Records from 2009 to 2019. Most recent: inspection, 22 May 2019.
Fire Fighting › Fixed Gas Fire Extinguishing System › Control Valve
Issued 25 June 2018
Resolved
Upon conducting a test of the vessels pre-engineered fire extinguishing system, the engines did not shut down as per 46 CFR 181.420(a)(3)
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 27 June 2018
Resolution: Vessel proved proper operation of fixed fire extinguishing system.
Engineering › Bilge Water Management System › Not Operational
Issued 25 June 2018
Resolved
During an opertional test of vessels bilge pump, a fitting in the piping system burst, rendering the bilge pump inoperable.
46 CFR 182.500(a)
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 27 June 2018
Resolution: vessel proved proper operation of fixed bilge system.
Communications › Public Address System › Amplifier
Issued 25 June 2018
Resolved
PA system was inoperable. 46 CFR 184.610
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 27 June 2018
Resolution: vessel proved proper operation of PA system.
Operations/Management › Drug and Alcohol Testing › EAP Display Requirements
Issued 25 June 2018
Resolved
Vessel was unable to provide EAP display requirements along with any kind of required training. 46 CFR 16
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 27 June 2018
Resolution: vessel provided all required documentation.
Lifesaving › Lifefloat › Serviceable
Issued 25 June 2018
Resolved
15 person lifefloat needs to be repaired with a manufacturer approved repair kit. 46 CFR 180.730
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 July 2018
Resolved 7 September 2018
Resolution: Vessel submitted pictures of repaired life float.
Lifesaving › Lifefloat › Floating Electric Waterlight
Issued 25 June 2018
Resolved
15 person lifefloat waterlight was inoperable. 46 CFR 180.175(d)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 July 2018
Resolved 9 July 2018
Lifesaving › Lifefloat › Painter
Issued 25 June 2018
Resolved
Painter needs to be replaced due to deterioation and also needs to be stowed in a way to release freely. 46 CFR 180.175(f)(3)(iii,iv)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 July 2018
Resolved 9 July 2018
Navigation › Piloting/Steering › Marine Charts
Issued 25 June 2018
Resolved
vessel must maintain up-to-date charts and publications. Vessel did not have updated charts, coast pilot, or light list. 46 CFR 184.420
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 27 June 2018
Resolution: vessel provided updated chart and publications
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 25 June 2018
Resolved
All moving parts exposed to crew that pose a safety hazard must be protected with a guard. The fly wheels on port and starboard engines need guards. 46 CFR 182.177.960
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 July 2018
Resolved 9 July 2018
Electrical › Electrical Distribution System (service) › Wiring
Issued 25 June 2018
No resolution recorded
All solid core wires nust be replaced with stranded core wire. 46 CFR 183.05-45(b). Prior to credit Drydock.
Action required: 705 - Other - as specified
Electrical › Lighting (service) › Lighting Fixture
Issued 25 June 2018
Resolved
Outlets exposed to weather must be watertight. Several outlets throughtout the decks are not watertight. Also lighting fixture on stern needs to be repaired. 46 CFR 183.01-15
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 July 2018
Resolved 9 July 2018
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 25 June 2018
Resolved
Stern light needs to be repaired. Stern light enclosure is not secured to the vessel. 46 CFR 183.01-15
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 July 2018
Resolved 9 July 2018
Accommodation/Occupational Safety › Occupational Safety › Rubbish/Waste Materials
Issued 25 June 2018
Resolved
All flammable items located in 2nd deck locker and locker located in the accommadation space (i.e. paint cans, mineral spirits, and propane tank) must be removed from vessel unless protected by a suppression system. 46 CFR 181.400
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 27 June 2018
Resolution: Vessel removed all flammable materials.
Construction/Loadline › Hull › Bottom Plating
Issued 6 April 2018
No resolution recorded
Provide written repair proposal for completion of all items listed above during 2018 dry dock period.
Action required: 705 - Other - as specified
Navigation › Piloting/Steering › Marine Charts
Issued 15 August 2017
Resolved
Provide up to date charts.
Condition: Invalid
Action required: 705 - Other - as specified
Due 29 August 2017
Resolved 29 August 2017
Resolution: Updated charts are onboard the vessel.
Navigation › Piloting/Steering › US Coast Pilot
Issued 15 August 2017
Resolved
Provide up to date Coast Pilot.
Condition: Invalid
Action required: 705 - Other - as specified
Due 29 August 2017
Resolved 29 August 2017
Resolution: Updated Coast Pilot is onboard.
Navigation › Piloting/Steering › Inland Navigation Rules
Issued 15 August 2017
Resolved
Provide up to date Navigation Rules and Regulations.
Condition: Invalid
Action required: 705 - Other - as specified
Due 29 August 2017
Resolved 29 August 2017
Resolution: Updated publication is onboard.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 15 August 2017
Resolved
Provide first-aid kit approved under 46 CFR 160.041
Condition: Invalid
Action required: 705 - Other - as specified
Due 29 August 2017
Resolved 29 August 2017
Resolution: Approved first aid kit is onboard.
Electrical › Electric Supply System (service) › Battery Installation
Issued 15 August 2017
Resolved
Secure battery box for generator starting.
