Inspection history · 44
1 March 1992
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 78290
27 April 1990
Administrative
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1231267
24 January 1990
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1211421
10 November 1989
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1243241
31 October 1989
Permit to Proceed
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1233198
30 September 1989
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1333749
29 September 1989
Damage Survey
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1331105
28 September 1989
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 437116
16 September 1989
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 481207
28 February 1989
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1202813
24 February 1989
Permit to Proceed
Administrative · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1351324
2 February 1989
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 510270
15 September 1988
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1194198
13 September 1988
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1195466
8 September 1988
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1040430
23 August 1988
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 524979
27 April 1988
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 487600
7 January 1988
Deficiency Check
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1316568
1 January 1988
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 537645
1 January 1988
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1315499
6 November 1987
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1021524
28 October 1987
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 535806
15 October 1987
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1327642
12 October 1987
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1322329
17 September 1987
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 462594
19 July 1987
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1336402
14 July 1987
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1016623
8 July 1987
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 478647
4 November 1986
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1022652
19 October 1986
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 443865
4 August 1986
Examination of Repairs
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1310961
1 August 1986
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 987898
11 June 1986
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 539045
10 March 1986
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 474299
27 November 1985
Examination of Repairs
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 994387
13 November 1985
Permit to Proceed
Administrative · MSO Mobile · USCG Heartland District (CGD-H) · Activity 993371
8 November 1985
Credit Drydock · COI Inspection
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1301690
23 March 1985
Type not recorded
No type recorded · MSO Mobile · USCG Heartland District (CGD-H) · Activity 1286510
9 November 1984
Type not recorded
No type recorded · MSO Mobile · USCG Heartland District (CGD-H) · Activity 1283580
30 October 1984
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 975125
18 October 1983
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 965974
28 March 1983
Type not recorded
No type recorded · MSO Mobile · USCG Heartland District (CGD-H) · Activity 1276658
17 January 1983
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 965314
27 October 1982
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1275969
Construction/Loadline
Issued 29 September 1989
Resolved
MAKE PERMANENT REPAIRS TO CRACKS AT THE PORT AFT BOTTOM CORNER WRAPPER AND THE PORT AFT CORNER DOUBLER PLATE PRIOR TO CARRYING CARGO. MAINTAIN TEMPORARY REPAIRS TO CRACKS UNTIL PERMANENT REPAIRS.
Condition: Unknown
Due 29 September 1989
Resolved 29 September 1989
Construction/Loadline
Issued 8 September 1988
Resolved
REPAIR/RENEW BROKEN/MISSING HATCH DROP-BOLTS ON FOLLOWING CARG TANK HATCHES1,2,3 & 4 STBD AND 4 PORT.
Condition: Unknown
Due 8 September 1988
Resolved 8 September 1988
Construction/Loadline
Issued 8 September 1988
Resolved
DISCHARGE CARGO FROM ALL TANKS PRIOR TO DEPARTING CORPUS CHRISTI. MAKE PERMANENT REPAIRS TO TANK #5 STBD AT SHELL PLT. JUNCTION OF DECK AT AFT STBD BITT & 4' FWD OF AFT BITT 4" BELOW EDGE OF DECK. REPAIRS TO BE MADE TO BARGE UPON ARRIVAL HOUSTON, TX.
Condition: Unknown
Due 8 September 1988
Resolved 8 September 1988
Construction/Loadline
Issued 8 September 1988
Resolved
FREE-UP BOW RAKE WT HATCH SO IT CAN BE CLOSED & DOGGED
Condition: Unknown
Due 8 September 1988
Resolved 8 September 1988
Construction/Loadline
Issued 1 January 1988
Resolved
PRIOR TO LOADING NEXT CARGO & IN ANY CASE NLT 15JAN88, EFFECT PERMANENT REPAIRS TO 6" CRACK ON DECK KNUCKLE, #1P COT. MAINTAIN TEMPORARY PATCH UNTIL PERMANENT REPAIRS ARE EFFECTED. REPAIRS TO BE TO SAT OF COG OCMI.
Condition: Unknown
Due 1 January 1988
Resolved 1 January 1988
Unknown
Issued 12 October 1987
Resolved
PROVIDE A PROPER WARNING SIGN.
