MAURY USCG vessel records Sign in
← All vessels

FAIRWEATHER EXPRESS

FAIRWEATHER EXPRESS is a 1996 passenger vessel (inspected). The Coast Guard has recorded 69 inspections since 1996, most recently in April 2026, along with 132 deficiencies and 1 casualty investigation in 2002.

Records from 1996 to 2026. Most recent: inspection, 28 April 2026.

Built
1996
Last inspected
28 April 2026
Documentation
Valid · documentation file of 10 September 2026
Controls
None recorded without a removal date

Identity

WDC9484
436366
Flag
UNITED STATES
367102890
Maury page id
psix-436366

Inspections, by type

…with no type recorded3
Years with a record 28 calendar years (1996–2026)
The 69 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 1977.

Documentation record

Registered dimensions (L × B × D)78.5 ft × 28.5 ft × 8.3 ft
Registered tonnagegross 91 / net 73
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderALLEN MARINE, INC. · SITKA, AK, UNITED STATES · built 1996
Hull materialAluminum
PropulsionJet Drive
Hull shapeNot recorded
Hull configurationTwin Hull
Hailing portJUNEAU, AK
Trade endorsementsCoastwise, unrestricted, Recreational, Registry
DocumentationValid · issued 12 May 2026 · expires 31 May 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it91 - Simplified, Gross Ton
73 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.

Radio station licence

WDC9484MMSI 367102890 · active · voluntarily equipped · granted 4 February 2026, expires 29 March 2036
WCW3817MMSI not assigned · expired · compulsorily equipped · granted 29 March 1996, cancelled 3 June 2006 · licensed under a name not among this hull’s recorded names (not shown)
FCC Universal Licensing System ship-station file of 6 September 2026, matched to this hull on its US Official Number. Status and dates are the file’s own. The licensee is not read from the file and is not shown. A lapsed licence’s MMSI is still the number the vessel transmitted under while it was valid.

Inspection history · 69

28 April 2026 Annual Inspection · Internal Structural Exam
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 8354701
10 April 2026 Internal Structural Exam · Hull Examination
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 8346031
15 April 2025 In-Service Inspection · Annual Inspection · Deficiency Check · Internal Structural Exam
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 8101528
29 April 2024 Internal Structural Exam · Annual Inspection · Administrative Inspection · Deficiency Check
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7904328
15 November 2023 Internal Structural Exam · Drydock Exam
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 7827889
17 June 2023 Damage Survey
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7716792
13 April 2023 Deficiency Check · Internal Structural Exam · Administrative Inspection · COI Inspection · In-Service Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7662873
5 April 2022 Annual Inspection · Deficiency Check
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7425426
28 March 2022 Deficiency Check · Internal Structural Exam · Hull Examination
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7428789
20 April 2021 Internal Structural Exam · Administrative Inspection · Annual Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7178998
29 December 2020 Deficiency Check
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7117567
14 October 2020 Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7077105
17 September 2020 Deficiency Check
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 7061073
6 May 2020 Deficiency Check · Annual Inspection · Administrative Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6948286
12 February 2020 Internal Structural Exam · Drydock Exam · Deficiency Check · Administrative Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6910975
27 June 2019 Deficiency Check
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6830635
25 April 2019 Internal Structural Exam · Annual Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6666313
10 September 2018 Deficiency Check
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6537474
5 June 2018 Deficiency Check
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6441535
26 April 2018 DAPI Audit · COI Inspection
Physical examination · Marine Safety Detachment Sitka · USCG Arctic District (CGD-A) · Activity 6399929
19 April 2018 Internal Structural Exam · Examination of Repairs · Hull Examination
Physical examination · Marine Safety Detachment Sitka · USCG Arctic District (CGD-A) · Activity 6395803
10 May 2017 Deficiency Check · Examination of Repairs · Annual Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6115484
23 March 2017 Administrative Inspection · Damage Survey
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 6111207
20 April 2016 Annual Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 5858799
14 April 2016 Damage Survey
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 5855040
29 March 2016 Hull Examination · Internal Structural Exam
Physical examination · Marine Safety Detachment Sitka · USCG Arctic District (CGD-A) · Activity 5843232
2 November 2015 Administrative Inspection · Deficiency Check
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 5755988
22 May 2014 Administrative Inspection · In-Service Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 4863452
5 March 2014 Plan Review "T" Boat · Administrative Inspection
Administrative · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 4810780
2 December 2011 Damage Survey · Examination of Repairs
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 4217004
22 April 2009 Annual Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 3458503
8 April 2009 Internal Structural Exam · Hull Examination
Physical examination · Marine Safety Detachment Sitka · USCG Arctic District (CGD-A) · Activity 3448851
29 July 2008 Deficiency Check
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 3283582
7 April 2008 COI Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 3179457
13 March 2008 Internal Structural Exam · Hull Examination
Physical examination · Marine Safety Detachment Sitka · USCG Arctic District (CGD-A) · Activity 3163782
7 September 2007 Examination of Repairs
Physical examination · Marine Safety Detachment Sitka · USCG Arctic District (CGD-A) · Activity 3054480
4 September 2007 Damage Survey
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 3049046
9 April 2007 Annual Inspection
Physical examination · Sector Southeast Alaska · USCG Arctic District (CGD-A) · Activity 2905082
15 May 2006 Annual Inspection
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 2646084
19 April 2006 Hull Examination · Internal Structural Exam
Physical examination · Sector Puget Sound · USCG Northwest District (CGD-NW) · Activity 2626764
13 May 2005 Annual Inspection
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 2359363
25 March 2005 Internal Structural Exam · Hull Examination
Physical examination · MSD SITKA · USCG Arctic District (CGD-A) · Activity 2324873
13 October 2004 Administrative Inspection
Administrative · Marine Safety Center (MSC) · Activity 2219836
4 October 2004 Administrative Inspection
Administrative · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 2213066
2 August 2004 Administrative Inspection · Deficiency Check
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 2153887
12 July 2004 Annual Inspection
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 2132780
12 May 2004 Security Inspection
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 2074242
6 May 2004 Security Inspection
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 2064026
28 April 2004 Damage Survey
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 2058236
22 December 2003 Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1970885
21 May 2003 Type not recorded
No type recorded · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 1803932
21 May 2003 Type not recorded
No type recorded · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 1803950
12 April 2003 COI Inspection
Physical examination · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 1769601
28 March 2003 Hull Examination
Physical examination · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 1766057
6 August 2002 Type not recorded
No type recorded · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 1799322
22 April 2002 Internal Structural Exam · Hull Examination
Physical examination · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 1605931
5 October 2001 Administrative
Administrative · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 1074494
30 March 2001 Re-Inspection · Examination of Repairs
Physical examination · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 1387018
30 August 2000 Administrative
Administrative · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 1053847
24 April 2000 Deficiency Check
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 1048702
17 April 2000 Re-Inspection
Physical examination · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 1393405
11 April 2000 Administrative
Administrative · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 816494
6 March 2000 Hull Examination
Physical examination · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 1465537
6 August 1999 Administrative
Administrative · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 775600
21 April 1999 COI Inspection
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 1360826
4 March 1998 Hull Examination · Re-Inspection
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 1441351
10 April 1997 Re-Inspection · MARPOL Annex V Examination
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 1377998
23 April 1996 Deficiency Check
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 1090352
18 April 1996 MARPOL Annex I Examination · Plan Review "T" Boat · Initial Certification · Hull Examination
Physical examination · MSO JUNEAU · USCG Arctic District (CGD-A) · Activity 1080951