Action required: 705 - Other - as specified
Due 29 August 2017
Resolved 29 August 2017
Resolution: Complete
Engineering › Diesel Engine (propulsion-reduction gear) › Exhaust Manifold
Issued 15 August 2017
Resolved
Double clamp non-metallic hose on main engine exhaust line in starboard side of generator space.
Action required: 705 - Other - as specified
Due 29 August 2017
Resolved 29 August 2017
Resolution: Complete
Engineering › Sea-water System (primary cooling) › Piping
Issued 15 August 2017
Resolved
Provide hose for generator raw water suction approved under SAE J-1942.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 29 August 2017
Resolved 29 August 2017
Resolution: Complete.
Construction/Loadline › Hull › Transverse Frame
Issued 27 April 2017
Resolved
Replace deck beam 2nd from fwd bulkhead in generator space
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 March 2018
Resolved 6 April 2018
Resolution: Deck beam replaced.
Construction/Loadline › Hull › Transverse Frame
Issued 27 April 2017
Resolved
Replace 2,3,4 & 5 deck beam in tank room.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 March 2018
Resolved 6 April 2018
Resolution: Deck beams replaced.
Construction/Loadline › Hull › Transverse Frame
Issued 27 April 2017
Resolved
Replace 1st deck beam from aft bulkhead stbd side in tank room
Action required: 705 - Other - as specified
Due 31 March 2018
Resolved 6 April 2018
Resolution: Deck Beams replaced.
Construction/Loadline › Hull › Side Shell
Issued 20 May 2016
Resolved
The epoxy and 5200 needs to be removed and area taken to good wood IWO all interior seams and made ready for inspection. To be completed at Dry Dock Scheduled for 31MAR2017.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 March 2017
Resolved 27 April 2017
Resolution: The owner/operator request specific areas be called out for further inspection. Specific areas were called out this dry dock.
Construction/Loadline › Hull › Transverse Frame
Issued 20 May 2016
Resolved
Remove all paint, epoxy and 5200 from all deck beams, side frames, bottom frames, knees, gussets and floors within 12" of all fastening points. To be completed at Dry Dock scheduled for 31MAR2017.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 March 2017
Resolved 27 April 2017
Resolution: The owner/operator request specific areas be called out for further inspection. Specific areas were called out this dry dock.
Construction/Loadline › Hull › Side Shell
Issued 20 May 2016
Resolved
Remove epoxy and 5200 from the exterior chine seams. To be completed at Dry Dock scheduled for 31MAR2017.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 March 2017
Resolved 27 April 2017
Resolution: The owner/operator request specific areas be called out for further inspection. Specific areas were called out this dry dock.
Construction/Loadline › Hull › Side Shell
Issued 20 May 2016
Resolved
Vessel required to schedule a mid season underway operational test and internal Structural examination to be conducted between 15AUG2016 and 31AUG2016.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 August 2016
Resolved 31 August 2016
Resolution: Complete
Operations/Management › Vessel Activity › Underway
Issued 20 May 2016
Resolved
Vessels route is restricted to Lakes, Bays and Sounds NOT MORE THAN 1000 FEET FROM SHORE until vessel completes Dry Dock Scheduled for 31MAR2017.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 March 2017
Resolved 27 April 2017
Resolution: Complete
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 18 May 2016
Resolved
Starboard running light is not functioning. Starboard running light required as per NAV Rules.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 1 June 2016
Resolved 20 May 2016
Communications › Radio Communications › VHF Radiotelephone
Issued 18 May 2016
Resolved
VHF radio required to be DSC capable. Current radio setup does not have MMSI programmed.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 1 June 2016
Resolved 20 May 2016
Engineering › Diesel Engine (propulsion-reduction gear) › Exhaust Manifold
Issued 18 May 2016
Resolved
STBD engine has exhaust/salt water leak at exhaust cooler. Exhaust is to be free of leaks.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 1 June 2016
Resolved 27 April 2017
Resolution: The exhaust was repaired.
Engineering › Diesel Engine (propulsion-reduction gear) › Exhaust Manifold
Issued 18 May 2016
Resolved
Exhaust piping needs to be double clamped when non metallic hose is utilized.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 1 June 2016
Resolved 27 April 2017
Resolution: Repairs were made.
Fire Fighting › Fixed Gas Fire Extinguishing System › Operating Controls
Issued 18 May 2016
Resolved
Pre engineered fixed gas fire fighting system is required to shutdown engines. Currently does not shutdown engines.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 1 June 2016
Resolved 20 May 2016
Communications › Alarms/Indicators › High Water Alarm
Issued 18 May 2016
Resolved
Bilge level alarms are currently mounted too high. Vessel needs to relocate bilge level alarms lower in the bilge area.
Condition: Improper Installation
Action required: 701 - Prior to carriage of passengers/cargo
Due 1 June 2016
Resolved 20 May 2016
Construction/Loadline › Hull › Hull Plating
Issued 16 May 2016
Resolved
Vessel has planks pulling away from frames. Broken fasteners, missing fasteners (butt blocks, floor to frame) Deck Beam in #2 Compartment has wasted area approximately 10" X 2". Signs of several butt blocks leaking, temp repairs made with what appears to be 5200. Several seams are weaping. Make repair proposal.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 20 May 2016
Resolution: Deficiency was rescended.