LAZARETTE.
Engineering
Issued 31 August 1994
Resolved
REPLACE FLEXIBLE HOSES ON BOTH DIESEL TANK FILLS VENTS AND SOUNDING TUBES WITH SUITABLE FLEXIBLE TUBING.
Engineering
Issued 10 August 1994
Resolved
INSTALL EXHAUST LAGGING ON STBD MDE EXHAUST SYSTEM. (01) 2 FT SECTION BEFORE WATER INJECTION. (01) 1 FT SECTION BEFORE SECOND 90 DEGREE ELBOW AFTER ENGINE LEFT BANK.
Engineering
Issued 10 August 1994
Resolved
FABRICATE AND INSTALL GUARD ON FWD CRANKSHAFT AUXILIARY DRIVE FULLY AND STEERING PUMP BELTS, STBD MDE
Accommodation/Occupational Safety
Issued 10 August 1994
Resolved
REPAIR FWD BERTHING ESCAPE HATCH SO IT CAN BE OPENED FROM INSIDE COMPT.
Lifesaving
Issued 4 August 1993
Resolved
PROVIDE LIGHTS FOR CHILD LIFE PRESERVERS TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR. VESSEL IS NOT TO OPERATE WITH CHILDREN ABOARD UNTIL REQUIREMENT IS SATISFIED BUT IN NO CASE LATER THAN 18AUG93.
Lifesaving
Issued 4 August 1993
Resolved
PROVIDE PROPER CLASS A EPIRB TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR. VESSEL IS NOT TO OPERATE ON AN OCEANS ROUTE UNTIL THIS REQUIREMENT IS CLEARED BUT IN NO CASE LATER THAN 18AUG93.
Lifesaving
Issued 4 August 1993
Resolved
PROVIDE PROPER PYRO DISTRESS SIGNALS TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR. VESSEL MAY ONLY BE OPERATED DURING DAYLIGHT HOURS UNTIL REQUIREMENT IS CLEARED. IN NO CASE LATER THAN 18AUG93. REQUIREMENT MAY BE CLEARED BY FAX.
Lifesaving
Issued 11 August 1992
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Electrical
Issued 11 August 1992
Resolved
PROVE PROPER OPERATION OF BOTH SHIP'S SERVICE GENERATOR AMPERE METERS TO BECOMPLETED TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR.
Fire Fighting
Issued 11 August 1988
Resolved
PROVE OPERATION AND ABILITY TO DELIVER A EFFECTIVE STREAM FROM ENGINE DRIVEN FIRE PUMP.
Fire Fighting
Issued 11 August 1988
Resolved
CO2 FIRE EXTINGUISHERS ARE PAST DUE FOR HYDROSTATIC TESTING.
Accommodation/Occupational Safety
Issued 11 August 1986
Resolved
TEST OPERATING CONTROLS AND SAFETY VALVES ON OIL-FIRED PACKAGE HEATING BOILER.
Accommodation/Occupational Safety
Issued 11 August 1986
Resolved
CONDUCT 1.5 HYDROSTATIC TEST ON STAINLESS STEEL H.W. STORAGE TANK.
Engineering
Issued 11 August 1986
Resolved
INSTALL RACOR FIRE SHIELDS ON ALL SEVEN (7) RACOR FUEL FILTERS IN ENGINE ROOM.
Ownership record
The Coast Guard's documentation record for this hull -- the Abstract of Title,
with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National
Vessel Documentation Center, files it here with its date, and every reader of this page gets it.