USNS KANE (AGS 27) is a 1966 research vessel. The Coast Guard has recorded 66 inspections since 1985, most recently in March 2000, along with 101 deficiencies.

Records from 1985 to 2000. Most recent: inspection, 6 March 2000.

Built
1966
Last inspected
6 March 2000
Documentation
Not in the documentation file of 10 September 2026
Controls
None recorded without a removal date

Identity

7738644 View on MarineTraffic leaves Maury; a third-party site, nothing from it is stored here
Flag
UNITED STATES
—
Maury page id
psix-41387

Inspections, by type

…with no type recorded20
Years with a record 16 calendar years (1985–2000)
The 66 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

This record may be incomplete: the most recent inspection recorded for this vessel was 26 years ago. Maury shows what the Coast Guard recorded, not whether the vessel has been inspected since, is still in service, or what condition it is in. Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Research Ship class in Maury's sources begin in 1980.

Documentation record

Tonnage as PSIX records it2616 - Regulatory (Subpart C or D), Gross Ton
835 - Regulatory (Subpart C or D), Net Ton
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.

Radio station licence

No FCC ship-station licence is recorded against this Official Number in the file of 6 September 2026. That is a fact about the licence file, not about the radio.

A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.

Inspection history · 66

6 March 2000 Deficiency Check
Physical examination · Activities Europe · Activity 815781
13 January 2000 Hull Examination · COI Inspection
Physical examination · Activities Europe · Activity 1372890
8 October 1999 Administrative
Administrative · Activities Europe · Activity 1125290
23 July 1999 Type not recorded
No type recorded · Activities Europe · Activity 12540
13 July 1999 Deficiency Check
Physical examination · Activities Europe · Activity 1096757
14 June 1999 Type not recorded
No type recorded · Activities Europe · Activity 691314
14 June 1999 Type not recorded
No type recorded · Activities Europe · Activity 808520
26 March 1999 Type not recorded
No type recorded · MSO HAMPTON ROADS · USCG East District (CGD-E) · Activity 220599
2 March 1999 Administrative
Administrative · Activities Europe · Activity 797069
22 December 1998 Re-Inspection
Physical examination · Activities Europe · Activity 1378531
9 February 1998 COI Inspection
Physical examination · Activities Europe · Activity 777271
31 October 1997 Hull Examination
Physical examination · Activities Europe · Activity 1107664
30 October 1997 Drydock Extension
Administrative · Activities Europe · Activity 779986
13 October 1997 Type not recorded
No type recorded · Activities Europe · Activity 1396810
14 May 1997 Deficiency Check
Physical examination · Activities Europe · Activity 1105102
4 February 1997 Deficiency Check
Physical examination · Activities Europe · Activity 1101095
29 December 1996 Re-Inspection
Physical examination · Activities Europe · Activity 1356049
16 May 1996 Deficiency Check
Physical examination · Activities Europe · Activity 1083377
26 March 1996 Deficiency Check
Physical examination · Activities Europe · Activity 1357548
11 March 1996 Deficiency Check
Physical examination · Activities Europe - OLD · USCG Northeast District (CGD-NE) · Activity 884715
29 February 1996 COI Inspection
Physical examination · Activities Europe - OLD · USCG Northeast District (CGD-NE) · Activity 885378
4 May 1995 Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1204914
3 April 1995 Re-Inspection
Physical examination · MSO HAMPTON ROADS · USCG East District (CGD-E) · Activity 1463169
12 November 1994 Deficiency Check
Physical examination · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 862701
8 November 1994 Type not recorded
No type recorded · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 1180892
17 October 1994 Type not recorded
No type recorded · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 643397
7 October 1994 Type not recorded
No type recorded · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 95149