Deficiency record · 132

02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 15 April 2025 Resolved
At each inspection all observed unsafe practices, fire hazardous siturations must be corrected and all protective devices must be in satisfactory condition. Battery lug protection missing in port engine room at alternator breaker. 46 CFR 176.830
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 April 2025
Resolved 29 April 2025
Resolution: Lugs protected
05 - Radio Communications › N/A - No Subsystem › VHF EPIRB
Issued 15 April 2025 Resolved
To enhance protection of life and property it is amandatory that each 406.0 - 406.1 MHz EPIRB must be registered with NOAA before installation and that information be kept up-to-date. Provide updated registration document and sticker to attending marine inspector. 46 CFR 80.1059(F)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 April 2025
Resolved 22 April 2025
Resolution: Cleared to satisfaction of attending Marine Inspector
05 - Radio Communications › N/A - No Subsystem › VHF EPIRB
Issued 15 April 2025 Resolved
Each EPIRB, other than an EPIRB in an inflatable liferaft must be tested monthly, using integrated test circuit and output indicatior. to determine that is is operative. The EPORB test required by paragraph (a) shall be logged or otherwise documenbted, as applicable. To be renewed at next annual inspection. 46 cfr 185.728(a)(c)
Action required: 705 - Other - as specified
Due 15 April 2025
Resolved 22 April 2025
Resolution: Vsl provided EPIRB log
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 15 April 2025 Resolved
The employer shall provide an employee assistance program (EAP) for all crew members. The employer may establish the EAP as a part of its internal personnel services or the employer may contract with an entity that with provide EAP servies to a crew member. Supervisory personnel must receive at least 60 minutes of training. Conduct EAP training for newly reporting crew members. 46 CFR16.401
Action required: 705 - Other - as specified
Due 15 April 2025
Resolved 30 April 2025
Resolution: Provided proof of EAP training to attending Marine Inspector
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 15 April 2025 Resolved
No marine employer may engage or employ any individual to serve as a crewmember unless the individual passes a chemical test for dangerous drugs for that employer. Provide evidence of all crew members enrolled in a chemical testing consortium. 46 CFR 16.210
Action required: 705 - Other - as specified
Due 30 April 2025
Resolved 29 April 2025
Resolution: Provided evidence of consortium testing.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 15 April 2025 Resolved
Machinery and equpment installed on each vessel must be suitable for the vessel and its operation and for the purpose intended and must be installled and maintained in such a mannner as to afford adequate protection from causing machinery failure, and personnel injury. Port aft main engine exhaust supported with zip-ties. Make repairs to return to as-designed condition. 46 CFR 182.100
Action required: 705 - Other - as specified
Due 30 April 2025
Resolved 30 April 2025
Resolution: Repaired as required to satisfaction of attending Marine Inspector
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 15 April 2025 Resolved
The construction and arrangement of a vessel must allow the safe operation of the vessel in accordance with the terms of its COI given consideration to provisions for guards and rails in hazardous places for passengers and crew. Repair cracked railing base at port side forward embarkation station. 46 CFR 177.100
Action required: 705 - Other - as specified
Due 30 April 2025
Resolved 29 April 2025
Resolution: Railing repaired
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 29 April 2024 Resolved
Exhaust piping shall be led to the point of escape with a minimum number of bends or elbows. It shall be gastight throughout its length and shall be properly supported by non-combustible hangers or blocks. MI identified exhaust leak (ivo water cooling injection) on port side aft engine. 46CFR182.15-20(a)
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 April 2024
Resolution: Alignment of spray ring pushed the exhaust gasket, causing exhaust leak. Exhaust and spray ring was properly re-aligned.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 29 April 2024 Resolved
All electrical installations shall be to the sat- isfaction of the Officer in Charge, Marine Inspection. Multiple electrical wires on upper deck engine room are not properly spliced, outlet cover at operating station is not covered, secure loose wire on generator. 46CFR183.01-15
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 April 2024
Resolution: E/R electrical - spliced wires were connected with marine type butt connectors and heat shrink was applied over connectors. Speaker wire ends on pax deck were heat shrunk and stowed away from pax. Ops station electrical outlet was covered.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 29 April 2024 Resolved
Propulsion machinery shall be suitable in type and design for propulsion requirements of the hull in which it is installed and capable of operating at constant marine load under such requirements without exceeding its designed limitations. Excessive oil leak observed on stbd aft main engine. 46CFR182.05-1
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 April 2024
Resolution: Oil leak was an oring that was replaced on the front of the thermostat plate of the oil cooler. Identified oring was pinched and not correctly placed in grove. Oring was replaced. Engine tested; all sat.
11 - Life Saving Appliances › N/A - No Subsystem › Inflatable liferafts
Issued 29 April 2024 Resolved
Each disposable hydrostatic release unit must be marked with an expiration date of two years after the date on which the unit is installed. HRU is not marked properly. 46CFRR185.740(b)
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 April 2024
Resolution: Hydrostatic unit was replaced.
14 - Pollution Prevention › 144 - MARPOL Annex IV (Not Applicable to PSC Exams conducted in the U.S.) › Sewage treatment plant
Issued 29 April 2024 Resolved
For items not covered by standards in this subchapter, inspection shall be in accordance with standards acceptable to the Officer in Charge, Marine Inspection, as good marine practice. Bathroom plumbing not connected to MSD. Reconnect and secure bathroom if not in use. 46CFR176.25-1(a)
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 April 2024
Resolution: Sewage line was re-connected to head.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 29 April 2024 Resolved
