Records from 1997 to 2016. Most recent: inspection, 22 March 2016.
Documentation record
Registered dimensions (L × B × D)240.9 ft × 56.0 ft × 18.8 ft
Registered tonnagegross 2,043 / net 908
ITC dimensions (L × B × D)240.9 ft × 56.0 ft × 18.8 ft
ITC tonnagegross 2,043 / net 908
BuilderNORTH AMERICAN SHIPBLDG · LAROSE, LA, UNITED STATES · built 1997
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portGALLIANO, LA
Trade endorsementsCoastwise, unrestricted, Registry
DocumentationValid · issued 20 January 2026 · expires 28 February 2027
Service, as the file records itOffshore Supply Vessel
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it2043 - Convention (Subpart B), Gross Ton
908 - Convention (Subpart B), Net Ton
2729 - Dead Weight, Ton
1882 - Displacement, Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 32
22 March 2016
Annual Inspection · Administrative Inspection
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 5838473
10 June 2014
Annual Inspection · Administrative Inspection · Deficiency Check
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 4884037
21 May 2012
COI Inspection · MTSA Verification
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4318133
16 July 2011
Annual Inspection
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 4083363
11 January 2011
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3928634
23 February 2010
Hull Examination · Internal Structural Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3684184
24 July 2008
Re-Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3304666
11 July 2008
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3264766
24 June 2008
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3246472
28 June 2007
Re-Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2976833
1 May 2007
Examination of Repairs · Cargo Tank Internal · Internal Structural Exam · Hull Examination
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2920795
11 September 2006
Re-Inspection · In-Service Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2775811
7 March 2006
Internal Structural Exam · Examination of Repairs · Hull Examination · Cargo Tank Internal · Administrative Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2597658
26 September 2005
Security Plan Amendment Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 2501593
20 July 2005
Re-Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2433039
23 June 2005
MTSA Verification
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2400400
16 February 2005
Security Plan Amendment Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 2293940
14 October 2004
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2220632
16 July 2004
Re-Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 2135217
2 December 2003
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 1957294
3 November 2003
Security Plan Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 1979508
15 May 2003
Cargo Tank Internal · COI Inspection · Hull Examination · Inclining Experiment · Internal Structural Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 1712917
24 April 2002
Re-Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 1608408
11 April 2002
Hull Examination
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 1603453
10 July 2001
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1068516
23 April 2001
COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1413920
20 April 2000
Re-Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1404961
18 April 2000
Hull Examination
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1361416
29 April 1999
COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1462753
3 June 1998
Re-Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1421522
30 April 1997
Hull Examination · Initial Certification
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1439855
18 April 1997
Deadweight Survey
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1106509
Engineering › Diesel Engine (auxiliary) › Nozzle, Injection (fuel injection)
Issued 10 June 2014
Resolved
Fuel injection line brackets missing.
Due 24 June 2014
Resolved 24 June 2014
Resolution: Tech rep installed factory required fuel line brackets
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 10 June 2014
Resolved
Three pump shaft guards not properly secured.
Due 24 June 2014
Resolved 24 June 2014
Resolution: All shaft guards properly secured.
Accommodation/Occupational Safety › Occupational Safety › Guards for Exposed Hazards
Issued 10 June 2014
Resolved
Generator exhuast had unlagged areas.
Due 10 July 2014
Resolved 24 June 2014
Resolution: All exhaust lagging installed. Exhuast piping adequately guarded.
Construction/Loadline › Structures › Scuttle
Issued 10 June 2014
Resolved
Engine room egress scuttle no watertight
Due 10 July 2014
Resolved 24 June 2014
Resolution: The scuttle was adjusted and found to be functioning and water tight.
Engineering › Generator (propulsion-electric) › Wiring
Issued 16 July 2011
Resolved
Visual alarm for overspeed on all three generators on MN switchboard in operable
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 10 August 2011
Resolved 11 August 2011
Resolution: Cleared by ABS surveyor Joesph
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 16 July 2011
Resolved
Audible alarm found inoperable
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 10 August 2011
Resolved 11 August 2011
Resolution: Cleared by ABS surveyor
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 24 July 2008
Resolved
Provide third party certificate that shows proper operation of OWS alarm, sensor and overboard valve.
Action required: 705 - Other - as specified
Due 24 October 2008
Resolved 18 August 2008
Pollution Prevention/Response › Prevention Equipment › Fixed Containment
Issued 11 September 2006
Resolved
Install correct sized fixed containment for "E" Generator fuel vent and both Hydraulic steering vent prior to next Dry-dock.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Due 30 May 2008
Resolved 28 June 2007
Resolution: Containment installed.
Operations/Management › Vessel Safety Management › Maintenance of Ship/Equipment
Issued 11 September 2006
Resolved
Provide Automation test procedure for Steering Deviation alarm.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Due 30 May 2008
Resolved 29 June 2009
Engineering › Bilge Water Management System › Valve
Issued 11 September 2006
Resolved
Install Forepeak remote valve wrench at the remote location.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Due 21 October 2006
Resolved 28 June 2007
Resolution: Wrench installed.
Communications › Internal Communications System › Sound-powered Telephone
Issued 24 April 2002
Resolved
PROPERLY INSTALL/REPAIR "Z" DRIVE COMPT SPP VISUAL CALL INDICATOR TO OPERATE UNDER NORMAL POWER, AND AUDIBLE / VISUAL CALL INDICATOR TO OPERATE UNDER EMERG POWER
Condition: Improper Installation
Due 24 April 2002
Resolved 24 April 2002
Lifesaving › Inflatable Liferafts › Painter
Issued 24 April 2002
Resolved
PROPERLY RIG LIFERAFT PAINTERS TO ENSURE A TANGLE FREE RELEASE
Condition: Improper Installation
Action required: 17 - Rectify deficiencies prior to departure
Due 24 April 2002
Resolved 24 April 2002
Engineering › Bilge Water Management System › Valve
Issued 24 April 2002
Resolved
REPAIR STRIPPED REACH ROD FOR UPPER FOREPEAK BILGE SUCTION LINE
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 24 April 2002
Resolved 24 April 2002
Navigation
Issued 23 April 2001
Resolved
Demonstrate proper operation of depth recording device to the satisfaction of the attending marine inspector.
Condition: Unknown
Due 23 April 2001
Resolved 23 April 2001
Documentation
Issued 18 April 2000
Resolved
Provide approved plans for modifications to liquid mud transfer system/piping. Addition of liquid mud priming pump._x001C_ Provide vessel with updated/correct drawing.
Condition: Unknown
Due 18 May 2000
Resolved 24 April 2002
Resolution: SIGHTED APPROVED PLANS WITH LETTER FROM MSC DTD 6 JUN 2000.
Engineering
Issued 29 April 1999
Resolved
DEMONSTRATE PROPER OPERATION OF ENGINEERING AUTOMATED CONTROL AND MONITORING SYSTEM IAW 46 CFR 130.400 TO THE SATISFACTION OF ATTENDING MARINE INSPECTOR.
Condition: Unknown
Due 29 April 1999
Resolved 29 April 1999
Deck/Cargo
Issued 30 April 1997
Resolved
Demonstrate local manual operation of liquid mud system power actuated valves in accordance with Title 46 Code of Federal Regulations Subpart 56.50-60(d)(1).
Condition: Unknown
Due 30 April 1997
Resolved 30 April 1997