MAURY USCG vessel records Sign in
← All vessels

VIRGINIA C II

VIRGINIA C II is a 1962 passenger vessel (inspected). The Coast Guard has recorded 65 inspections since 1985, most recently in August 2011, along with 138 deficiencies — 36 with no resolution recorded —.

Records from 1985 to 2011. Most recent: inspection, 26 August 2011.

Built
1962
Last inspected
26 August 2011
Documentation
No Operation - PM · documentation file of 10 September 2026
Controls
None recorded without a removal date

Identity

WT8034
Flag
UNITED STATES
367312260 (licence lapsed)
Maury page id
psix-44324

Inspections, by type

…with no type recorded12
…past their stated due date36
Years with a record 26 calendar years (1985–2011)
The 65 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

This record may be incomplete: the most recent inspection recorded for this vessel was 15 years ago. Maury shows what the Coast Guard recorded, not whether the vessel has been inspected since, is still in service, or what condition it is in. Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 1977.

Documentation record

Registered dimensions (L × B × D)85.0 ft × 21.4 ft × 7.8 ft
Registered tonnagegross 93 / net 63
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
Builderbuilder not recorded · BILOXI, MS, UNITED STATES · built 1962
Hull materialWood
PropulsionDiesel Reduction
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portBOSTON, MA
Trade endorsementsCoastwise, unrestricted
DocumentationNo Operation - PM · issued 30 June 2004
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it93 - Regulatory (Subpart C or D), Gross Ton
63 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.

Radio station licence

WT8034MMSI 367312260 · expired · compulsorily equipped · granted 7 September 2007, cancelled 30 December 2017 · licensed under a name not among this hull’s recorded names (not shown)
FCC Universal Licensing System ship-station file of 6 September 2026, matched to this hull on its US Official Number. Status and dates are the file’s own. The licensee is not read from the file and is not shown. A lapsed licence’s MMSI is still the number the vessel transmitted under while it was valid.

A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.

Inspection history · 65

26 August 2011 Annual Inspection · Administrative Inspection
Physical examination · Sector Boston · USCG Northeast District (CGD-NE) · Activity 4127678
20 July 2011 Drydock Extension
Administrative · Sector Boston · USCG Northeast District (CGD-NE) · Activity 4087994
30 March 2010 Type not recorded
No type recorded · Sector Boston · USCG Northeast District (CGD-NE) · Activity 3705649
11 September 2008 Annual Inspection
Physical examination · Sector Boston · USCG Northeast District (CGD-NE) · Activity 3322401
27 June 2007 Re-Inspection · Hull Examination
Physical examination · Sector Boston · USCG Northeast District (CGD-NE) · Activity 2975510
17 July 2006 Re-Inspection
Physical examination · Sector Boston · USCG Northeast District (CGD-NE) · Activity 2715683
23 June 2005 Hull Examination · COI Inspection
Physical examination · Sector Boston · USCG Northeast District (CGD-NE) · Activity 2400011
20 June 2005 MTSA Verification
Physical examination · Sector Boston · USCG Northeast District (CGD-NE) · Activity 2382553
6 July 2004 Re-Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 2122932
16 December 2003 Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1970584
21 July 2003 Re-Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1852610
10 June 2003 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1919748
3 December 2002 Drydock Extension
Administrative · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1713650
23 September 2002 Security Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1679560
25 June 2002 Re-Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1640113
25 July 2001 Re-Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1472938
7 June 2001 Deficiency Check · Hull Examination
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1401531
12 September 2000 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 659517
5 September 2000 Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 824789
3 July 2000 Deficiency Check · COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1470271
23 June 2000 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1440347
29 July 1999 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 6193
29 July 1999 Damage Survey
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1461216
15 June 1999 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1457664
19 May 1999 Hull Examination
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 798470
28 December 1998 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 225951
15 June 1998 Re-Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1130170
14 July 1997 Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 778462
30 June 1997 Re-Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 777262
19 June 1997 Hull Examination
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 776720
22 May 1997 Hull Examination · Drydock Extension
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1104336
22 August 1996 Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1090073
19 August 1996 Administrative
Administrative · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1132738
1 July 1996 Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1086347
14 June 1996 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 883934
20 November 1995 Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1186287
27 June 1995 Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1189407
14 June 1995 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1187906
30 May 1995 Hull Examination
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 880562
25 October 1994 Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 863186
13 June 1994 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1335897
5 August 1993 Administrative
Administrative · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1153697
18 June 1993 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 847235
24 May 1993 Hull Examination
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 829281
8 October 1992 Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1132391
9 September 1992 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 955064
19 August 1992 Excursion Permit
Administrative · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 940009
13 July 1992 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 950816
4 July 1992 Excursion Permit
Administrative · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 952764
22 April 1992 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 949053
16 April 1991 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1232554
5 April 1991 Hull Examination
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1220942
4 September 1990 Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1235334
13 April 1990 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1231798
29 March 1990 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1212964
3 April 1989 Hull Examination
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1032315
3 April 1989 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1210463
31 March 1989 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 890261
9 November 1988 Drydock Extension
Administrative · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 895512
1 April 1988 COI Inspection · Deficiency Check
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 992729
17 April 1987 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1022797
8 April 1987 Hull Examination
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 1330306
15 April 1986 COI Inspection
Physical examination · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 998676
16 April 1985 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 984037
4 April 1985 Type not recorded
No type recorded · MSO BOSTON · USCG Northeast District (CGD-NE) · Activity 984036