Protection from mechanical damage shall be specially considered. Protective covering or shields shall be installed to the satisfaction of the Officer in Charge, Marine Inspection. Multiple hoses (fuel, lube, fire main, and bilge) are positioned over internal framing causing damage to hoses. Place chaffing gear on hoses to prevent further damage. To be corrected within seven days. 46CFR182.40-1(a)(2)
Action required: 705 - Other - as specified
Due 6 May 2024
Resolved 23 May 2024
Resolution: Chaffing gear placed in between vital system hoses and vessel framing.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 29 April 2024 Resolved
For items not covered by standards in this subchapter, inspection shall be in accordance with standards acceptable to the Officer in Charge, Marine Inspection, as good marine practice. Stbd bilge discharge and port side engine room raw water flexible hose is cracked. Replace hose. 46CFR176.25-1(a)
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 10 May 2024
Resolution: Hoses replaced.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 29 April 2024 Resolved
Suitable covers, guards, or rails shall be installed in way of all exposed and hazardous places such as gears, machinery, etc. Guards on port and stbd fwd engine is removed. 46CFR177.35-15
Action required: 10 - Deficiency Rectified
Resolved 29 April 2024
Resolution: Guard placed on port and stb fwd engines.
10 - Safety of Navigation › N/A - No Subsystem › Charts
Issued 13 April 2023 Resolved
As appropriate for the intended voyage, a vessel must carry adequate and up-to-date: Charts of large enough scale to make safe navigation possible, U.S. Coast Pilot [name withheld] List and Current tables. Current tables and CG Light List were missing. Paper chart, electronic charts and Coast Pilot were not up-to-date. Update/provide appropriate charts & nautical publications. 46 CFR 184.420
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 26 April 2023
Resolution: Operator updated all charts and pubs to 2023 - all sat.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 13 April 2023 Resolved
Each item of lifesaving equipment with an expiration date must be replaced during the annual inspection and repair if the expiration date has passed. Waterlight battery for the ring life buoy outside the pilothouse was expired. Replace battery. 46 CFR 185.726(c)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 26 April 2023
Resolution: Operator replaced the battery with a new proper type battery - all sat.
11 - Life Saving Appliances › N/A - No Subsystem › Launching arrangements for survival craft
Issued 13 April 2023 Resolved
Each survival craft on a vessel must be ready for immediate use before the vessel leaves port and at all times when the vessel is underway. All 04 inflatable rafts were outfitted with hydrostatic release units for "EPIRB use only". Replace each hydrostatic release unit prior to carrying passengers. 46 CFR 185.700
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 26 April 2023
Resolution: Operator replaced all expired hydrostatic release units with life raft units and marked new expiration dates - all sat.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 13 April 2023 Resolved
Each life jacket must be marked in clearly legible block capital letters with the vessel's name. Ten lifejackets had the wrong vessel name. Re-label correct name on each life jacket. 46 CFR 185.604
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 26 April 2023
Resolution: Operator stenciled vessels name onto the new lifejackets - all sat.
04 - Emergency Systems › N/A - No Subsystem › Muster list
Issued 13 April 2023 Resolved
The master and crew of a vessel will be familiar with the content of and have mounted at the operating station, emergency instructions containing the actions to be taken in the event of fire, heavy weather, or man overboard conditions. Emergency instructions were posted in the accommodation space but not at the operating station. Place instructions at the operating station. 46 CFR 185.510
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 26 April 2023
Resolution: Operator posted emergency instructions in the operating station - all sat.
05 - Radio Communications › N/A - No Subsystem › Satellite EPIRB 406MHz/1.6GHz
Issued 13 April 2023 Resolved
The name of the vessel must be marked or painted in clearly legible letters on each EPIRB. The vessel name and NOAA registration sticker were missing. Properly label EPIRB. 46 CFR 185.604 (c)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 26 April 2023
Resolution: Operator stenciled vessels name onto the EPIRB and placed the NOAA registration decal onto the same - all sat.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 13 April 2023 Resolved
At each inspection for certification, all observed fire hazards must be corrected. Unmounted space heater was being used on the bridge. Remove space heater. 46 CFR 176.830
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 26 April 2023
Resolution: Operator removed the space heater from the bridge - all sat.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 13 April 2023 Resolved
Unless other means are provided to ensure that a potential waste receptacle fire would be limited to the receptacle, waste receptacles must be constructed of noncombustible materials with no openings in the sides or bottom. Combustible waste receptacle being used on the bridge. Remove waste receptacle from the vessel. 46 CFR 177.405
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 26 April 2023
Resolution: Operator replaced the plastic garbage can with a metal can with a lid - all sat.
01 - Certificates & Documentation › 012 - Crew Certificates › Certificates for radio personnel
Issued 13 April 2023 Resolved
Each ship transporting more than 6 passengers for hire must carry a radio operator who meeting the following: where the station power does not exceed 250 watts carrier power or 1500 watts peak envelope power, a marine radio operator permit or higher class license. Master was unable to provide his marine radio operator permit at the time of inspection. Provide proof of valid permit. 47 CFR 80.159(e)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 26 April 2023
Resolution: Master had onboard his FCC Marine Radio Operator Permit - all sat.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 13 April 2023 Resolved
A hatch cover must: (1) Have securing devices; and (2) Be attached to the hatch frame or coaming by hinges, captive chains, or other devices of substantial strength to prevent its loss. The port side jet room hatch cover, the captive chain is broken. Repair or replace the captive chain for the hatch cover. 46 CFR 179.360
Condition: Damaged By Earlier Event
Action required: 16 - Rectify deficiencies w/in 14 days
