Inspection history · 10
11 September 2024
In-Service Inspection
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 8000579
25 November 2019
Drydock Exam · Internal Structural Exam
Physical examination · Sector Jacksonville · USCG Southeast District (CGD-SE) · Activity 6862254
31 October 2019
Administrative Inspection
Administrative · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 6846591
23 September 2019
Administrative Inspection
Administrative · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 6818484
8 May 2019
In-Service Inspection · Inclining Experiment
Physical examination · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 6680220
17 January 2019
Annual Inspection · DAPI Audit
Physical examination · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 6611843
27 August 2018
In-Service Inspection
Physical examination · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 6524172
25 August 2018
Type not recorded
No type recorded · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 6528556
23 July 2018
In-Service Inspection
Physical examination · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 6504849
10 February 2016
Internal Structural Exam · COI Inspection · Drydock Exam · Deficiency Check
Physical examination · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 5812920
03 - Water/Weathertight Conditions › N/A - No Subsystem › Doors
Issued 8 May 2019
No resolution recorded
Install proper height sills at both aft main deck doors IAW 46 CFR 179.380(d)(1) NLT next scheduled dry docking.
Action required: 705 - Other - as specified
Due 31 October 2019 — due date passed with no resolution recorded
03 - Water/Weathertight Conditions › N/A - No Subsystem › Ventilators, air pipes, casings
Issued 8 May 2019
No resolution recorded
Make all main deck gooseneck vents available for inspection, including ball check valves at next scheduled dry docking.
Action required: 705 - Other - as specified
Due 31 October 2019 — due date passed with no resolution recorded
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 17 January 2019
Resolved
Provide lifejacket donning placard at passenger muster area.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
03 - Water/Weathertight Conditions › N/A - No Subsystem › Windows, sidescuttles and deadlights
Issued 17 January 2019
Resolved
Renew cracked starboard side bridge window.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
03 - Water/Weathertight Conditions › N/A - No Subsystem › Bulwarks and freeing ports
Issued 17 January 2019
Resolved
Make watertight hatch to chain locker operable.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 17 January 2019
Resolved
Renew control wiring to steering where damaged due to heat in steering compartment.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 17 January 2019
Resolved
Identify cause of fuel leak on starboard generator and repair.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 17 January 2019
Resolved
Properly lag exahaust manifolds for both SSDG's
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
03 - Water/Weathertight Conditions › N/A - No Subsystem › Ventilators, air pipes, casings
Issued 17 January 2019
Resolved
Remove drain hose from engine room exhaust louver.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 17 January 2019
Resolved
Remount bilge alarm in shaft alley.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 17 January 2019
Resolved
Renew wasted hydraulic hose for steering gear.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 17 January 2019
Resolved
Identify cause of erratic steering and repair.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 February 2019
Resolved 21 February 2019
Resolution: corrected
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 27 August 2018
Resolved
Determine cause of power and propulsion failure and demonstrate proper opertion of both to the satisfaction of the attending CG Marine Inspector prior to operating.
Action required: 701 - Prior to carriage of passengers/cargo
Due 27 August 2018
Resolved 27 August 2018
Resolution: Corrected - see narrative
Documentation › Certificates/Documents › Certificate of Documentation (CG-1270)
Issued 10 February 2016
Resolved
Provide COD, drug testing info, CPR cards, and masters license prior to operating.
Action required: 705 - Other - as specified
Due 23 October 2017
Resolved 5 December 2017
Resolution: Cleared
Documentation › Markings/Placards › Warning Signs
Issued 10 February 2016
Resolved
Provide emergency instructions and post prior to operating.
Action required: 705 - Other - as specified
Due 23 October 2017
Resolved 5 December 2017
Resolution: Cleared
Operations/Management › Drills/Instruction › Abandon Ship
Issued 10 February 2016
Resolved
Conduct fire and man overboard drills prior to operating.
Action required: 705 - Other - as specified
Due 23 October 2017
Resolved 5 December 2017
Resolution: Cleared
Electrical › Electric Generation Source (service) › Generator
Issued 10 February 2016
Resolved
Install ammeters for generators.
Action required: 705 - Other - as specified
Due 31 December 2017
Resolved 4 January 2018
Resolution: corrected
Accommodation/Occupational Safety › Occupational Safety › Rubbish/Waste Materials
Issued 10 February 2016
Resolved
Remove excessive paint from vessel and stow all loose gear prior to operating.
Action required: 705 - Other - as specified
Due 23 October 2017
Resolved 5 December 2017
Resolution: Corrected
Engineering › Diesel Engine (propulsion-reduction gear) › Cylinder
Issued 10 February 2016
Resolved
Prove proper operation of main engine temperature gauge at operators station prior to operating.
Action required: 705 - Other - as specified
Due 23 October 2017
Resolved 5 December 2017
Resolution: Corrected
Electrical › Electric Generation Source (service) › Generator
Issued 10 February 2016
Resolved
Prove proper operation of SSDG#1 under load as generator was noted to be running at excessive temperatures nearing its alarm point. Prior to operating.
Action required: 705 - Other - as specified
Due 23 October 2017
Resolved 5 December 2017
Resolution: Corrected
Engineering › Shafting/Propeller Arrangements › Bearing
Issued 10 February 2016
Resolved
Secure excessive leaking from shaft packing gland prior to operating.
Action required: 705 - Other - as specified
Due 23 October 2017
Resolved 5 December 2017