Deficiency record · 138

Construction/Loadline › Structures › End Bulkhead
Issued 26 August 2011 No resolution recorded
Collision bulkhead rotted, unserviceable at bilge suction piping penetration
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Sheerstrake
Issued 26 August 2011 No resolution recorded
-Hole in deck at shear plank on stbd side at collision bulkhead, rotted
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Deck Plating
Issued 26 August 2011 No resolution recorded
-Deck plywood sheeting rotted and delaminated from collision bulkhead to 3 frames forward of bulkhead
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Side Shell
Issued 26 August 2011 No resolution recorded
-Port side shear planking joint to deck rotted and open from collision bulkhead fwd to 4th frame
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Hull Plating
Issued 26 August 2011 No resolution recorded
-Shear plank port side 2nd frame from collision bulkhead holed, renew plank
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Sheerstrake
Issued 26 August 2011 No resolution recorded
-Shear plank port side Dutchman installed behind deck knee wall frame, remove Dutchman and renew plank
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Keel
Issued 26 August 2011 No resolution recorded
-Port and stbd side of stem, garboard plank soft and not flush at planking end joint to stem. Stbd side inset and sub-flush from stem. Both planks soft, possible rot.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Electrical › Electric Supply System (service) › Cable
Issued 26 August 2011 No resolution recorded
Stbd side frame 4 forward from collision bulkhead, circuit box unserviceable with broken cover, broken box, loosed wires, cabling loose, falling down and not serviceable
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › End Bulkhead
Issued 26 August 2011 No resolution recorded
-Cable penetration thru collision bulkhead not wt, repair collision bulkhead
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Girder
Issued 26 August 2011 No resolution recorded
-Delaminated and rotted deck planking at thru deck hatch framing, remove rotted decking to good wood
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Penetrations › Gasket
Issued 26 August 2011 No resolution recorded
-Wt hatch to forepeak not wt, loose and broken gasket, frozen deck hatch dogs, decking wood around hatch frame rotted, delaminated and non serviceable
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Engineering › Bilge Water Management System › Piping
Issued 26 August 2011 No resolution recorded
-Bilge suction reach rod rotted, broken and non serviceable
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Penetrations › Gasket
Issued 26 August 2011 No resolution recorded
-Forepeak deck vent wood box assemblies broken wood framing, rotted and split box joints, not weather tight
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Hull Plating
Issued 26 August 2011 No resolution recorded
Fwd lodge compartment -Port side shear plank rotted and holed extending from collision bulkhead aft to next bulkhead aft
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Hull Plating
Issued 26 August 2011 No resolution recorded
--Fwd lodge compartment Shear plank loose from deck and not wt. numerous cracks, breaks, splits and old concrete broken, split and falling out
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Deck Plating
Issued 26 August 2011 No resolution recorded
Fwd lodge compartment Plywood deck plating delaminated and soft extending from collision bulkhead to aft bulkhead and full beam of vessel
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Hull Plating
Issued 26 August 2011 No resolution recorded
-- Fwd lodge compartment Port side shear plank from collision bulkhead to aft bulkhead all split, connection to decking not made and open in numerous areas, further aft it gets from the collision bulkhead to the aft bulkhead the wider the gap gets. Beginning at collision to greater than 1" gap at rear bulkhead, deck joint not made and open. Numerous old fiberglass filler and old caulking failing