7 October 1994 Type not recorded
No type recorded · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 147278
7 October 1994 Damage Survey · Deficiency Check · Examination of Repairs · Hull Examination
Physical examination · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 1353655
30 September 1994 Deficiency Check
Physical examination · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 868094
17 August 1994 Type not recorded
No type recorded · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 1171756
28 July 1994 Type not recorded
No type recorded · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 643398
27 July 1994 Type not recorded
No type recorded · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 24938
31 May 1994 Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 868658
26 April 1994 Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1168473
30 March 1994 COI Inspection · MARPOL Annex V Examination
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1167218
14 October 1993 Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1154531
23 May 1993 Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1147416
2 February 1993 Type not recorded
No type recorded · Commandant (CG-INV) · Activity 226134
21 December 1992 Deficiency Check
Physical examination · MSO HAMPTON ROADS · USCG East District (CGD-E) · Activity 831486
15 December 1992 Hull Examination
Physical examination · MSO HAMPTON ROADS · USCG East District (CGD-E) · Activity 826576
19 August 1992 Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 951326
11 May 1992 COI Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 950545
31 July 1991 Re-Inspection
Physical examination · MSO CHARLESTON · USCG Southeast District (CGD-SE) · Activity 1249010
29 May 1990 Deficiency Check
Physical examination · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 1231408
29 May 1990 Deficiency Check
Physical examination · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 1232522
19 May 1990 Deficiency Check
Physical examination · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 919866
18 May 1990 Deficiency Check
Physical examination · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 1228484
15 May 1990 COI Inspection
Physical examination · MSO CHARLESTON · USCG Southeast District (CGD-SE) · Activity 928402
25 April 1990 Hull Examination
Physical examination · MSO CHARLESTON · USCG Southeast District (CGD-SE) · Activity 923360
20 April 1990 Type not recorded
No type recorded · MSO JACKSONVILLE · USCG Southeast District (CGD-SE) · Activity 925780
26 October 1989 Type not recorded
No type recorded · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 930091
26 October 1989 Type not recorded
No type recorded · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1238976
18 September 1989 Damage Survey
Physical examination · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 886830
16 June 1989 Re-Inspection
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1035330
27 May 1988 Hull Examination · COI Inspection
Physical examination · MSO CHARLESTON · USCG Southeast District (CGD-SE) · Activity 898022
5 April 1988 Type not recorded
No type recorded · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 996356
8 February 1988 Type not recorded
No type recorded · MSO MIAMI · USCG Southeast District (CGD-SE) · Activity 1326630
20 November 1987 Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1339079
9 July 1987 Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1028889
18 August 1986 Deficiency Check
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1294238
31 May 1986 Deficiency Check
Physical examination · MSO CHARLESTON · USCG Southeast District (CGD-SE) · Activity 1298295
9 May 1986 Credit Drydock
Administrative · MSO CHARLESTON · USCG Southeast District (CGD-SE) · Activity 988012
16 September 1985 Examination of Repairs
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1297921
3 April 1985 Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1289314
4 March 1985 Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1285597