Due 25 April 2023
Resolved 26 April 2023
Resolution: Operator replaced the broken captive chain on the port side jet room hatch cover - all sat.
09 - Working and Living Conditions › 092 - Working Conditions › Pipes, wires (insulation)
Issued 13 April 2023 Resolved
Protection against hot piping. Piping, including valves, pipe fittings and flanges, conveying vapor, gas, or liquid, the temperature of which exceeds 65.5 °C (150 °F), must be suitably insulated where necessary to prevent injuries. Repair or replace all missing or worn out exhaust lagging on all four main diesel engines. 46 CFR 177.970
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 26 April 2023
Resolution: Operator replaced all loose and missing exhaust lagging - all sat.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 13 April 2023 Resolved
A vessel is inspected for compliance with the standards required by this subchapter. Machinery, equipment, materials, and arrangements not covered by standards in this subchapter may be inspected in accordance with standards acceptable to the cognizant OCMI as good marine practice. The starboard jet room electric submersible bilge pump float switch is attached with a plastic wire tie. Properly mount bilge pump/alarm float switch iaw manufacturers instruction. 46 CFR 176.800
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 April 2023
Resolved 26 April 2023
Resolution: Operator mounted the float switch iaw mfr's instruction and tested - all sat.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Doors
Issued 29 April 2022 Resolved
The jetroom hatches port/starboard did not have anything attaching them to the vessel hull as required. Install mechanism to secure hatch to the vessel.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 21 June 2022
Resolution: The operator secured the hatches with suitable wire rope - all sat.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 29 April 2022 Resolved
Found 33 adult and 7 child lifejackets that needed repair or replacement. Vessel is limited to 120 adult passengers until lifejackets have been repaired or replaced.
Action required: 705 - Other - as specified
Resolved 21 June 2022
Resolution: The owner repaired or replaced the defective lifejackets - all sat.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Railing, gangway, walkway and means for safe passage
Issued 29 April 2022 Resolved
The aft lifelines between the house and the railing wre missing several courses. Replace missing lifelines the meet requirements.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 21 June 2022
Resolution: The owner replaced the missing lifelines - all sat.
05 - Radio Communications › N/A - No Subsystem › Satellite EPIRB 406MHz/1.6GHz
Issued 29 April 2022 Resolved
The hydrostatic release unit on the EPIRB was expired. Provide new valid hydrostatic release unit.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 21 June 2022
Resolution: The owner replaced the expired hydrostatic release for the EPIRB.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 29 April 2022 Resolved
The ring buoy on the upper deck aft had paint overspray on retroreflective material. Remove paint or renew retro material to original condition.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 21 June 2022
Resolution: The owner replaced the retro flective tape - all sat.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Doors
Issued 29 April 2022 Resolved
Ensure watertight condition of vessel. Below the main deck, a hose penetrates the aft engine room bulkhead into the jet room and in both vestibules port and starboard, the stuffing tubes penetrating the deck into the engine room were missing the packing material. Repair holes to ensure weathertightness.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 21 June 2022
Resolution: The owner renewed the packing in the stuffing tubes - all sat.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 29 April 2022 Resolved
A light fixture in the fwd part of port side engine room had bare conductors going into fixture and into the junction box. Ensure proper electrical cables are installed for light fixture.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 21 June 2022
Resolution: Operator emailed me photos showing new electrical conduit installed - all sat.
04 - Emergency Systems › N/A - No Subsystem › Means of communication between safety centre and other control stations
Issued 29 April 2022 Resolved
The upper starboard outdoor PA speaker was not operating as required. Install/repair speaker to original condition.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 21 June 2022
Resolution: Owner had a new speaker installed and tested - all sat.
02 - Structural Conditions › N/A - No Subsystem › Decks - cracking
Issued 28 March 2022 Resolved
Approximately 29" crack in the deck weld on the fore deck, 5 feet port of amidship. Gouge and reweld crack.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 7 April 2022
03 - Water/Weathertight Conditions › N/A - No Subsystem › Scuppers, inlets and discharges
Issued 28 March 2022 Resolved
An old discharge port was temporarily plugged. Remove old plug weld in insert.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 7 April 2022
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 20 April 2021 Resolved
The starboard e/r fuel return pipe at the fwd bulkhead has a minor fuel leak. Repair leak prior to departure from port.
Action required: 17 - Rectify deficiencies prior to departure
Due 20 April 2021
Resolved 7 April 2022
Resolution: Owner repaired fuel oil leak. All sat.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 20 April 2021 Resolved
Exhaust on the fwd starboard engine is not properly supported as required. Properly support engine exhaust as required.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 4 May 2021
Resolved 4 May 2021
Resolution: Exhaust stack was supported properly.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 20 April 2021 Resolved
Starboard fwd engine has an exhaust leak at the turbocharger. Repair exhaust leak on engine.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 4 May 2021
Resolved 29 April 2022
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 20 April 2021 Resolved
All three life ring buoys were not in serviceable condition. Replace all three life ring buoys prior to departure from port.
Action required: 17 - Rectify deficiencies prior to departure
Due 20 April 2021
Resolved 4 May 2021
Resolution: New life ring bouys were installed.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 20 April 2021 Resolved
Fire hose nozzle was stuck in fog position. Repair/renew fire hose nozzle to be able to be changed between solid stream and fog pattern.
Action required: 17 - Rectify deficiencies prior to departure