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Deck Plating
Issued 26 August 2011 No resolution recorded
All deck sheeting fully delaminated and soft in majority of accessible areas located immediately under existing delaminated FRP delaminated overlay
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Deck Plating
Issued 26 August 2011 No resolution recorded
Deck sheeting frame 4 to 7 aft of collision bulkhead soft and rotted
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Hull Plating
Issued 26 August 2011 No resolution recorded
Stbd side shear plank fully separated from deck sheeting, plank split, temp FRP fillers and repairs all unserviceable, renew shear plank from collision bulkhead to frame 7 aft of collision bulkhead
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Deck Plating
Issued 26 August 2011 No resolution recorded
From the port side to the starboard side at the shear strake, amidships, the deck is buckled up to ten inches and very spongy.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Deck Plating
Issued 26 August 2011 No resolution recorded
The deck house at main deck under the pilot house is collapsing due to rotted decking
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Deck Plating
Issued 26 August 2011 No resolution recorded
The entire second deck is rotting to point that no one should be allowed to walk on the deck. Mushrooms are growing out of the rotten areas.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Side Shell
Issued 26 August 2011 No resolution recorded
Auto body filler is being used to patch a lot of the rotten areas.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Superstructure
Issued 26 August 2011 No resolution recorded
The gunnels around the entire vessel is split and can no longer offer adequate support for the hand rail.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Transverse Bulkhead
Issued 26 August 2011 No resolution recorded
The collision bulkhead has numerous holes through it and is no longer water tight.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Hull › Hull Plating
Issued 26 August 2011 No resolution recorded
In the forward lodge space all along the shear strake the deck and side shell have separated and is no longer water tight.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Transverse Bulkhead
Issued 26 August 2011 No resolution recorded
In the forward lodge space the over head main deck supports are cracked and missing fasteners.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Lifesaving › Lifefloat › Lifeline
Issued 26 August 2011 No resolution recorded
Grab-lines on the aft group of life floats upper deck badly UV damaged
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Lifesaving › Lifefloat › Float-free Link
Issued 26 August 2011 No resolution recorded
Forward group of life floats was not connected to a painter and float-free link. A painter and link were provided, but not connected to the rafts. The lanyards connecting the rafts to each other were tangled but appeared to be rigged correctly; lines and splices were in fair condition.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Lifesaving › Lifefloat › Paddle
Issued 26 August 2011 No resolution recorded
One life float on the aft stack was missing paddles
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Lifesaving › Lifeboat Equipment › Electric Torch
Issued 26 August 2011 No resolution recorded
One water light on the middle life float stack was non-functioning.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Lifesaving › Buoyant Apparatus › Serviceable
Issued 26 August 2011 No resolution recorded
The BA atop the forward life float stack was in fair condition, with significant splitting and cracking.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Lifesaving › Lifejacket/PFD (Type I) › Quantity
Issued 26 August 2011 No resolution recorded
Condemned 5 adult life jackets. 183 passed, 1 compartment said to contain 35 not counted.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Electrical › Electric Supply System (service) › Cable
Issued 26 August 2011 No resolution recorded