Deficiency record · 101

Documentation
Issued 13 January 2000 Resolved
Provide a manual containing procedures for conducting drug tests for "Reasonable Cause."
Condition: Unknown
Due 13 March 2000
Resolved 28 February 2000
Lifesaving
Issued 13 January 2000 Resolved
Post donning instructions for the lifejackets in all accommodation spaces. The instructions must match the type of lifejackets being stored.
Condition: Unknown
Due 6 March 2000
Resolved 6 March 2000
Fire Fighting
Issued 13 January 2000 Resolved
Install and prove the proper operation of the general alarm beacon in the engineroom. Beacon must be labelled and visible from all areas of the engineroom.
Condition: Unknown
Due 6 March 2000
Resolved 6 March 2000
Documentation
Issued 13 January 2000 Resolved
Provide a licensed 1st assistant engineer as per the certificate of inspection.
Condition: Unknown
Due 13 March 2000
Resolved 28 February 2000
Lifesaving
Issued 13 January 2000 Resolved
Renew the improperly installed rivets on the starboard lifeboat.
Condition: Unknown
Due 13 March 2000
Resolved 28 February 2000
Fire Fighting
Issued 13 January 2000 Resolved
Provide and post the approved fire control plan.
Condition: Unknown
Due 6 March 2000
Resolved 6 March 2000
Electrical
Issued 13 January 2000 Resolved
Prove the proper operation of the emergency battery operated light in the corning winch compartment.
Condition: Unknown
Due 6 March 2000
Resolved 6 March 2000
Documentation
Issued 13 January 2000 Resolved
Provide a manual containing procedures for drug testing following a "Serious Marine Incident."
Condition: Unknown
Due 13 March 2000
Resolved 28 February 2000
Documentation
Issued 13 January 2000 Resolved
Provide one additional able bodied seaman (AB) as per the certificate of inspection.
Condition: Unknown
Due 13 March 2000
Resolved 28 February 2000
Navigation
Issued 14 June 1999 Resolved
STEERING GEAR FAILURE.
Condition: Unknown
Due 15 June 1999
Resolved 14 June 1999
Documentation
Issued 14 June 1999 Resolved
VESSEL MISSING 2AE._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 15 June 1999
Resolved 14 June 1999
Lifesaving
Issued 14 June 1999 Resolved
EPIRB INOP.
Condition: Unknown
Due 15 June 1999
Resolved 14 June 1999
Lifesaving
Issued 14 June 1999 Resolved
PORT LIFE BOAT HOLED in FIVE PLACES ALONG KEEL.
Condition: Unknown
Due 15 June 1999
Resolved 14 June 1999
Lifesaving
Issued 14 June 1999 Resolved
STARBOARD WINCH BRAKE INOP.
Condition: Unknown
Due 15 June 1999
Resolved 14 June 1999
Engineering
Issued 22 December 1998 Resolved
RENEW FILL SWITCH FOR #2 BOILER. _x001C_
Condition: Unknown
Due 11 January 1999
Resolved 11 January 1999
Lifesaving
Issued 22 December 1998 Resolved
REPAIR HOLES IN #2 LIFEBOAT. REPAIRS MUST BE MADE TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR. A 25 PERSON LIFERAFT MAY BE TEMPORARILY BEUSED TO TO REPLACE THE LIFEBOAT FOR 60 DAYS. _x001C_
Condition: Unknown
Due 22 December 1998
Resolved 22 December 1998
Engineering
Issued 9 February 1998 Resolved
Repair and test operation of #1 (aft) Auxiliary Boiler High Coil Temperature trip device. #1 Boiler is not to be operated until device is functioning properly.
Condition: Unknown
Due 18 March 1998
Resolved 6 April 1998
Navigation
Issued 9 February 1998 Resolved
Repair and demonstrate proper operation of Engine Order Telegraph.
Condition: Unknown
Due 18 March 1998
Resolved 6 April 1998
Documentation
Issued 9 February 1998 Resolved
Revise vessel's Oil Transfer Procedures to contain all required elements specified by 33 CFR 155.720.
Condition: Unknown
Due 18 March 1998
Resolved 6 April 1998
Navigation
Issued 9 February 1998 Resolved
Repair sound powered telephone for Aft 01 Deck Steering Station. This steering station may not be used until the repair is made
Condition: Unknown
Due 18 March 1998
Resolved 6 April 1998
Navigation
Issued 9 February 1998 Resolved
