Inspection history · 58
14 September 2004
Administrative Inspection
Administrative · Marine Safety Center (MSC) · Activity 2195755
30 December 2003
Security Plan Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 1984259
17 October 2003
Administrative Inspection
Administrative · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1930518
10 July 2003
Periodic Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1868275
25 July 2002
Annual Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1653856
2 October 2001
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 516647
28 August 2001
Deficiency Check
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1071999
22 August 2001
Re-Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1071654
8 January 2001
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 483805
6 September 2000
COI Inspection · Hull Examination
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1455893
13 July 1999
COI Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1429186
2 July 1998
Re-Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 796387
5 August 1997
COI Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1383634
24 September 1996
Re-Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 835167
17 March 1996
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 463427
26 September 1995
Hull Examination · COI Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 885962
27 March 1995
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 486333
26 September 1994
Re-Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1172834
30 August 1994
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 517710
3 December 1993
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 531941
2 September 1993
COI Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 842218
9 June 1993
Examination of Repairs
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1155276
9 November 1992
Type not recorded
No type recorded · Marine Safety Detachment Cincinnati · USCG Heartland District (CGD-H) · Activity 441073
24 September 1992
Re-Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 942407
3 March 1992
Type not recorded
No type recorded · Marine Safety Detachment Cincinnati · USCG Heartland District (CGD-H) · Activity 487270
21 November 1991
Deficiency Check
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 939616
13 November 1991
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 642105
7 November 1991
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 460901
7 November 1991
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 1245163
6 September 1991
COI Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1253600
6 September 1991
Administrative
Administrative · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1253601
30 July 1991
Examination of Repairs
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1247851
10 April 1991
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 496449
28 September 1990
Hull Examination · Re-Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 930364
20 August 1990
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 531756
17 August 1990
Damage Survey
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 912324
16 February 1990
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 448233
15 September 1989
COI Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1202179
14 August 1989
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 464989
16 May 1989
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 539906
29 November 1988
Administrative
Administrative · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 895724
7 November 1988
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 489329
26 October 1988
Re-Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1203635
8 January 1988
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 467028
16 September 1987
COI Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1005506
29 June 1987
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 495717
23 June 1987
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 441628
27 May 1987
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 470628
24 February 1987
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 493837
14 January 1987
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 500697
29 October 1986
Re-Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1014222
23 October 1986
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 521082
29 August 1986
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 467921
20 August 1986
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 461930
7 April 1986
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 473341
26 September 1985
COI Inspection
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1286318
8 August 1984
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 488525
21 June 1984
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 534285
Engineering › Diesel Engine (auxiliary)
Issued 29 July 2002
Resolved
Emergency shutdown was inoperative. Cable was frozen in pipe and would not pull.
Condition: Unknown
Action required: 705 - Other - as specified
Due 29 July 2002
Resolved 29 July 2002
Resolution: Corrected.
Deck/Cargo
Issued 22 August 2001
Resolved
REPAIR BRAKE ON STB AFT DECK WINCH.
Condition: Unknown
Due 22 August 2001
Resolved 22 August 2001
Construction/Loadline
Issued 22 August 2001
Resolved
REPAIR DAMAMGED AND HOLED FLAME SCREENS ON FWD AND AFT VOID GOOSENECK VENTS.
Condition: Unknown
Due 22 August 2001
Resolved 22 August 2001
Deck/Cargo
Issued 22 August 2001
Resolved
REPAIR BROKEN #5P P/V VALVE.
Condition: Unknown
Due 22 August 2001
Resolved 22 August 2001
Construction/Loadline
Issued 24 September 1996
Resolved
PRIOR TO RELOADING MAKE PERMANENT REPAIRS TO 2 INCH FRACTURE ON STARBOARD SIDE SHELL PLATING IN WAY OF 4 FOOT FROM BOTTOM KNUCKLE AFT OF BOW CORNER WRAPPER.
Condition: Unknown
Due 24 October 1996
Resolved 4 October 1996
Deck/Cargo
Issued 24 September 1992
Resolved
PRIOR TO LOADING CARGO, COMPLETE USCG/ASHLAND OIL WORKLIST DATED 23SEP92 AND DETERMINE SOURCE OF FLAMMABLE VAPORS (8% LEL) IN WAY OF THE PORT BOW VOID.
Condition: Unknown
Due 23 October 1992
Resolved 25 September 1992
Deck/Cargo
Issued 7 November 1991
Resolved
Reattach the pressure-vacuum relief valve to the #3 port cargo tank as required by 46CFR32.55-25(b) prior to the next cargo loading and not later than the compliance date.
Condition: Unknown
Due 7 November 1991
Resolved 7 November 1991
Construction/Loadline
Issued 17 August 1990
Resolved
AFTER OFFLOADING AND PRIOR TO RELOADING, MAKE PERMANENT REPAIRS TO THE 2" FRACTURE IN WAY OF THE #6 STARBOARD CARGO TANK LOCATED AT THE 9'6" DRAFT MARK.
Condition: Unknown
Due 17 August 1990
Resolved 17 August 1990
Deck/Cargo
Issued 29 October 1986
Resolved
CONDUCT OR SHOW PROOF OF ANNUAL CARGO PIPING AND RELIEF VALVE TEST PRIOR TO LOADING CARGO BUT NOT LATER THAN 07NOV86.
Condition: Unknown
Due 29 October 1986
Resolved 29 October 1986