Electrical wiring in pilothouse appeared to be in poor condition.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Construction/Loadline › Structures › Superstructure
Issued 26 August 2011 No resolution recorded
Condition of upper deck and railings fair. Deck was spongy, visibly delaminating in places, particularly the portside forward. Mushrooms were growing under the benches. Wire lifelines forming the lower rungs of the deck rails were loose.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 August 2011 — due date passed with no resolution recorded
Fire Fighting › Portable CO2 Fire Extinguisher › Mounting Bracket
Issued 11 September 2008 Resolved
Re-mount portable fire ext in void #2.
Due 24 September 2008
Resolved 11 October 2008
Resolution: mounted sat.
Engineering › Bilge Water Management System › Not Operational
Issued 11 September 2008 Resolved
Repair bigle pump float switch in engine room.
Due 24 September 2008
Resolved 2 July 2009
Resolution: Repaired and tested sat.
Construction/Loadline › Structures › Deck Plating
Issued 11 September 2008 Resolved
Crop and re-new with marine grade plywood the following areas- repalce plywwod deck IWO port aft 2nd deck two places and several places IWO the pilot house roof.
Due 29 June 2009
Resolved 29 June 2009
Resolution: Repaired sat.
Navigation › Collision/Grounding Avoidance › Radar
Issued 11 September 2008 Resolved
make repairs to rotten radar mount on pilot house roof.
Due 16 July 2009
Resolved 15 July 2010
Resolution: Radar mast repaired sat.
Communications › Radio Communications › EPIRB
Issued 11 September 2008 Resolved
repair or replace inop EPIRB.
Due 24 September 2008
Resolved 4 October 2008
Resolution: EPIRB repaired and tested sat.
Operations/Management › Lifesaving › Op Readiness/Maintenance/Inspection
Issued 11 September 2008 Resolved
Provide lifesaving equipment log.
Due 24 September 2008
Resolved 11 October 2008
Resolution: Provided sat.
Navigation › Piloting/Steering › Coast Guard Light List
Issued 11 September 2008 Resolved
Provide copies of light list, tide and current table, and coast pilot.
Due 24 September 2008
Resolved 29 June 2009
Resolution: all pubs provided sat.
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 11 September 2008 Resolved
repair loose navigation light brackets for both port and starboard running lights.
Due 24 September 2008
Resolved 2 July 2009
Resolution: Repaired sat.
Lifesaving › Buoyant Apparatus › Serviceable
Issued 11 September 2008 Resolved
repair rips and tears in BA.
Due 24 September 2008
Resolved 2 July 2009
Resolution: Repaired sat.
Lifesaving › Buoyant Apparatus › Lifeline
Issued 11 September 2008 Resolved
Renew rotted man lines and life lines on lifefloats, renew painter to weak link assembly.
Due 11 October 2008
Resolved 11 October 2008
Resolution: All man lines repaired sat.
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 11 September 2008 Resolved
Re-tighten anchor light mast stays on pilot house.
Due 16 July 2009
Resolved 15 July 2010
Resolution: Anchor light stay tightened.
Documentation › Certificates/Documents › Cargo Ship Safety Radio Certificate
Issued 17 July 2006 Resolved
provide safety radio certificate.
Due 31 July 2006
Resolved 1 August 2006
Resolution: Provided sat.
Accommodation/Occupational Safety › Occupational Safety › Deck Rail
Issued 17 July 2006 Resolved
Make permanent repairs to deck rail.
Due 17 July 2006
Resolved 1 August 2006
Resolution: Rail repair.
Engineering › Pressure Vessel › Maximum Allowable Working Pressure
Issued 23 June 2005 Resolved
Conduct a hydrostatic pressure test of vessel's air receiver in the presence of an Coast Guard Marine Inspector.
Condition: Unknown
Action required: 705 - Other - as specified
Due 23 August 2005
Resolved 23 August 2005
Engineering › Bilge Water Management System › Manifold
Issued 6 July 2004 Resolved
Provide line diagram for bilge system.
Action required: 705 - Other - as specified
Due 2 March 2005
Resolved 23 June 2005
Construction/Loadline › Hull
Issued 10 June 2003 Resolved
Clean and ream loose caulking and recaulk
Action required: 705 - Other - as specified
Due 10 June 2003
Resolved 10 June 2003
Construction/Loadline › Hull
Issued 10 June 2003 Resolved