Repair all Bridge [name withheld] indicating lamps for steering pumps.
Condition: Unknown
Due 18 March 1998
Resolved 6 April 1998
Construction/Loadline
Issued 9 February 1998 Resolved
Renew bilge suction valve for after end of Shaft Alley.
Condition: Unknown
Due 16 February 1998
Resolved 20 February 1998
Lifesaving
Issued 29 December 1996 Resolved
Provide the missing framing for the port and stbd lifeboat "SOLAS" covers.
Condition: Unknown
Due 29 December 1996
Resolved 29 December 1996
Fire Fighting
Issued 29 December 1996 Resolved
Renew the defective heat activation device for the aft paint locker fixed CO2 system.
Condition: Unknown
Due 29 December 1996
Resolved 29 December 1996
Lifesaving
Issued 29 December 1996 Resolved
All four Viking inflatable 20-man liferafts on board must be serviced no later than 01AUG97. This is due to hydrostatic testing of CO2 bottles (due7/97) being out of phase with the servicing anniversary date. Testing of the bottles was not practical at the time of annual servicing (01JAN97).
Condition: Unknown
Due 29 December 1996
Resolved 29 December 1996
Lifesaving
Issued 29 December 1996 Resolved
Provide 20 additional CG-approved lifejackets with waterlights & whistles. Vessel may carry no more than 58 total persons on board until these lifejackets are provided.
Condition: Unknown
Due 29 December 1996
Resolved 29 December 1996
Construction/Loadline
Issued 29 December 1996 Resolved
Renew both Auxilliary Salt Water Pump non-metallic expansion joints.
Condition: Unknown
Due 29 December 1996
Resolved 29 December 1996
Electrical
Issued 29 February 1996 Resolved
PROVE PROPER OPERATION INCLUDING ALL SHUTDOWNS ON 40 KW GENERATOR SET LOCATED IN EMERGENCY GENERATOR ROOM
Condition: Unknown
Due 11 March 1996
Resolved 11 March 1996
Electrical
Issued 29 February 1996 Resolved
PROVIDE EMERGENCY LIGHTING FOR ALL LIFERAFTS AND LIFEBOATS AS PER 46CFR111.75-16 AND FOR THE NEW FORWARD EMERGENCY GEAR LOCKER.
Condition: Unknown
Due 29 February 1996
Resolved 29 February 1996
Lifesaving
Issued 29 February 1996 Resolved
PROVIDE DOCUMENTATION THAT ALLOWED THE TOTAL PERSONS TO BE INCREASED (28 PERSONS) BEYOND THE NORMAL 50 PERSONS LIFEBOAT CAPACITY.
Condition: Unknown
Due 29 February 1996
Resolved 29 February 1996
Accommodation/Occupational Safety
Issued 29 February 1996 Resolved
CROP & RENEW IN WAY OF SOFT PATCHES WASTED PIPING ON PORT EVAPORATOR (3) THREE PLACES.
Condition: Unknown
Due 29 February 1996
Resolved 29 February 1996
Electrical
Issued 29 February 1996 Resolved
PROVE PROPER OPERATION OF JACKET WATER ALARMS & TRIPS ON S/S GENERATOR 1, 2& 3.
Condition: Unknown
Due 29 February 1996
Resolved 29 February 1996
Accommodation/Occupational Safety
Issued 29 February 1996 Resolved
CROP & RENEW PIPING IN WAY OF SOFT PATCHES (1) ON STBD EVAPORATOR
Condition: Unknown
Due 29 February 1996
Resolved 29 February 1996
Engineering
Issued 29 February 1996 Resolved
CROP & RENEW CONDENSATE PIPING IN WAY OF SOFT PATCHES LOCATED FORWARD PORT SIDE OF ENGINE ROOM
Condition: Unknown
Due 29 February 1996
Resolved 29 February 1996
Electrical
Issued 8 November 1994 Resolved
PROVE PROPER OPERATION OF THE MAIN PROPULSION MOTOR PRIOR TO THE VESSELS DEPARTURE FROM THE PORT OF JACKSONVILLE.
Condition: Unknown
Due 8 January 1995
Resolved 14 November 1994
Electrical
Issued 7 October 1994 Resolved
Clean, repair and demonstrate each auxiliary electric motor in main motor room, prior to departing the port of Jacksonville.
Condition: Unknown
Due 9 November 1994
Resolved 9 November 1994
Electrical
Issued 7 October 1994 Resolved
Provide meggar readings of main motor & demonstrate proper operation of same, prior to departing the port of Jacksonville.
Condition: Unknown
Due 9 November 1994
Resolved 9 November 1994
Lifesaving
Issued 7 October 1994 Resolved
Clean oil from deck plates of main motor room prior to departing the port of Jacksonville.