Due 20 April 2021
Resolved 7 April 2022
Resolution: Owner repaired the nozzle. Tested - all sat.
07 - Fire Safety › N/A - No Subsystem › Ventilation
Issued 20 April 2021 Resolved
Fuel vent screens on both fuel vents were corroded beyond use. Replace fuel vent screen with appropriate 30x30 vent screen or two 20x20 vent screens as applicable.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 4 May 2021
Resolved 7 April 2022
Resolution: Owner replaced the fuel vent screens. All sat.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 20 April 2021 Resolved
Flammable materials are being stowed in the crew head and storage area by galley. Remove all flammable materials and store correctly.
Action required: 17 - Rectify deficiencies prior to departure
Due 20 April 2021
Resolved 4 May 2021
Resolution: Flammable materials were all removed.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 20 April 2021 Resolved
Both e/r’s had insulation, from original construction, that is falling from overhead, worn beyond use or held in place with wood support. Renew/replace insulation to original condition and remove combustible materials (wood) from e/r.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 4 May 2021
Resolved 7 April 2022
Resolution: Owner repaired insulation.
09 - Working and Living Conditions › 092 - Working Conditions › Lighting (Working spaces)
Issued 20 April 2021 Resolved
The light fixture in the starboard e/r over the aft engine does not have a cover. Provide a cover for the light fixture or renew light fixture.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 4 May 2021
Resolved 7 April 2022
Resolution: Owner replaced the light fixture with a new one. Tested - all sat.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 20 April 2021 Resolved
All four main engines have exhaust lagging that is not completely covering exhaust pipes or has been worn away. Repair/renew exhaust lagging to original condition as required.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 4 May 2021
Resolved 29 April 2022
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 20 April 2021 Resolved
Bilge pump cross-connect between hulls is not operational. Prove proper operation of bilge system prior to departure from port.
Action required: 17 - Rectify deficiencies prior to departure
Due 20 April 2021
Resolved 29 April 2022
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 20 April 2021 Resolved
Several dead end wires were found in the port engine room. Properly terminate all wires as required.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 4 May 2021
Resolved 7 April 2022
Resolution: Owner removed dead end wires.
11 - Life Saving Appliances › N/A - No Subsystem › Inflatable liferafts
Issued 14 October 2020 Resolved
VESSEL REQUESTED A REDUCTION IN LIFE RAFT CAPACITY TO FACILITATE LIFE RAFT SERVICING. VESSEL IS LIMITED TO CARRYING 100 PASSENGERS UNTIL FULL CAPACITY OF LIFE RAFTS HAVE BEEN REINSTALLED AND VERIFIED BY THE ATTENDING MARINE INSPECTOR.
Action required: 705 - Other - as specified
Due 1 December 2020
Resolved 29 December 2020
07 - Fire Safety › N/A - No Subsystem › Fire pumps and its pipes
Issued 9 July 2020 Resolved
Prove proper operation of fire pump to CG Marine inspector prior to departure from port.
Action required: 10 - Deficiency Rectified
Due 9 July 2020
Resolved 9 July 2020
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 9 July 2020 Resolved
Replace 5 lifejackets that were deemed unservicable.
Action required: 701 - Prior to carriage of passengers/cargo
Due 1 September 2020
Resolved 17 September 2020
Resolution: The 05 unserviceable life jackets were replaced with new lifejackets.
09 - Working and Living Conditions › 092 - Working Conditions › Other (accident prevention)
Issued 9 July 2020 Resolved
Remove all flammable and combustible material that is not stored in the proper flammable locker.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 August 2020
Resolved 17 September 2020
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 9 July 2020 Resolved
Repair/replace wiring in port e/r vestibule for aft deck light.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 August 2020
Resolved 17 September 2020
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 9 July 2020 Resolved
Properly cover electrical boxes in both e/r vestibules.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 August 2020
Resolved 17 September 2020
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 9 July 2020 Resolved
Replace chaffed starboard hydraulic bucket hose between bucket and resovoir.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 August 2020
Resolved 17 September 2020
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 9 July 2020 Resolved
Repair exhaust leak on stbd fwd, port fwd and port aft engines at turbocharger.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 August 2020
Resolved 17 September 2020
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 9 July 2020 Resolved
Repair excessive oil leak on stbd fwd engine outboard side below exhaust manifold.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 August 2020
Resolved 17 September 2020
09 - Working and Living Conditions › 092 - Working Conditions › Guards - fencing around dangerous machinery parts
Issued 9 July 2020 Resolved
Replace missing bolts on port aft engine belt cover.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 9 August 2020
Resolved 17 September 2020
11 - Life Saving Appliances › N/A - No Subsystem › Stowage and provision of liferafts
Issued 25 April 2019 Resolved
The 6-person IBA installed on the upper deck is not installed in a float-free arrangement. Attach painter to weak link in accordance with manufacturer's instructions. Vessel total passenger count reduce to 144 until IBA properly installed. - 46 CFR 180.137
Action required: 10 - Deficiency Rectified
Resolved 25 April 2019
Resolution: Painter attached to weak link.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 25 April 2019 Resolved
The aft ring lifebuoy is deteriorated beyond servicibility. Repair or replace ring lifebuoy. - 46 CFR 180.70
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 May 2019
Resolved 27 June 2019
Resolution: Lifebuoy verified replaced.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 25 April 2019 Resolved
Sea strainer for raw water cooling on the generator is leaking water into the starboard #3 void. Repair or replace strainer to eliminate leak. - 46 CFR 182.700
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 May 2019
Resolved 27 June 2019
Resolution: Leak repaired.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Gauges, thermometers, etc
Issued 25 April 2019 Resolved