Fill areas as marked on the stem, keel midship starboard area.
Action required: 705 - Other - as specified
Due 10 June 2003
Resolved 10 June 2003
Construction/Loadline › Penetrations
Issued 10 June 2003 Resolved
Rebolt rudder assemblies port and starboard sides.
Action required: 705 - Other - as specified
Due 10 June 2003
Resolved 10 June 2003
Engineering › Sea-water System (primary cooling)
Issued 10 June 2003 Resolved
Clean and reassemble all sea vales.
Action required: 705 - Other - as specified
Due 10 June 2003
Resolved 10 June 2003
Accommodation/Occupational Safety › Occupational Safety
Issued 10 June 2003 Resolved
Refasten ladder rung in lazarette.
Action required: 705 - Other - as specified
Due 21 July 2003
Resolved 21 July 2003
Engineering › Fuel Oil Service System
Issued 10 June 2003 Resolved
Repair or replace fuel oil valve for day tank in Lazarette.
Action required: 705 - Other - as specified
Due 21 July 2003
Resolved 21 July 2003
Engineering › Fuel Oil Service System
Issued 10 June 2003 Resolved
Replace fuel supply hose for center fuel tank in lazarette.
Action required: 705 - Other - as specified
Due 21 July 2003
Resolved 21 July 2003
Construction/Loadline › Hull
Issued 10 June 2003 Resolved
Crop and renew the 4th plank downward from the gunwale approximately 25' section located on the starboard side.
Action required: 705 - Other - as specified
Due 21 July 2003
Resolved 21 July 2003
Engineering › Fuel Oil Storage/Transfer System
Issued 25 June 2002 Resolved
Renew flexible hose fill line to center fuel tank in the steering compartment.
Due 15 July 2002
Resolved 11 July 2002
Electrical › Electrical Distribution System (service)
Issued 25 June 2002 Resolved
Renew circuit breaker box to anchor windlass along with wiring in the forepeak compartment.
Due 15 July 2002
Resolved 11 July 2002
Construction/Loadline › Hull
Issued 25 June 2002 Resolved
Re-caulk sheer strake port and starboard along the main deck and caulk additional areas in the forepeak and the aft lodge starboard.
Due 15 July 2002
Resolved 11 July 2002
Electrical › Electrical Distribution System (service)
Issued 25 June 2002 Resolved
Hard wire freshwater pump in the after engine room.
Due 15 July 2002
Resolved 11 July 2002
Engineering › Compressed Air System (start air)
Issued 25 June 2002 Resolved
Refasten foundation for air compressor inboard in the engine room.
Due 15 July 2002
Resolved 11 July 2002
Construction/Loadline › Hull
Issued 25 June 2002 Resolved
Dry-dock vessel and make repair to leaking keel cooler backing block stbd 10th frame aft lodge compartment; aslo examine bolts in port and starboard rudder post assemblies.
Due 15 July 2002
Resolved 11 July 2002
Resolution: A TEMPORARY BACKING BLOCK HAS BEEN INSTALLED, NO LEAKAGE HOWEVER, BLOCK MUST BE EXAMINED MONTHLY UNTIL VESSEL IS DRYDOCKED (11/30/2002) WHEN A PERMANENT BLOCK WILL BE INSTALLED.
Construction/Loadline
Issued 7 June 2001 Resolved
Provide recommendation from a wood boat carpenter concerning rot found on top 1 1/2 inches of transom deck beam.
Condition: Unknown
Due 30 June 2001
Resolved 9 July 2001
Documentation
Issued 3 July 2000 Resolved
Provide a current FCC Safety Radiotelephone Certificate.
Condition: Unknown
Due 3 July 2000
Resolved 3 July 2000
Lifesaving
Issued 30 June 1997 Resolved
PROVIDE EPIRB IN A FLOAT-FREE ARRANGEMENT. VESSEL'S OPERATION IS LIMITED TO NON-HIGH SEAS VOYAGES UNTIL REQUIREMENT IS SATISFIED.
Condition: Unknown
Due 7 July 1997
Resolved 14 July 1997
Construction/Loadline
Issued 19 June 1997 Resolved
REPLACE THE FOLLOWING PLANKS: PORT SIDE-SHEER STRAKE IN WAY OF #9-#11 RAILSTANCHIONS; STBD SIDE-2ND BELOW SHEER, LAST PLANK AFT/1ST BELOW SHEER IN WAY OF #8-#10 RAIL STANCHIONS/4TH BELOW SHEER IN WAY OF #9 RAIL STANCHION TO BUTT.
Condition: Unknown
Due 27 June 1997
Resolved 30 June 1997
Accommodation/Occupational Safety
Issued 19 June 1997 Resolved
REPAIR BOTH PORT AND STBD RAILS AT AFT CORNERS, MAIN DECK.
Condition: Unknown
Due 27 June 1997
Resolved 30 June 1997
Construction/Loadline
Issued 19 June 1997 Resolved
PAINT DRAFT MARKS IN COLOR CONTRASTING TO HULL.
Condition: Unknown
Due 27 June 1997
Resolved 30 June 1997