Condition: Unknown
Due 9 November 1994
Resolved 9 November 1994
Construction/Loadline
Issued 7 October 1994 Resolved
Dewater main motor room. Cycle each sea valve in main motor room (open & close) in presence of attending Marine Inspector. Complete prior to departing port of Jacksonville.
Condition: Unknown
Due 9 November 1994
Resolved 9 November 1994
Construction/Loadline
Issued 7 October 1994 Resolved
Demonstrate proper operation of each bilge high level alarm throughout vessel prior to departing port of Jacksonville.
Condition: Unknown
Due 9 November 1994
Resolved 9 November 1994
Electrical
Issued 30 March 1994 Resolved
VSL IS PERMITTED TO OPERATE WITH A TEMPORARY GEN, BUT WILL HAVE TO KEEP A LIVE WATCH FOR THE TEMP GEN WHEN USED. THIS REQ'T IS IN FORCE UNTIL PERMANENT REAIRS COMPLETED ON ALL REQ'D GEN TO THE SATISFACTION OF A USCG INSPECTOR.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Unknown
Issued 30 March 1994 Resolved
PROVE PROPER OPERATION OF THE FORECASTLE SOUND POWERED TELEPHONE, NLT 30APR94.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Construction/Loadline
Issued 30 March 1994 Resolved
MAKE PERMANENT REPAIRS TO BLKHD IN VENT SPACE 01-102 WHERE CURRENTLY REPAIRED BY TEMPORARY MEANS AT NEXT DRYDOCKING, BUT NLT 31JUL94.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Electrical
Issued 30 March 1994 Resolved
PROVE PROPER OPERATION OF ALL ALARMS AND SHUTDOWNS FOR THE TURBINE GENERATOR, NLT 30APR94.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Engineering
Issued 30 March 1994 Resolved
MAKE PERMANENT REPAIRS TO F/O TANK #6 VENT APE IN LOWER E/R PORT SIDE, AT NEXT DRYDOCKING, NLT 31JUL94.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Unknown
Issued 30 March 1994 Resolved
PROVIDE CLOSURE FOR NAVO ELECTRIC SUPPLY ROOM VENT AT NEXT DRYCOCKING NLT 31JUL94.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Lifesaving
Issued 30 March 1994 Resolved
SERVICE LIFERAFTS NLT 31JUL94.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Electrical
Issued 30 March 1994 Resolved
PROVE PROPER VOLTAGE REGULATION FOR #3 SSDG IN SINGLE/PARALLEL OPERATION, NLT 30APR94.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Unknown
Issued 30 March 1994 Resolved
INSTALL VENT COVERS IN STATEROOMS WHERE MISSING AT NEXT DRYDOCKING, BUT NLT31JUL94.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Electrical
Issued 30 March 1994 Resolved
REPAIR/REPLACE GOVERNOR FOR #1, 2, & 3 SSDG AND PROVE PROPER OPERATION OF THE SPEED CONTROL AUTOMATICALLY IN SINGLE/PARALLEL OPERATION, NLT 30APR94.
Condition: Unknown
Due 30 March 1994
Resolved 30 March 1994
Lifesaving
Issued 14 October 1993 Resolved
PROVIDE [name withheld] WITH DOCUMENTATION PROVING LATEST LIFEBOAT FALLS INSTALLATION DATES._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 14 October 1993
Resolved 14 October 1993
Fire Fighting
Issued 23 May 1993 Resolved
PROPERLY INSTALL VENT EXHAUST MOTOR FOR AFT PAINT LOCKER AND PROVE PROPER OPERATION OF EMERGENCY SHUTDOWN TO SATISFACTION OF ATTENDING MARINE INSPECTOR.
Condition: Unknown
Due 23 May 1993
Resolved 23 May 1993
Lifesaving
Issued 23 May 1993 Resolved
PROVIDE [name withheld] WITH DOCUMENTATION PROVING LATEST LIFEBOAT FALLS INSTALLATION DATES.
Condition: Unknown
Due 14 June 1993
Resolved 14 June 1993
Electrical
Issued 23 May 1993 Resolved
IN PRESENCE OF A COAST GUARD MARINE INSPECTOR CONDUCT LOAD TEST AND PROVE PROPER OPERATION OF ALL SHUTDOWNS AND ALARMS ON #1 SSG.
Condition: Unknown
Due 23 May 1993
Resolved 23 May 1993
Documentation
Issued 23 May 1993 Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Condition: Unknown
Due 14 June 1993
Resolved 14 June 1993
Electrical
Issued 15 December 1992 Resolved
CLEAR GROUNDS ON MAIN SWITCH BOARD. _x001C_ _x001C_ _x001C_ _x001C_
Condition: Unknown
Due 23 December 1992
Resolved 1 February 1993