Oil pressure gauge for generator not reflecting actual oil pressure. Provide means for determining generator lubricating oil pressure. - 46 CFR 183.320
Action required: 50 - Rectify deficiencies w/in 30 days
Due 25 May 2019
Resolved 27 June 2019
Resolution: Gauge functional.
Operations/Management › Drug and Alcohol Testing › Employee Coverage
Issued 26 April 2018 Resolved
Provide evidence of current enrollment into drug consortium.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 May 2018
Resolved 5 June 2018
Resolution: Proof of enrollment provided.
Lifesaving › Lifebuoys › Serviceable
Issued 26 April 2018 Resolved
Lifebuoy light battery is expired and not manufacturer recommended. Provide new and appropriate battery.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 May 2018
Resolved 5 June 2018
Resolution: New battery provided.
Documentation › Certificates/Documents › Stability Letter
Issued 26 April 2018 Resolved
Post the most current Stability Letter at the operating station.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 May 2018
Resolved 5 June 2018
Resolution: Letter posted.
Engineering › Engine Controls (Electric/Electronic) › Actuator
Issued 26 April 2018 Resolved
Repair and prove proper operation of the port aft engine shutdown from the operating station.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 May 2018
Resolved 10 September 2018
Resolution: Witnessed satisfactory shutdown from pilothouse.
Navigation › Collision/Grounding Avoidance › Danger Messages
Issued 26 April 2018 Resolved
Provide a ship's bell.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 May 2018
Resolved 5 June 2018
Resolution: Bell provided.
Construction/Loadline › Hull › Weld
Issued 19 April 2018 Resolved
Provide proposal and make permanent repairs to hull fractures in way of the starboard swim step.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 23 May 2018
Resolved 10 September 2018
Resolution: Fractures repaired.
Electrical › Electric Supply System (service) › Battery Installation
Issued 19 April 2018 Resolved
Provide electrolyte resistant battery trays.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 23 May 2018
Resolved 10 September 2018
Resolution: Tray provided.
Construction/Loadline › Hull › Hull Plating
Issued 23 March 2017 Resolved
Properly crop and renew wasted hull plating iaw approved plan iwo of the port and stbd mid engine room inboard side, just fwd of the aft engine, side shell just off of bottom hull plating aprox 4' x 18" areas with heavy pitting. Conduct NDT testing of all welds. All repairs to be made to the satisfaction of the attending CG Marine Inspector.
Action required: 705 - Other - as specified
Due 31 May 2017
Resolved 26 May 2017
Resolution: Owners rep text me detailed photos of the repairs and NDT testing. All SAT.
Operations/Management › Drills/Instruction › Fire
Issued 20 April 2016 Resolved
Demonstrate emergency drills (fire, abandon ship, & MOB) & safety orientation with the permanent crew to the satisfaction of an attending marine inspector.
Condition: Invalid
Action required: 705 - Other - as specified
Due 5 May 2016
Resolved 7 May 2016
Resolution: Done, sat
Construction/Loadline › Hull › Side Shell
Issued 14 April 2016 Resolved
Side Shell on port outer enginer room has pinhole leak. Repair proposal needed for cropping and renewing portion of plate.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 28 April 2016
Resolved 7 May 2016
Resolution: Repaired ... Sat.
Construction/Loadline › Hull › Bottom Plating
Issued 29 March 2016 Resolved
Conduct NDT of hull pitting in #2 starboard void from bow extending upward from the keel.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 1 May 2016
Resolved 1 April 2016
Resolution: Areas had NDT conducted. The locations were less than 25% wastage. The affected areas will receive salt removal process and have a anti-coroosion material applied.
Construction/Loadline › Penetrations › Valve Flange
Issued 29 March 2016 Resolved
Repair dissimilar metal on through hull fitting on port side.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 1 May 2016
Resolved 12 April 2016
Lifesaving › Buoyant Apparatus › Capacity
Issued 2 November 2015 Resolved
Buoyant Apparatus are currently on the Admiralty Wind while it's rafts are being serviced. Vessel is not allowed to get underway until liferafts are returned to the vessel and it has been verified.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Due 16 November 2015
Resolved 7 May 2016
Resolution: Sat.
Construction/Loadline › Hull › Weld
Issued 5 December 2011 Resolved
Four cracked welds (outboard and inboard of both hulls) at FR 4 due to design flaw in vessel. Make suitable repairs prior to carrying passengers.
Condition: Design Flaw
Action required: 17 - Rectify deficiencies prior to departure
Due 5 March 2012
Resolved 25 January 2012
Resolution: Observed final repairs. All welds and inserts, inspected sat.
Navigation › Piloting/Steering › Magnetic Compass
Issued 29 July 2008 Resolved
Vsl has 2 independent magnetic compasses on bridge. 1 in the overhead and 1 on stbd side chart table. A 5 deg difference exists between the 2. The chart table compass has no electrical equipment in the vicinity, while the overhead has many. Vsl to identify accurate reading and make permenant repairs at next drydock.
Action required: 705 - Other - as specified
Due 30 January 2009
Resolved 30 July 2008
Resolution: Def issued in error. Should have been on the FWX, not FWX EXPRESS.
Lifesaving › Lifebuoys › Markings (ship name/port)
Issued 7 April 2008 Resolved
Re-stencil vessel's name on all (3) three life rings.
Action required: 705 - Other - as specified
Due 29 July 2008
Resolved 29 July 2008
Construction/Loadline › Hull › Side Shell
Issued 4 September 2007 Resolved
Repair crack at waterline in starboard void #2 to the satisfaction of the attending marine inspector.
Action required: 701 - Prior to carriage of passengers/cargo
Due 11 September 2007
Resolved 7 September 2007
Resolution: Area cropped & renewed.
Lifesaving › Lifejacket/PFD (General) › Marking
Issued 9 April 2007 Resolved
Children's PFDs need to be re-marked.
Due 9 April 2007
Resolved 9 April 2007
Resolution: Corrected on-the-spot.
Stability › Watertight Integrity › General
Issued 9 April 2007 Resolved
Hatches to starboard and port jet rooms were not attached by lanyard.
Due 9 April 2007
Resolved 9 April 2007
Resolution: Corrected on-the-spot
Navigation › Piloting/Steering › Tide/Tidal Current Tables
Issued 9 April 2007 Resolved
Did not have tidal current tables on board.
Due 9 April 2007
Resolved 9 April 2007
Resolution: Corrected on-the-spot
Navigation › Piloting/Steering › Magnetic Compass
Issued 9 April 2007 Resolved
Compass was not illuminated.
Due 9 April 2007
Resolved 9 April 2007
Resolution: Corrected on-the-spot