Accommodation/Occupational Safety
Issued 19 June 1997 Resolved
REPAIR STBD AFT CORNER RAIL, 2ND DECK.
Condition: Unknown
Due 27 June 1997
Resolved 30 June 1997
Accommodation/Occupational Safety
Issued 19 June 1997 Resolved
REPAIR RAIL AT TOP OF AFT LADDER TO 2ND DECK.
Condition: Unknown
Due 27 June 1997
Resolved 30 June 1997
Lifesaving
Issued 14 June 1996 Resolved
BOUYANT APPARATUS PAINTER CANISTER OBSTRUCTING FREE RELEASE OF PAINTER. MODIFY OR RENEW PAINTER CONTAINER TO ALLOW FREE PAYING OUT OF PAINTER AND FLOAT FREE RELEASE OF BOUYANT APPARATUS.
Condition: Unknown
Due 1 July 1996
Resolved 1 July 1996
Lifesaving
Issued 14 June 1996 Resolved
RENEW DETERIORATED/MISSING BECKETS FOR LIFE FLOATS. LIGHT TO BE REPAIRED AS ORIGINAL.
Condition: Unknown
Due 1 July 1996
Resolved 1 July 1996
Fire Fighting
Issued 14 June 1996 Resolved
RENEW CRUSHED/BUCKLED DRYCHEM DISCHARGE HOSE. EXTINGUISHER LOCATED OUTSICDE THE Galley
Condition: Unknown
Due 1 July 1996
Resolved 1 July 1996
Accommodation/Occupational Safety
Issued 14 June 1996 Resolved
LADDER HAND RAIL, MAIN DECK TO UPPER DECK LOOSE, NOT PROPERLY FASTENED. PROPERLY SECURE STAIR HAND RAIL LEADING FROM MAIN DECK TO UPPER DECK.
Condition: Unknown
Due 1 July 1996
Resolved 1 July 1996
Accommodation/Occupational Safety
Issued 14 June 1996 Resolved
WOODEN RESCUE LADDER RAIL CRACKED.
Condition: Unknown
Due 19 June 1996
Resolved 19 June 1996
Fire Fighting
Issued 14 June 1996 Resolved
PORT FIRE PUMP INOP. TROUBLE SHOOT, MAKE PERMANENT REPAIR AND PROVE PROPEROPERATION OF FIRE PUMP.
Condition: Unknown
Due 14 July 1996
Resolved 19 June 1996
Unknown
Issued 14 June 1996 Resolved
FORE PEAK VENT ROTTEN. REMOVE ROTTED AREA TO SOUND WOOD AND RENEW AS ORIGINAL.
Condition: Unknown
Due 1 July 1996
Resolved 1 July 1996
Engineering
Issued 14 June 1996 Resolved
PROVIDE FLAME SCREENS OF PROPER MESS SIZE FOR FUEL TANK VENTS. THE SCREEN SHALL CONSIST OF CORROSION RESISTANT WIRE OF A TLEAST 30X30 MESS IN ACCORDANCE WITH 46CFR182.20-35(d)
Condition: Unknown
Due 1 July 1996
Resolved 1 July 1996
Lifesaving
Issued 14 June 1996 Resolved
OIL AND OIL/WATER ACCUMULATION IN ENGINE ROOM BILGES DEPTH APPROXIMATELY 5 INCHES MEASURED AT FWD BULKHEAD. CLEAN OIL FROM ENGINE ROOM BILGE.
Condition: Unknown
Due 14 June 1996
Resolved 14 June 1996
Navigation
Issued 14 June 1996 Resolved
NAV LIGHT SOCKETS ADRIFT IN FIXTURE AND CABLE PENETRATION NOT PROPER._x001C_ RENEW OR REPAIR NAV LIGHT FIXTURES AS ORIGINAL. LIGHT ARE TO BE IN COMPLIANCE WITH UL LISTING.
Condition: Unknown
Due 1 July 1996
Resolved 1 July 1996
Electrical
Issued 14 June 1996 Resolved
SHORE TIE INDICATORS LAMP UNIT MISSING BULB AND LENS COVER. RENEW INDICATOR LAMP AND LENS AS ORIGINAL.
Condition: Unknown
Due 1 July 1996
Resolved 1 July 1996
Construction/Loadline
Issued 14 June 1995 Resolved
PROVE WATERTIGHT THE FOREPEAK AND LAZARETTE WEATHERDECK HATCHES.
Condition: Unknown
Due 14 June 1995
Resolved 14 June 1995
Unknown
Issued 30 May 1995 Resolved
MAKE VESSEL AVAILABLE FOR UNDERWAY EXAMINATION PRIOR TO CARRYING PASSENGERSAND UPON COMPLETION OF HULL REPAIRS._x001C_
Condition: Unknown
Due 26 June 1995
Resolved 26 June 1995
Accommodation/Occupational Safety
Issued 30 May 1995 Resolved
REPLACE FRACTURED WINDOW IN AFT SALON DOOR.
Condition: Unknown
Due 26 June 1995
Resolved 26 June 1995
Construction/Loadline
Issued 30 May 1995 Resolved
RENEW UPPER MOST PLANK AND DETERIORATED BULWARK KING POST ON PORT SIDE FORWARD (FOREPEAK).
Condition: Unknown
Due 30 May 1995
Resolved 30 May 1995
Construction/Loadline
Issued 30 May 1995 Resolved
RENEW FRACTURED PLANK AS MARKED DURING INSPECTION ON THE PORT SIDE FORWARD OF AMIDSHIPS (#15 PLANK).
Condition: Unknown
Due 26 June 1995
Resolved 26 June 1995
Construction/Loadline
Issued 30 May 1995 Resolved
#2 COMPARTEMNT-PORT SIDE-INSIDE AFT STORAGE LOCKER, REPLACE DETERIORATING UPPER MOST PLANK.
Condition: Unknown
Due 30 May 1995
Resolved 30 May 1995
Construction/Loadline
Issued 30 May 1995 Resolved
RENEW DETERIORATED SECTION ON BULWARK CAP ON AFT STARBOARD CORNER OF MAIN DECK.
Condition: Unknown
Due 26 June 1995
Resolved 26 June 1995
Construction/Loadline
Issued 30 May 1995 Resolved
