Inspection history · 70
8 October 2015
Administrative Inspection
Administrative · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 5738329
31 October 2013
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4800331
12 August 2013
Administrative Inspection · Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4684829
16 July 2013
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4654895
16 November 2012
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4511217
31 July 2012
Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 4396976
14 June 2012
Damage Survey
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 4344003
26 September 2011
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4203941
3 November 2010
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3883893
28 October 2010
Periodic Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3879851
23 March 2010
Type not recorded
No type recorded · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 3701973
9 September 2009
Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3682593
30 October 2008
MTSA Verification · COI Inspection · Internal Structural Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3354227
16 March 2008
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3168352
1 October 2007
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3084506
19 December 2006
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2843130
30 November 2006
Damage Survey
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 2832459
30 November 2006
Type not recorded
No type recorded · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 2836101
19 September 2006
Periodic Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2852722
24 August 2006
Type not recorded
No type recorded · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 2758631
4 May 2006
Permit to Proceed
Administrative · Marine Safety Unit Huntington · USCG Heartland District (CGD-H) · Activity 2640237
1 February 2006
MTSA Verification · Annual Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2577310
28 September 2005
Administrative Inspection
Administrative · Marine Safety Unit Huntington · USCG Heartland District (CGD-H) · Activity 2521821
20 February 2005
Administrative Inspection
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2296129
16 August 2004
MTSA Verification · Annual Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2227767
24 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1985584
30 October 2003
Cargo Tank Internal · Examination of Repairs · Hull Examination · COI Inspection · Internal Structural Exam
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1920583
25 March 2003
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1770446
26 February 2003
Examination of Repairs
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1749926
27 August 2002
Periodic Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1676845
16 August 2001
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1072097
5 April 2001
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1062413
13 October 2000
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1470279
12 November 1999
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 810715
19 February 1999
Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 796653
18 December 1998
COI Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 808088
3 December 1997
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1113529
24 February 1997
Re-Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1096312
24 January 1996
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1414572
21 February 1995
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1355108
6 April 1994
COI Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1165831
14 October 1993
Administrative
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 832002
17 September 1993
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1153226
24 February 1993
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 642037
12 February 1993
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 505673
12 February 1993
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 525971
29 October 1992
COI Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1252932
15 September 1992
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 947300
9 September 1992
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1250557
9 July 1992
Damage Survey
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 952202
26 March 1992
Re-Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1261080
26 April 1991
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 933581
19 December 1990
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 906795
12 December 1990
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 924269
8 November 1990
Damage Survey
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1230356
4 September 1990
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 466332
25 June 1990
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1242222
1 March 1990
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 531475
25 May 1989
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 970355
28 June 1988
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1338155
22 May 1987
Hull Examination · COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1004483
29 March 1986
COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 999574
12 July 1985
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 985522
5 July 1985
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 978732
17 October 1984
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 450046
18 June 1984
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 974079
23 May 1984
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 973154
7 March 1984
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1280213
22 July 1983
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 970421
1 June 1982
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 968327
Construction/Loadline › Hull › Hull Plating
Issued 16 July 2013
Resolved
D8 TBSIP SELF-REPORTED DEFICIENCY. Make permanent repair to fracture approx. 4" x ¼". Fracture is located between starboard push knee and center line of barge 18" up from bottom.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 20 August 2013
Resolved 14 August 2013
Resolution: Witnessed satisfactory air test of repairs made to fractured plate in way of stern rake.
Construction/Loadline › Hull › Double Hull
Issued 14 June 2012
Resolved
Discovered 1/4" x 6" crack in the starboard bow corner wrap. Within the perameters of "minor damage" as defined in the TBSIP.
Action required: 705 - Other - as specified
Due 1 August 2012
Resolved 14 June 2012
Construction/Loadline › Hull › Double Hull
Issued 30 November 2006
Resolved
3 ft x 5 ft fracture/holed 32" above waterline 15 " inset
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Resolved 19 December 2006
Construction/Loadline › Hull › Hull Plating
Issued 4 May 2006
Resolved
REPAIR 3 INCH FRACTURE IN THE STBD BOW CORNER WRAP WHICH IS TEMP PATCHED WITH SHINGLES AND OAKUM.
Condition: Unknown
Action required: 705 - Other - as specified
Due 17 June 2006
Resolved 19 December 2006
Construction/Loadline › Hull › Hull Plating
Issued 28 September 2005
Resolved
REPAIR 15" FRACTURE ON STBD STERN CORNER AT THE 10FT DRAFT UNDER THE RUB RAIL WHICH IS TEMP PATCHED.
Condition: Unknown
Action required: 705 - Other - as specified
Due 11 November 2005
Resolved 4 May 2006
Resolution: REPAIRED IN HOUSTON AT STOLT BARGE SERVICE ON 02/03/06
Construction/Loadline
Issued 9 July 1992
Resolved
MAKE #1 PORT VOID AVAILABLE FOR INSPECTION AND PERMANENT REPAIR OF TWO SHINGLED HOLES IN WAY OF BOTTOM SIDE LONG. PROVIDE SHELL GAGING TO COGNIZANT OCMI FOR ADJACENT PLATE AREA.OFFLOAD PRESENT CARGO AND DON'T RELOAD. MAINTAIN TEMP REPAIRS AND KEEP ALL VOIDS PUMPED DRY.
Condition: Unknown
Due 9 July 1992
Resolved 9 July 1992
Construction/Loadline
Issued 8 November 1990
Resolved
MAKE PERMENENT REPAIRS TO 3" FRACTURE, IN STERN VOID STBD CORNER 1' DRAFT. TO SATISFACTION OF ATTENDING CG MARINE INSPECTOR.
Condition: Unknown
Due 8 November 1990
Resolved 8 November 1990
Deck/Cargo
Issued 5 July 1985
Resolved
PERFORM HYDROSTATIC TEST OF CARGO PIPING 1 1/2 X MAWP
Condition: Unknown
Due 5 July 1985
Resolved 5 July 1985
Deck/Cargo
Issued 5 July 1985
Resolved
INSTALL VALVE IN PORT CONTAINMENT RECEPTACLE TO STOP TANK FROM DRAINING ON DOCK.
Condition: Unknown
Due 5 July 1985
Resolved 5 July 1985