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 9 April 2007 Resolved
Starboard nav light not functioning (loose in socket)
Due 9 April 2007
Resolved 9 April 2007
Resolution: corrected on-the-spot
Engineering › Steering Gear System › Feedback Unit
Issued 15 May 2006 Resolved
Double lock linkage to Port & Starboard buckets steering indicator reverse mode.
Condition: Unknown
Due 15 May 2006
Resolved 15 May 2006
Resolution: Done
Electrical › Electric Generation Source (service) › Conductor
Issued 15 May 2006 Resolved
Secure dead end wire of aft main engine Port Side engineroom outboard aft side via reduction gear.
Condition: Unknown
Due 15 May 2006
Resolved 15 May 2006
Resolution: Done
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 15 May 2006 Resolved
Provide a CG Approved First Aid Kit onboard.
Condition: Unknown
Due 15 May 2006
Resolved 15 May 2006
Resolution: Provided by the Operation Officer ...
Accommodation/Occupational Safety › Occupational Safety › Spark Producing Device
Issued 16 May 2005 Resolved
Removed all flammable cans, (thinner, paints, kerosene) found in the aft STBD storage space.
Condition: Improper Installation
Due 16 May 2005
Resolved 16 May 2005
Resolution: Removed off the vessel. Claimed leftovers from drydock.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 16 May 2005 Resolved
Add missing aspirin or equivalent to the first aid kit.
Condition: Unknown
Due 16 May 2005
Resolved 16 May 2005
Resolution: Added, sat.
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 16 May 2005 Resolved
Repair broken bracket to the machinery guard of alternator belt No.1 Port Engine.
Condition: Unknown
Due 16 May 2005
Resolved 16 May 2005
Resolution: Engineer [name withheld], fixed & repaired during this inspection, sat.
Fire Fighting › Fixed Fire Detection System › Smoke Detectors
Issued 16 May 2005 Resolved
Repair STBD engine room smoke detector, loose screws just hanging.
Condition: Unknown
Due 16 May 2005
Resolved 16 May 2005
Resolution: Repaired, sat.
Fire Fighting › Fire Hydrants › Condition
Issued 16 May 2005 Resolved
Repair temporary rigging of rubber hoses and short pipe to aft fire station.
Condition: Improper/Lack of Maintenance
Due 16 May 2005
Resolved 16 May 2005
Resolution: Done by port [name withheld] & engineers on dock.
Navigation › Piloting/Steering › Steering Magnetic Compass
Issued 13 May 2005 Resolved
Install missing steering wheels on the port & starboard bridge wings.
Condition: Unknown
Due 13 May 2005
Resolved 13 May 2005
Resolution: Alternate steering joysticks were in place in lieu of the steering wheels. Vessel port captain will removed the old hydraulic actuators & blanked-off old P/S steering wheels. Tested Port & Starboard steering joysticks, sat.
Construction/Loadline › Hull › Side Shell
Issued 25 March 2005 Resolved
Starboard (Stbd) hull, forward (fwd) inboard, crop & renew (C&R) area where cracked.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Resolved 31 March 2005
Construction/Loadline › Hull › Side Shell
Issued 25 March 2005 Resolved
Stbd hull aft corner, C&R area marked approx. 2'x3'
Action required: 705 - Other - as specified
Resolved 31 March 2005
Construction/Loadline › Hull › Hull Plating
Issued 25 March 2005 Resolved
C&R port bow at bulwarks where previous collision damage repairs are failing; including keel, and hull plate where cracks are radiating.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Construction/Loadline › Hull › Hull Plating
Issued 25 March 2005 Resolved
C&R port hull at deck; four places where Bondo conceals damage, three additional areas identified as cosmetic may be left as is.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Stability › Watertight Integrity › General
Issued 25 March 2005 Resolved
Install water-tight deck hatches (WTDH) for all four forward voids. Vessel is designed to meet Type II subdivision and plans as drawn by architect call out for WTDHs.
Action required: 705 - Other - as specified
Due 30 April 2005
Resolved 13 May 2005
Resolution: Done
Construction/Loadline › Hull › Weld
Issued 25 March 2005 Resolved
Pick up missing double continuous welds at deck in fwd voids; bay two of both Port & Stbd hulls.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Construction/Loadline › Hull › Weld
Issued 25 March 2005 Resolved
Weld frames three & four to keel.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Engineering › Bilge Water Management System › Valve
Issued 25 March 2005 Resolved
Provide reach rods for both valves to bilge systems at collision bulkhead.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Accommodation/Occupational Safety › Heating › Electric Air Heating Equipment
Issued 25 March 2005 Resolved
Provide plans or Coast Guard approvals of "CruiseAir" systems or remove systems from vessel.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Resolution: Proved original system installation at new construction
Accommodation/Occupational Safety › Heating › Piping
Issued 25 March 2005 Resolved
If approved installation can be proved for "CruiseAir" systems, renew improper insulation on "CruiseAir" lines as it is melting.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Construction/Loadline › Hull › Transverse Frame
Issued 25 March 2005 Resolved
In both Port & Stbd voids aft of collision bulkhead, make repairs to both cracked frames and all frames at horizontal plate where welds are cracked.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Accommodation/Occupational Safety › Potable Water System › General
Issued 25 March 2005 Resolved
Provide plans or Coast Guard approvals of four tanks used as water system or remove systems from vessel. Note fill line runs out air vent to deck and all tanks show signs of over-pressurization.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Due 31 May 2005
Resolved 19 May 2005
Resolution: Water tanks removed from vessel as per Port Captain provided photos, sat.
Pollution Prevention/Response › Prevention Equipment › Marine Sanitation Device, Type III
Issued 25 March 2005 Resolved
Provide plans or Coast Guard approvals of "new" sewage system including electrical distribution or remove systems from vessel. Note additionally, that new transfer pump was found to be 13amps on a circuit protected by a 10amp breaker.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Due 30 April 2005
Resolved 13 May 2005
Resolution: The 13 amps was actually 13 joules. Existing breakers were sat.
Stability › Intact Righting Energy › General
Issued 25 March 2005 Resolved
Show that weight of all systems/equipment installed since Stability Letter was issued (from initial deadweight survey) do not exceed 2% of ships deadweight. Otherwise conduct new deadweight survey and apply for new Stability Letter