COMPLETE DECK REPAIRS ON THE PORT SIDE AMIDSHIPS AT BOARDING GATE, AREA SURROUNDING FORE PEAK HATCH, STARBOARD SIDE AT FORWARD END OF DECK HOUSE, AREA OUTSIDE OF FORWARD SALON DOOR ON STARBOARD SIDE AND UPPER DECK AFT OF STAIRCASE TO UPPER DECK.
Condition: Unknown
Due 26 June 1995
Resolved 26 June 1995
Lifesaving
Issued 13 June 1994 Resolved
REPLACED 8 ADULT, 3 CHILD PFD'S.
Condition: Unknown
Due 13 June 1994
Resolved 23 June 1994
Documentation
Issued 13 June 1994 Resolved
PROVIDE COPY OF VALID FCC RADIOTELEPHONY CERTIFICATE.
Condition: Unknown
Due 13 June 1994
Resolved 13 June 1994
Fire Fighting
Issued 13 June 1994 Resolved
REPLACED 3 PORTABLE CO2 FIRE EXTINGUISHERS.
Condition: Unknown
Due 13 June 1994
Resolved 23 June 1994
Fire Fighting
Issued 13 June 1994 Resolved
REPLACED MISSING 5 GALLON PER MINUTE HAND PUMP.
Condition: Unknown
Due 13 June 1994
Resolved 23 June 1994
Accommodation/Occupational Safety
Issued 18 June 1993 Resolved
MAKE VESSEL FRESH POTABLE WATER SYSTEM OPERATIONAL.
Condition: Unknown
Due 18 June 1993
Resolved 24 June 1993
Construction/Loadline
Issued 18 June 1993 Resolved
MAKE NECESSARY REPAIRS TO FORPEAK AND LAZARETTE WATERTIGHT HATCHES SO AS TOPROVE WATERTIGHT.
Condition: Unknown
Due 18 June 1993
Resolved 24 June 1993
Lifesaving
Issued 18 June 1993 Resolved
REPLACE LIFE LINES N ONE 20 MAN BUOYANCY APPARATUS.
Condition: Unknown
Due 18 June 1993
Resolved 24 June 1993
Fire Fighting
Issued 18 June 1993 Resolved
REPAIR/REPLACE LOVE JOY COUPLINGS ON BOTH VESSEL FIRE PUMPS.
Condition: Unknown
Due 18 June 1993
Resolved 24 June 1993
Construction/Loadline
Issued 18 June 1993 Resolved
MAKE VESSEL AVAILABLE FOR UNDERWAY TRIALS AND GET VESSEL UNDERWAY FOR OBSERVATION.
Condition: Unknown
Due 18 June 1993
Resolved 24 June 1993
Electrical
Issued 18 June 1993 Resolved
PROVE PROPER OPERATION OF BOTH SHIPS SERVICE GENERATORS AND ALL THREE PHASEMOTORS BILGE/WINCH/AIR COMPRESSOR.
Condition: Unknown
Due 18 June 1993
Resolved 24 June 1993
Construction/Loadline
Issued 24 May 1993 Resolved
REPLACE SEVEN OUTER PLANKS ON SIDE SHELL.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Construction/Loadline
Issued 24 May 1993 Resolved
MAKE PERMANENT REPAIR TO PORT QTR RUTS RAIL.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Accommodation/Occupational Safety
Issued 24 May 1993 Resolved
MAKE PERMENANT REPAIR TO SUPPORT FLANGES NO BASE OF LADDER LEADING TO UPPERDECK.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Construction/Loadline
Issued 24 May 1993 Resolved
MAKE PERMANENT REPAIR TO TWO FRACTURED FRAMES PORT QTR IN LAZARETTE.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Construction/Loadline
Issued 24 May 1993 Resolved
MAKE PERMANENT REPAIRS TO ONE FRACTURED FRAME PORT SIDE ENGINE ROOM.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Construction/Loadline
Issued 24 May 1993 Resolved
MAKE PERMANENT REPAIRS TO ROTTEN SISTERED DECK BEAM ENGINE ROOM IN WAY OF PORT ENGING MUFFLERS.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Construction/Loadline
Issued 24 May 1993 Resolved
REPLACE FAIRING PIECE ON STBD STRUT.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Construction/Loadline
Issued 24 May 1993 Resolved
REFASTEN AREAS OF OUTER PLANING AS MARKED DURING WALK AROUND INSPECTION.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Engineering
Issued 24 May 1993 Resolved
MAKE SHIPS SERVICE AIR RECIEVER AVAILABLE FOR HYDROSTATIC TEST.
Condition: Unknown
Due 25 May 1993
Resolved 25 May 1993
Accommodation/Occupational Safety
Issued 24 May 1993 Resolved
OPEN FOR EXAMINATION SANITARY PUMP RAW WATER SEA SUCTION VALVE.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Construction/Loadline
Issued 24 May 1993 Resolved
REFASTEN WORM SHOE ENTIRE LENGTH OF KEEL.
Condition: Unknown
Due 26 May 1993
Resolved 26 May 1993
Construction/Loadline
Issued 8 October 1992 Resolved
REPAIR OR REPLACE FRACTURED AND HOLDED FRP COVERING IN WAY OF MAIN AND 01 DECKS AND PROVE DECKS TIGHT ON OR BEFORE NEXT DRYDOCK SCHEDULED MAY 93 AND PRIOR TO PLACING VESSEL IN OPERATION.
Condition: Unknown
Due 8 October 1992
Resolved 8 October 1992
Construction/Loadline
Issued 22 April 1992 Resolved