Condition: Unknown
Due 12 October 1987
Resolved 12 October 1987
Unknown
Issued 12 October 1987
Resolved
DISCHARGE CARGO. PRIOR TO LOADING NEXT CARGO MAKE PERMANENT REPAIRS TO THEFRATURE #5 STARBOARD CARGO TANK, SIDE SHELL, 3 FEET FROM DECK KNUCKLE.
Condition: Unknown
Due 12 October 1987
Resolved 12 October 1987
Unknown
Issued 12 October 1987
Resolved
MAKE PERMANENT REPAIRS TO THE PORT AFT MOORING BIT.
Condition: Unknown
Due 12 October 1987
Resolved 12 October 1987
Deck/Cargo
Issued 14 July 1987
Resolved
PROCEED TO HOUSTON TX., DISCHARGE CARGO,THEN PROCEED TO REPAIR FACILITY, AIR TEST #5 STBD CARGO TANK, AND MAKE PERMANENT REPAIRS TO PINHOLE LEAK.
Condition: Unknown
Due 14 July 1987
Resolved 14 July 1987
Construction/Loadline
Issued 14 July 1987
Resolved
MAKE REPAIR TO STBD AFT CLEAT BY NEXT DRYDOCK.
Condition: Unknown
Due 14 July 1987
Resolved 14 July 1987
Deck/Cargo
Issued 1 August 1986
Resolved
MAKE PERMENANT REPAIRS TO CARGO PUMP MUFFLER IN WAY OF WASTED TAILPIECE TO PREVENT MUFFLER FROM EMITTING SPARKS.
Condition: Unknown
Due 1 August 1986
Resolved 1 August 1986
Construction/Loadline
Issued 23 March 1985
Resolved
MAKE TEMPORARY REPAIRS TO #5 STBD CARGO TANK DECK KNUCKLE IN WAY OF 6" CRACK PRIOR TO GETTING UNDERWAY. CARGO IS ONLY PERMITTED TO BE LOADED NO MORE THAN 24" BELOW THE CARGO EXPANSION TANK OF THE #5 STBD CARGO TANK UNTIL PERMANENT REPAIRS ARE COMPLETED.
Condition: Unknown
Due 23 March 1985
Resolved 23 March 1985
Construction/Loadline
Issued 23 March 1985
Resolved
MAKE PERMANENT REPAIRS TO STBD DECK KNUCKLE IN WAY OF THE #5 STBD CARGO TANK IN A AREA CRACKED APPROXIMATL 6" IN LENGTH. REPAIRS ARE TO MADE DURINGTHE NEXT DRYDOCKING AND IN NO CASE LATER THAN 18 OCTOBER 1985. ALL ITEMS ARE TO BE COMPLETED TO THE SATISFACTION OF THE COGNIZANT OCMI.
Condition: Unknown
Due 23 March 1985
Resolved 23 March 1985
Construction/Loadline
Issued 9 November 1984
Resolved
CROP AND RENEW A MINIMUM OF ONE(1) FRAME SPACE THE STBD DECK KNUCKLE IWO THE A #2/3 CARGO TANK BULKHEAD.
Condition: Unknown
Due 9 November 1984
Resolved 9 November 1984
Construction/Loadline
Issued 9 November 1984
Resolved
CROP AND RENEW THE DECK KNUCKLE AND THE STARBOARD PUSHING PAD ON THE AFT RAKE END.
Condition: Unknown
Due 9 November 1984
Resolved 9 November 1984
Unknown
Issued 9 November 1984
Resolved
CARGO IS ONLY PERMITTED TO BE LOADED NO MORE THAN 24 IN. BELOW THE CARGO EXPANSION TRUNK OF THE #2 STBD CARGO TANK UNTIL PERMANENT REPAIRS ARE COMPLETED.
Condition: Unknown
Due 9 November 1984
Resolved 9 November 1984
Deck/Cargo
Issued 27 October 1982
Resolved
MAKE REPAIRS TO HANDWHEEL ON NO.1 PORT CARGO TANK REACH ROD AT THE NEXT REGULAR GAS FREEING, BUT IN NO CASE LATER THAN 04NOV83.
Condition: Unknown
Due 27 October 1982
Resolved 27 October 1982