Action required: 705 - Other - as specified
Resolved 31 March 2005
Electrical › Electrical Distribution System (service) › Wiring
Issued 25 March 2005 Resolved
Replace improper "Yellow Jacket" extension cord with boat cable. It is hard wired between the switch and light in port fuel tank void.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Resolved 31 March 2005
Electrical › Lighting (service) › Lighting Fixture
Issued 25 March 2005 Resolved
Replace broken and missing light covers in both fuel tank voids.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Electrical › Electrical Distribution System (service) › Junction Box
Issued 25 March 2005 Resolved
Provide covers for electrical connections of fuel tank sensors.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Construction/Loadline › Penetrations › Pipe Flange
Issued 25 March 2005 Resolved
C&R stand pipe and 12"x12" hull plate in way of raw water suction in stbd fuel tank void for the "CruiseAir" system due to severe corrosion.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Resolution: Flange replaced, stand pipe cut down to good metal. Hull found to be serviceable.
Stability › Watertight Integrity › Coaming
Issued 25 March 2005 Resolved
Provide 3" coamings for all weather tight doors.
Action required: 705 - Other - as specified
Due 31 May 2005
Resolved 15 May 2006
Resolution: Done ... raise coamings to Port & STBD access doors to 4 inches, sat.
Electrical › Electrical Distribution System (service) › Wiring
Issued 25 March 2005 Resolved
Make repairs to cable identified as stbd forward engine exhaust temperature alarm where cable is dead ended in engine room.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Pollution Prevention/Response › Prevention Equipment › Marine Sanitation Device, Type III
Issued 25 March 2005 Resolved
Remove vent for Marine Sanitation Device where it is connected to overboard discharge. Run vent properly up through deck and provide flame screen. As installed vent is designed to allow overflow to freely discharge overboard.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Resolved 31 March 2005
Electrical › Electrical Distribution System (service) › Wiring
Issued 25 March 2005 Resolved
In pilot house below dash, remove light/plug adapter that is supplying power to portable heater and replace protection globe over light.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Resolved 31 March 2005
Electrical › Electrical Distribution System (service) › Junction Box
Issued 25 March 2005 Resolved
In pilot house below dash, replace wire nuts with UL crimp connectors on gph meter or wrap in electrical tape and place in junction box.
Action required: 705 - Other - as specified
Resolved 31 March 2005
Lifesaving › Lifebuoys › Serviceable
Issued 14 July 2004 Resolved
Renew worn retro-reflective tape on the lifebuoy located on the port side pilothouse.
Condition: Improper/Lack of Maintenance
Due 14 July 2004
Resolved 14 July 2004
Resolution: Done prior to departure.
Fire Fighting › Fire Hoses › Condition
Issued 14 July 2004 Resolved
Replace the firehose with a pin hole leak located on the upper deck area.
Condition: Unknown
Action required: 17 - Rectify deficiencies prior to departure
Due 14 July 2004
Resolved 14 July 2004
Resolution: Done
Engineering › Freshwater System (jacketwater cooling) › Pump
Issued 14 July 2004 Resolved
Replace the leaking mechanical seal for the Jacket Water pump for the STBD Main engine.
Condition: Unknown
Due 14 July 2004
Resolved 14 July 2004
Electrical › Electrical Distribution System (service) › Busway
Issued 14 July 2004 Resolved
Secure wiring (bundle) and tape speaker wire located overhead panel lower level mid section.
Condition: Unknown
Due 14 July 2004
Resolved 14 July 2004
Resolution: Done
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 14 July 2004 Resolved
Install guards to exposed front pulley moving parts of the inboard main engine STBD side.
Condition: Unknown
Due 14 July 2004
Resolved 14 July 2004
Resolution: Guard on order.
Accommodation/Occupational Safety › Occupational Safety › Portable Electric Equipment/Appliances
Issued 14 July 2004 Resolved
Secure for sea small refrigerator in the galley area.
Due 14 July 2004
Resolved 14 July 2004
Communications › Radio Communications › EPIRB
Issued 12 July 2004 Resolved
Provide an Emergency Position Indicating Radio Beacon (EPIRB) to the vessel IAW CGD17 Instructions 16714.1 dated 15 FEB 2001.The EPIRB must be properly installed & registered USCG Approved 406 MHZ EPIRB. In addition to the EPIRB type, float free arrangement & installation location must be highly consider.
Condition: Unknown
Action required: 705 - Other - as specified
Due 14 August 2004
Resolved 2 August 2004
Resolution: EPIRB ACR Model 2774 UIN: ADCD023E6D42001-32667
Unknown
Issued 17 April 2000 Resolved
PROVIDE CPR/FIRST AID CARDS FOR 50% OF THE CREW.
Condition: Unknown
Due 17 April 2000
Resolved 17 April 2000
Navigation
Issued 17 April 2000 Resolved
PROVIDE UP TO DATE NAUTICAL PUBLICATIONS TO INCLUDE CHARTS, COAST PILOT ANDLIGHTLIST.
Condition: Unknown
Due 17 April 2000
Resolved 17 April 2000
Unknown
Issued 17 April 2000 Resolved
MOUNT FCC EMERGENCY BROADCAST PLACARD AT THE OPERATORS STATION.
Condition: Unknown
Due 17 April 2000
Resolved 17 April 2000
Unknown
Issued 17 April 2000 Resolved
MAKE REPAIRS TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR TO DAMAGED AREA WHERE DECK AND TRANSOM MEET ON THE PORT SIDE OF VESSEL.
Condition: Unknown
Due 17 April 2000
Resolved 17 April 2000
Accommodation/Occupational Safety
Issued 4 March 1998 Resolved
Install chain link fence, wire mesh or the equivelant to the space below the rail in all passenger accessible locations per 46CFR177.35-1(c)
Condition: Unknown
Due 4 March 1998
Resolved 4 March 1998
Lifesaving
Issued 18 April 1996 Resolved
Install life lines (safety lines) on swim platforms prior to carrying passengers for hire.
Condition: Unknown
Due 18 April 1996
Resolved 18 April 1996
Construction/Loadline
Issued 18 April 1996 Resolved
Istall loading marks as required.
Condition: Unknown
Due 18 April 1996
Resolved 18 April 1996
Navigation
Issued 18 April 1996 Resolved
Install a working compass prior to carrying passengers for hire.
Condition: Unknown
Due 18 April 1996
Resolved 18 April 1996

Casualty record · 1

6 August 2002Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 1799322
Each line is an incident investigation the Coast Guard recorded with this hull among the vessels involved, with the date and the classification the Coast Guard gave it, and the bridge, lock or dam the investigation names where it names one. Involvement is not fault. The investigation narrative is not published. Source: IIR, through 2026.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.