CLEAN OR REPLACE GASKET AT WATERTIGHT DOOR AT FRAME 29.
Condition: Unknown
Due 23 June 1992
Resolved 23 June 1992
Lifesaving
Issued 22 April 1992 Resolved
PROVIDE ADDITIONAL 15 ADULT LIFEPRESERVERS AND 1 CHILD LIFE PRESERVER. UNTIL SUCH TIME, TOTAL PERSONS ALLOWED IS REDUCED TO 203 ADULTS AND 21 CHILDREN.
Condition: Unknown
Due 27 May 1992
Resolved 2 June 1992
Construction/Loadline
Issued 22 April 1992 Resolved
PROVIDE PROPOSAL FOR RENEWAL OF MAIN DECK PLYWOOD WHERE WASTED.
Condition: Unknown
Due 23 June 1992
Resolved 23 June 1992
Construction/Loadline
Issued 22 April 1992 Resolved
REMOVE SHEATHING AND DECKS TO SATISFACTION OF AN ATTENDING MARINE INSPECTORTO PERMIT COMPLETE AND THOROUGH EXAMINATION OF VESSELS HULL STRUCTURE.
Condition: Unknown
Due 22 April 1992
Resolved 22 April 1992
Electrical
Issued 22 April 1992 Resolved
RESECURE ELECTRIC VENT IN ENGINE ROOM, STARBOARD SIDE AFT.
Condition: Unknown
Due 23 June 1992
Resolved 23 June 1992
Lifesaving
Issued 22 April 1992 Resolved
PROVIDE AND SECURE ADDITIONAL PADDLE FOR EACH LIFEFLOAT.
Condition: Unknown
Due 23 June 1992
Resolved 23 June 1992
Lifesaving
Issued 22 April 1992 Resolved
REPAIR LIFELINE ON 12 MAN BUOYANT APPARATUS.
Condition: Unknown
Due 23 June 1992
Resolved 23 June 1992
Lifesaving
Issued 22 April 1992 Resolved
REPAIR/RESECURE SECTION OF RAIL ON UPPER DECK ADJACENT TO LIFEFLOAT STORAGE.
Condition: Unknown
Due 23 June 1992
Resolved 23 June 1992
Construction/Loadline
Issued 22 April 1992 Resolved
INSTALL STRAINER IN LOWER AFT LODGE BILGE SUCTION.
Condition: Unknown
Due 23 June 1992
Resolved 23 June 1992
Fire Fighting
Issued 4 September 1990 Resolved
RESERVICE FIXED CO2 FIRE FIGHTING SYSTEM.
Condition: Unknown
Due 4 September 1990
Resolved 4 September 1990
Construction/Loadline
Issued 4 September 1990 Resolved
MAKE PERMANENT REPAIRS TO DAMAGED UNDERDECK BEAMS AND ASSOCIATED MEMBERS INWAY OF AFT ENGINE ROOM PORT.
Condition: Unknown
Due 4 September 1990
Resolved 4 September 1990
Engineering
Issued 4 September 1990 Resolved
REPAIR PORT MUFFLER AND RELAG INCLUDING ALL EXHAUST PIPING.
Condition: Unknown
Due 4 September 1990
Resolved 4 September 1990
Electrical
Issued 4 September 1990 Resolved
RENEW DAMAGED WIRING FROM STARBOARD SUPPLY BLOWER.
Condition: Unknown
Due 4 September 1990
Resolved 4 September 1990
Lifesaving
Issued 1 April 1988 Resolved
PROVIDE 2 CHILD AAND 40 ADULT TYPE 1 CG APPROVED PFD'S
Condition: Unknown
Due 1 April 1988
Resolved 1 April 1988
Lifesaving
Issued 1 April 1988 Resolved
REFURBUSH 2, 12 PERS. L/FLOATS RENEW LINES AND NETTING
Condition: Unknown
Due 1 April 1988
Resolved 1 April 1988
Fire Fighting
Issued 1 April 1988 Resolved
REPAIR/REPLACE FIRE MAIN PRESS. GAUGES (2)EA.
Condition: Unknown
Due 1 April 1988
Resolved 1 April 1988
Fire Fighting
Issued 1 April 1988 Resolved
REPAIR STBD FIRE PUMP. (PUMP HAS EXCESSIVE LEAKAGE)
Condition: Unknown
Due 1 April 1988
Resolved 1 April 1988
Fire Fighting
Issued 1 April 1988 Resolved
PROVIDE TWO ADDITIONAL BII FIRE EXTINGUISHERS IN ACCOMMADATION SPACE UNTIL FIRE PUMP IS CAPABLE OF PRODUCING 50 GALLONS PER MINUTE AT A PRESSURE NOT LESS THAN 60 PSI AS PER 46CFR 181.10-1 (C). THE FIRE PUMP SHALL MEET AFOREMENTIONED REQMT. NO LATER THAN 08OCT88.
Condition: Unknown
Due 1 April 1988
Resolved 1 April 1988
Fire Fighting
Issued 17 April 1987 Resolved
HAVE FIXED CO2 SYSTEM SERVICED AND PROVIDE TEST REPORT
Condition: Unknown
Due 17 April 1987
Resolved 17 April 1987
Construction/Loadline
Issued 15 April 1986 Resolved
FREE-UP BILGE VALVE FORWARD OF COLLISION BULKHEAD
Condition: Unknown
Due 15 April 1986
Resolved 15 April 1986
Fire Fighting
Issued 15 April 1986 Resolved
SERVICE FIXED CO2 SYSTEM
Condition: Unknown
Due 15 April 1986
Resolved 15 April 1986
Engineering
Issued 15 April 1986 Resolved
SECURE MOUNTING OF INBOARD COMPRESSOR
Condition: Unknown
Due 15 April 1986
Resolved 15 April 1986
Fire Fighting
Issued 15 April 1986 Resolved
INSTALL GUAGES ON FIRE PUMPS
Condition: Unknown
Due 15 April 1986
Resolved 15 April 1986
Engineering
Issued 15 April 1986 Resolved
REPAIR VALVE ON STBD FUEL TANK
Condition: Unknown
Due 15 April 1986
Resolved 15 April 1986

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.