Lifesaving
Issued 11 May 1992 Resolved
HAVE BOTH REVERE L/R'S SERVICED AT FIRST PORT WITH APPD FACILITY L/R'S NOT TO BE USED AS PART OF PRIMARY LIFESAVING UNTIL SERVICED VSL RESTRICTED TO CARRY NOT MORE THAN 65 PERSONS UNTIL THIS REQT AND REQT E-10 IS MET.
Condition: Unknown
Due 27 August 1992
Resolved 27 August 1992
Fire Fighting
Issued 11 May 1992 Resolved
REPLACE BOTH PULL BOXES FOR FIXED FIRE EXTINGUISHING SYSTEMS FOR FLAMMABLE LIQUID STORES COMPT 2-6-0 & 1-4-1.
Condition: Unknown
Due 24 July 1992
Resolved 24 July 1992
Fire Fighting
Issued 11 May 1992 Resolved
REPLACE SPRAY TIPS IN FIRE HOSE NOCZZELS WITH APPROVED TYPES. (ALL 1 1/2" NOZZELS AND 13 OF THE 2 1/2 NOZZELS).
Condition: Unknown
Due 24 July 1992
Resolved 24 July 1992
Engineering
Issued 11 May 1992 Resolved
PROVIDE NEW APPROVED OR MAKE REPAIRS IAW NVIC 1-71 TO AFT BOILER SAFETY VALVE. BOILER NOT TO BE USED UNTIL THIS ITEM IS CORRECTED.
Condition: Unknown
Due 11 May 1992
Resolved 11 May 1992
Electrical
Issued 11 May 1992 Resolved
PROVE PROPER OPERATION OF ELECTRIC SUB PUMP IN MSD SPACE.
Condition: Unknown
Due 24 July 1992
Resolved 24 July 1992
Engineering
Issued 11 May 1992 Resolved
REPLACE MISSING LAGGING ON MAIN STEAM LINE ON AFT BOILER.
Condition: Unknown
Due 24 July 1992
Resolved 24 July 1992
Engineering
Issued 11 May 1992 Resolved
MAKE PERMANENT REPAIRS TO AFT BOILER FURNACE WHERE COMBUSTION FUMES ARE LEAKING.
Condition: Unknown
Due 24 July 1992
Resolved 24 July 1992
Lifesaving
Issued 11 May 1992 Resolved
PROVIDE APPVD 15 MAN INFLATABLE L/R TO REPLACE CONDEMNED ONE VSL RESTRICTEDTO CARRYING NOT MORE THAN 65 TOTAL PERSONS UNTIL THIS RQMNT AND REQT D-3 ISMET.
Condition: Unknown
Due 24 July 1992
Resolved 24 July 1992
Electrical
Issued 11 May 1992 Resolved
PROVIDE UP TO DATE ACCURATE LISTING OFF ALL ELECTRIC PANELBOARD EQUIPMENT FOR ALL PANELBOARDS THROUGHOUT VSL.
Condition: Unknown
Due 11 May 1992
Resolved 11 May 1992
Fire Fighting
Issued 11 May 1992 Resolved
REPLACE OR HYDRO TEST PORTABLE CO2 FIRE EXTINGUISHER AS PER SHIP RECORDS (APPROX 15 BOTTLES).
Condition: Unknown
Due 11 May 1992
Resolved 11 May 1992
Engineering
Issued 19 May 1990 Resolved
EFFECT PERMANENT REPAIRS TO #1 AND #2 AUXILIARY BOILER EXHAUST GAS LEAKS AT THE CASINGS.
Condition: Unknown
Due 19 May 1990
Resolved 19 May 1990
Engineering
Issued 18 May 1990 Resolved
EFFECT REPAIRS TO #1 AND #2 AUXILIARY BOILER EXHAUST GAS LEAKS AT THE CASINGS. BOILERS NOT TO BE OPERATED UNTIL REPAIRS ARE COMPLETE AND TESTED BY CG MARINE INSPECTOR.
Condition: Unknown
Due 18 May 1990
Resolved 18 May 1990
Construction/Loadline
Issued 15 May 1990 Resolved
MAKE ACCESSIBLE FOR INSPECTION THE PORTION OF THE AFT PEAK TANK, AFT OF THERUDDER POST.
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
PROPERLY STRAP UP WIRING IN OVERHEAD ON MAIN DECK STBD SIDE.
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
RENEW CABLE TO #3 GEN SOLENOID LUBE OIL TO GOVERNOR OR OPEN FOR INSPECTION OF WIRES.
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
REMOVE HANGING LIGHT CIRCUIT OVER 60KW GEN.. WAS A HEAT LAMP,.....
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
RTEMOVE HEAT LAMPS TO PUMPS IN ENG RM L/L AFT
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
COVER ELECTRIC WATER CONNECTION BOX
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
PROVIDE GLOBES AND GUARDS IN STEERING COMP AND REEFER FLAT.
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Engineering
Issued 15 May 1990 Resolved
TEST AFTER BOILER RESET BUTTON WHEN PINNED SO IT WONT TURN.
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Engineering
Issued 15 May 1990 Resolved
OPEN BOILER VALVES (FIRST VALVES) FOR INSPECTION
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Engineering
Issued 15 May 1990 Resolved
COMPLETE INSTALLATION OF THE FWD BOILER FEED PUMP (LOWER LEVEL).
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
PROPERLY REPAIR GAS TURBINE EXHAUST DRAIN
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
COMPLETE BOLTING OF THE GAS TURBINE RADIATOR BRACKETS..
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Engineering
Issued 15 May 1990 Resolved
LABEL REACH RODS FOR FUEL VALVES ON MAIN DECK
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Engineering
Issued 15 May 1990 Resolved
REPAIR KING GAGE FOR OIL BILGE TANK IN ENG ROOM LOWER LEVEL AFT
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
PROVIDE OPERABLE AMP METER FOR THE 40KW GEN ALARM CIRCUIT BATTERY CHARGER
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Fire Fighting
Issued 15 May 1990 Resolved
PROVIDE 2 SCBA'S FOR FIREMAN OUTFIT
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Engineering
Issued 15 May 1990 Resolved
PROVIDE FIXED OR 5 GALLON PORTABLE CONTAINMENT AT EACH FUEL OIL OR BULK LUBRICATING OIL TANK VENT DURING BUNKERING OPERATIONS.
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Engineering
Issued 15 May 1990 Resolved
REPLACE FLAME SCREENS IN FUEL OIL TANK VENTS 01-54-1 AND 01-76-1
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Accommodation/Occupational Safety
Issued 15 May 1990 Resolved
PROVIDE STEEL COVER AND GASKET FOR VENT IN AFT PAINT LOCKER
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Accommodation/Occupational Safety
Issued 15 May 1990 Resolved
PROVIDE CLOSURE DEVICES FOR OUTSIDE VENTS ABOVE AFT PAINT LOCKER DOOR
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Accommodation/Occupational Safety
Issued 15 May 1990 Resolved
PROVIDE CLOSURE DEVICES AND GASKET MATERIAL FOR INTAKE SUPPLY SYSTEM VENT ADJACENT TO AFT PAINT LOCKER DOOR.
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
REPAIR, REPLACE OR REMOVE BOW SOUND POWER PHONE STATION
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Lifesaving
Issued 15 May 1990 Resolved
PROVIDE NEW EPIRB BATTERY
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Electrical
Issued 15 May 1990 Resolved
PROVIDE COVERS FOR FLOURESCENT LIGHTS OVER MSD TANK (2)
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Engineering
Issued 15 May 1990 Resolved
TESR FWD BOILER DRAFT SWITCH, HIGH PRESSURE CUT OUT, ALARM AND MAIN DECK TRIP CIRCUIT.
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Engineering
Issued 15 May 1990 Resolved
TEST AFTER BOILER DRAFT SWITCH, HIGH PRESSURE CUT OUT, ALARM, ATOMIZING AIR PRESSURE SWITCH, AND MAIN DECK TRIP.
Condition: Unknown
Due 15 May 1990
Resolved 15 May 1990
Lifesaving
Issued 26 October 1989 Resolved
DAMAGE PORT A STRAKE
Condition: Unknown
Due 26 October 1989
Resolved 26 October 1989
Lifesaving
Issued 18 September 1989 Resolved
#2L/B REMOVE AND REPAIR DAMAGE FORWARD PORT QUARTER STRAKES.
Condition: Unknown
Due 18 September 1989
Resolved 18 September 1989
Electrical
Issued 27 May 1988 Resolved
MAKE TESTS TO THE SOLAR GAS TURBINE GENERATOR - OVER SPEED TRIP - LOW LUBE OIL AND OTHER MFG REQUIRED TESTS
Condition: Unknown
Due 27 May 1988
Resolved 27 May 1988
Lifesaving
Issued 20 November 1987 Resolved
PROPERLY REPAIR THE DAMAGED RIVETS AND PLATES ON THE STARBOARD LIFEBOAT, PORT SIDE APPROXIMATELY FOUR FEET FORWARD OF THE STERN. REPAIRS SHOULD BE IN ACCORDANCE WITH NVIC 2-63.
Condition: Unknown
Due 20 November 1987
Resolved 20 November 1987
Documentation
Issued 9 May 1986 Resolved
UPDATE STABILITY LETTER
Condition: Unknown
Due 9 May 1986
Resolved 9 May 1986
Engineering
Issued 9 May 1986 Resolved
MAKE OPERATIONAL STARBOARD MAIN ENGINE/GENERATOR
Condition: Unknown
Due 9 May 1986
Resolved 9 May 1986
Lifesaving
Issued 3 April 1985 Resolved
THE VESSEL'S LIFERAFTS ARE TO BE SERVICED IN ACCORDANCE WITH 46 CFR 160.051-6. A COAST GUARD MARINE INSPECTOR SHALL WITNESS THE SERVICING.
Condition: Unknown
Due 3 April 1985
Resolved 3 April 1985

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.